HomeMy WebLinkAboutFIN 11-25Report to Council
Report Number: FIN 11-25
Date: June 23, 2025
From: Stan Karwowski
Director, Finance & Treasurer
Subject: Ontario Transfer Payment Amending Agreement for the Building Faster
Fund
File: F-4910-011
Recommendation:
1.That Report FIN 11-25 regarding the amendment to Ontario Transfer Payment
Agreement with the Province of Ontario be received;
2.That the Mayor and City Clerk be authorized to execute the amended Ontario
Transfer Payment Agreement with the Province of Ontario for the Building Faster
Fund; and
3.That the appropriate City of Pickering officials be given authority to take the
necessary actions to give effect thereto.
Executive Summary: The purpose of this report is to authorize the execution of the
Building Faster Fund (BFF) amended Transfer Payment Agreement (TPA) with the
Province of Ontario. The program’s original end date was March 31, 2026 and it is now
being extended to March 31, 2028.
The BFF is a provincial performance-based funding program established in 2023 to
support municipalities in addressing housing supply challenges. The program awards
funding based on a municipality’s progress toward annual housing targets.
Relationship to the Pickering Strategic Plan: The recommendations in this report
respond to the Pickering Strategic Plan Corporate Key: Good Governance/Customer
Service Excellence.
Financial Implications: The City of Pickering has been allocated $5.2 million for
year 2 of the program, with total BFF funding of $10.4 million to date. (The City also
received $5.2 million in 2024). The 2025 Capital Budget anticipated the City receiving
these grant dollars and these dollars have been mainly allocated to the 2025 road re-
surfacing program.
Discussion: The purpose of this report is to authorize the execution of the BFF
amended TPA with the Province of Ontario. A key change to the program is the
FIN 11-25 June 23, 2025
Page 2
_____________________________________________________________________
extension of the end date from March 31, 2026, to March 31, 2028. This means that
recipients will have until March 31, 2028 (an additional two years) to spend program
funds earned from Years 1, 2, or 3 (based on performance in 2023, 2024, and 2025,
respectively).
The BFF is a provincially funded program established in 2023 designed to incentivize
municipalities to tackle housing supply issues, by providing performance -based funding
for housing and community infrastructure, based on meeting its provincially assigned
housing targets.
It is a three-year program that will provide $400 million per year to municipalities that
have achieved 80% or more of their annual housing targets. The funds are awarded
based on the percentage of the housing targets met, with bonuses for exceeding the
target (up to a maximum of 25% over target).
As communicated by the Ministry of Municipal Affairs and Housing, the City of Pickering
has qualified for $5.2 million for Year 2 of the program based on its 2024 performance.
Inclusive of 2024, the City has been granted $10.4 million that have been applied to
projects that contribute to towards meeting the housing targets.
The purpose of this report is to seek Council’s authorization for the Mayor and City
Clerk to execute the amended TPA, which is due to the Province of Ontario no later
than June 27, 2025.
Attachment:
1.Ontario Transfer Payment Amending Agreement for the Building Faster Fund
Prepared By: Approved/Endorsed By:
Raghu Kumar, CPA,CMA Stan Karwowski, CPA, CMA, MBA
Senior Financial Analyst, Director, Finance & Treasurer
Development Charges & Capital
Management
Original Signed By:Original Signed By:
FIN 11-25 June 23, 2025
Page 3
_____________________________________________________________________
Recommended for the consideration
of Pickering City Council
Marisa Carpino, M.A.
Chief Administrative Officer
Original Signed By:
1
ONTARIO TRANSFER PAYMENT AMENDING AGREEMENT
for the Building Faster Fund
This Amending Agreement No.1 effective as of the 1st day of January, 2025.
B E T W E E N :
HIS MAJESTY THE KING IN RIGHT OF ONTARIO
as represented by the Minister of Municipal Affairs and
Housing
(the “Province”)
-and –
[enter the full legal name of the Recipient above]
(the “Recipient”)
BACKGROUND
1.The Province and the Recipient entered into an Ontario Transfer Payment
Agreement for the Building Faster Fund effective as of the 1st day of April, 2024
(the “Agreement”).
2.The Parties wish to extend the Agreement to June 30, 2028.
3.The Parties wish to otherwise amend the Agreement in the manner set out in this
Amending Agreement No.1.
IN CONSIDERATION of the mutual covenants and agreements contained herein, and
for other good and valuable consideration, the receipt and sufficiency of which are
hereby acknowledged, the Parties hereto agree as follows:
1.Capitalized terms used but not defined in this amending agreement No.1 (the
“Amending Agreement No.1”) have the meanings ascribed to them in the
Agreement.
Attachment 1 to Report FIN 11-25
2
2. Section A1.2 of Schedule “A” is amended by adding the following definition in
alphabetical order:
“Additional Reporting Period” means the period commencing on January 1,
2027 and ending on March 31, 2028.
3. Section A1.2 of Schedule “A” is amended by replacing the definition of
“Investment Plan” with the following definition:
“Investment Plan” means an investment plan identifying the Recipient’s
proposed use of Funds in a form to be provided by the Province.
4. The definition of “Program Year” in Section A1.2 of Schedule “A” is amended by
adding the following new clause (c) after clause (b):
(c) in the case of the third Program Year, the period commencing on
January 1, 2026 and ending on December 31, 2026.
5. Section A4.7 of Schedule “A” is deleted and replaced with the following:
A4.7 Saved Funds. The Recipient may save any Funds that it receives in
one Program Year for use in a later Program Year or in the Additional
Reporting Period. For greater certainty, saved Funds include Funds not
committed and not spent, Funds committed but not spent, and any
interest earned pursuant to section A4.4. Despite anything else in this
Agreement, the Recipient will spend any Funds that it has saved by no
later than March 31, 2028. In the event that the Recipient does not
spend those saved Funds in accordance with the requirements set out
in this section A4.7 or otherwise in accordance with the Agreement,
those saved Funds will be returned to the Province.
6. Article A14.0 of Schedule “A” is deleted and replaced with the following:
A14.0 FUNDS UPON PROGRAM END DATE
A14.1 Funds Upon Program End Date. By March 31, 2028, the
Recipient will pay to the Province any unspent Funds remaining in
its possession, under its control, or both.
7. Schedule “B” is amended by deleting the Expiry Date of “March 31, 2026” and
substituting “June 30, 2028”.
8. Section B1.2 of Schedule “B” is amended by deleting the following sentence:
“The Recipient’s eligibility for a given Program Year will be assessed prior to the
start of that Program Year.”
3
9. Schedule “B” is amended by adding the following Additional Provision:
B4.0 PROGRAM GUIDELINES
B4.1 Program Guidelines May be Amended from Time to Time. The
Province may update Schedule “G” from time to time without the
agreement of the Recipient provided that the changes do not impose
substantial additional liability on the Recipient. The Province shall
provide any updated Schedule “G” to the Recipient by Notice.
10. Section (1) of Schedule “C” is amended by adding the words “and the Additional
Reporting Period,” after “Program Year”, and by adding the words “and in a form
to be provided by the Province” after “Schedule “G””.
11. Section (2) of Schedule “C” is amended by adding the words “and the Additional
Reporting Period” after “Program Year”.
12. Section (3) of Schedule “C” is amended by adding the words “or the Additional
Reporting Period” after “Program Year” in the second bullet.
13. Section (5) of Schedule “C” is amended by adding the words “or the Additional
Reporting Period” after the first “Program Year”, and by adding “or July 30th, 2027
for the Additional Report Period” after the second “Program Year”.
14. Section D2.3 of Schedule “D” is amended by deleting “the Expiry Date” and
substituting “March 31, 2028”.
15. Section D3.0 of Schedule “D” is amended by adding a new subsection iii. “iii.
Incentive payments for the construction of market-rate housing” and by
renumbering the remainder of the list accordingly.
16. Schedule “F” of the Agreement is deleted and replaced with Schedule “F”,
attached to Amending Agreement No.1 as Appendix “1”.
17. Schedule “G” of the Agreement is deleted and replaced with Schedule “G”
attached to the Amending Agreement No. 1 as Appendix “2”.
18. The Agreement is amended to reflect that wherever the conjunction “; and”, or
“or” is used before the last item on a list, and the last item on the list has been
deleted, or one or more new items have been added at the end of the list, the
subject conjunction shall be deemed to have been moved to the end of the
penultimate item on the amended list.
19. Amending Agreement No.1 shall be effective as of the date set out at the top of
the Amending Agreement No.1.
4
20. Except for the amendments provided for in Amending Agreement No.1, all
provisions in the Agreement shall remain in full force and effect.
The Parties have executed this Amending Agreement No.1 on the dates set out below.
HIS MAJESTY THE KING IN RIGHT OF ONTARIO
as represented by the Minister of Municipal Affairs and
Housing
____________________
Signature
Name:
Title:
____________________
Date
[enter the full legal name of the Recipient above]
____________________
Signature
Name:
Title:
____________________
Date
____________________
Signature
Name:
Title:
____________________
Date
I/We have authority to bind the Recipient.
5
Appendix “1”
Attached to and forming part of the Amending Agreement No.1 entered into between
the Province and the Recipient effective as of the 1st day of January, 2025.
Schedule “F”
Attached to and forming part of the Agreement entered into between the Province and
the Recipient dated the 1st day of April 2024.
SCHEDULE “F”
REPORTS
Name of Report Due Date
Investment Plan In accordance with Schedule “G”
Year End Report In accordance with Schedule “G”
Report Due Dates
The reporting period is set out in Schedule “G”.
Except as noted below, if the due date of any Report falls on a non-Business Day, the
due date is deemed to be the next Business Day.
Submission of Reports
All reports are to be submitted in accordance with Schedule “G”.
Report Details
1. The Investment Plan shall include the required information as set out in Schedule
“C” and shall be in a form to be provided by the Province.
2. The Year End Report shall provide information on the Eligible Expenditures
incurred in the Program Year or Additional Reporting Period, as applicable, and
progress made in each project, and shall be in a form to be provided by the
Province.
Performance Measures
- Delivery of all Reports within established timelines
- Ensuring all expenditures are in accordance with the Agreement
- Timely responses to requests from the Province
- # of housing units or homeless shelter beds supported or created (if applicable)
6
Appendix “2”
Attached to and forming part of the Amending Agreement No.1 entered into between
the Province and the Recipient effective as of the 1st day of January, 2025.
Schedule “G”
Attached to and forming part of the Agreement entered into between the Province and
the Recipient dated the 1st day of April 2024.
[PROGRAM GUIDELINES ATTACHED]