HomeMy WebLinkAboutOES 28-08
REPORT TO
EXECUTIVE COMMITTEE
Report Number: OES 28-08
Date: October 14, 2008
'1
~-_.__.~-~_.~----"-~_.._---,._----_._._-_.._-~----~~-.------+-----
From:
Everett Buntsma
Director, Operations & Emergency Services
Subject:
Information Technology (IT) Server Room
Ventilation and Air Conditioning, Civic Complex
File: A-1440
Recommendation:
1. That Report OES 28-08 regarding the Ventilation and Air Conditioning (HVAC)
requirements for the Information Technology (IT) Server Room in the Civic
Complex be received;
2. That staff be directed to proceed with a formal tender process for the provision of
ventilation and air conditioning in the Information Technology Server Room.
Executive Summary: The IT Server Room on the second floor of the Civic
Complex is experiencing serious climate control problems. Three factors were
identified that necessitated the HVAC be upgraded within the computer room during
2007: the first being additional hardware being added during the past several years to
accommodate network growth; the second to compensate for the warming of the Civic
Complex's air conditioning system that the computer room partially depends upon; and
the third to replace the roof-mounted unit that was installed approximately five years
ago that is now insufficient to meet demand.
The 2008 Capital Budget included a $20,000.00 allowance for the IT computer room air
conditioning replacement; however, the total cost based on informal quotations
received on the Consultant's design is estimated to be approximately $175,000.00,
therefore, it was decided to re-submit this project in the 2009 Capital Budget and
implement a temporary solution until then.
However, during mid-July, a temporary unit was installed within the computer room to
assist with rising temperatures, but during the night of September 4, 2008, the unit
failed resulting in a complete shutdown of the computer room servers as a result of
temperatures reaching 108 degrees Fahrenheit. The shutdown of the computer
network resulted in the lost productivity of one-half day for most employees, and a full
day for others, depending on the application system accessed. The ability of the City to
provide the expected level of customer service to its residents also was impacted.
As this failure could occur again at any time, staff are seeking authorization to proceed
through the formal tendering process now.
Report OES 28-08
October 14, 2008
Subject: IT Server Room
2 Ventilation and Air Conditioning
Page 2
Financial Implications: The 2008 Capital Budget included a $20,000 allowance for
IT Server Room air conditioning, but the total cost based on quotations received is
estimated to be approximately $ 175,000.00. This is the realistic cost for a long-term
solution.
Funding for the expenditure, if approved by Council after the results of the Tender Call
are known, will be provided from the 2008 Current Budget Contingency Account and/or
Federal Gas Tax Funds and therefore, will not increase the total approved Budgets for
2008.
Sustainability Implications: At present, the internal remedial measures being
used to cool the Server Room are not energy or cost effective.
If a properly designed upgrade is constructed, the climate control will once again fall
within the City's Sustainability Guidelines. Adequate ventilation and ducting will reduce
the energy requirement for cooling the area thus reducing the carbon footprint.
In addition, the potential loss of network time is in itself not sustainable due to loss of
productivity and customer service.
Background: The need for upgraded ventilation and climate control in the IT
Server Room, on the second floor of the Civic Complex was recognized in 2007 and
budgeted for as a capital item in the 2008 Capital Budget for a total amount of
$20,000.00. This budget estimate was originally based on an assumption that
additional compressor units could simply be added to the roof.
Engineering consultants (TSH) were commissioned to provide working sketches and
specifications for the required upgrades in spring of 2008. During this process, it
became evident that the required modifications would exceed the original budget
estimate, as the ducting and ventilation was considered to be inadequate for a simple
fix. Therefore, it was decided to defer the project until 2009, and during 2008,
implement a temporary solution using a portion of the $20,000.00. As stated, the
temporary solution failed causing a complete shutdown in the City's computer network.
Informal quotations from a list of qualified contractors were requested in July 2008 and
site meetings were arranged by staff with each of the contractors.
CORP0227-07/01 revised
Report OES 28-08
October 14, 2008
Subject: IT Server Room
Ventilation and Air Conditioning
Page 3
:3
Quotations were received from three qualified contractors and ranged from
$140,000.00 to $175,000.00. These quotations were based on detailed working
sketches and a site visit. Details of the actual bids are not included due to
confidentiality issues.
As the prices greatly exceeded budget, it was decided to defer this project to the 2009
Capital Budget. In consultation with the Manager of Information Technology, an interim
solution involving portable air conditioners was agreed upon in July 2008. However,
because of the ducting limitations only one air conditioner could be operating and it was
the only solution available within the budget restraints.
On September 4, 2008, the temporary system failed. While it is unknown how long the
computer room was without air-conditioning, it is known that at 8: 1 0 am, the
temperature within the computer room was 108 degrees Fahrenheit and metal
components were hot to the touch. The following identifies both the known impact of
this equipment failure, as well as the potential impact.
Known
1. The City as a whole suffered a minimum of four and one-half hours of lost
productivity, as the network was known to be inoperative from 7:00 am to 11 :30
am.
2. Most servers went into thermal mode and shut down to protect against the
extreme heat. The newer servers did not shut down, but powered down the
processing capacity to reduce the heat output and power requirements.
3. The server hosting the financial, budget, customer care and property systems
failed to start at 11 :30 am, most likely as a result of heat damage. HP was called
and according to the maintenance contract, the server was operational by 5:00
pm.
Potential
1. It is quite possible the City will experience computer equipment failure(s) within the
next three to five weeks. The result will be lost productivity.
2. It is possible that components of the telephone system could fail within the coming
weeks due to the extreme heat experienced. If that were to occur, the City would
be unable to respond to incoming telephone calls, or to place outgoing calls. A
system identified as the Corporation's most important system would be
unavailable for an unknown time period.
CORP0227-07/01 revised
Report OES 28-08
October 14, 2008
Subject:
14
IT Server Room
Ventilation and Air Conditioning
Page 4
3. It is possible that components of the email system could fail within the coming
weeks due to the extreme heat experienced. If that were to occur, the City would
be unable to send emails, and incoming emails could be lost.
Staff have set up two portable air conditioning units to maintain an appropriate
temperature in the Server Room. However, this solution is not effective in the long
term. At present, hot air discharging from the Server Room is increasing the cooling
load demand and creating a static air pressure problem in the entire Civic Complex.
It is therefore recommended that staff be authorized to proceed with a formal tender
process. Once completed, the results, together with financing will be presented to
Council for approval in 2008.
Attachments:
Not applicable
Prepared By:
Approved/Endorsed By:
/::- ) 1'/
/' /
Ton(t~1
Division Head, Facilities Operations
Everett unts
Director, Operations & Emergency Services
Prepared By:
Approved/Endorsed By:
/1
/ j
i'
i'
i ...---'"
il 1._ ..'
1-1--
;; .
'-.....- '......- ~
<C:-f;~[?:=~ c_'
Gillis A. Paterson
Director, Corporate Services & Treasurer
JOI},$torms
Manager, Information Technology
TP:mld
Copy: Chief Administrative Officer
Recommended for the consideration
of Pickering City~ouncil
/'
//
CORP0227 -07 /01 revised