REPORT TO COUNCIL
FROM:
Bruce Taylor, AMCT, CMM
City Clerk
DATE: May 6, 2002
-
REPORT NUMBER: CL 14-02
SUBJECT:
2002 Current and Capital Budgets
- Ajax Pickering Transit Authority (APT A)
RECOMMENDATION:
1.
That the letter iÌ'om the General Manager of the Ajax Pickering Transit Authority dated
April 2, 2002 advising of the resolution passed by the Board of APT A regarding the 2002
Current and Capital Budgets of APT A be received.
2.
That the Council of the Corporation of the City of Pickering hereby approves the 2002
APT A Current and Capital Budgets as set out in APT A Report 07-02 attached to the
April 2, 2002 letter of the General Manager of APT A.
ORIGIN:
-
Resolution of APT A Board passed on March 26, 2002
AUTHORITY:
Municipal Act
FINANCIAL IMPLICATIONS:
As set out in APT A Report 07-02
EXECUTIVE SUMMARY:
This Report forwards a summary of the 2002 APT A Current and Capital Budgets to Council for
its approval.
-
BACKGROUND:
Please find attached to this Report a letter ftom the General Manager of APT A advising of a
resolution passed by APT A on March 26, 2002 to approve the 2002 Current and Capital Budgets
of APTA and requesting the approval of the Councils of Ajax and Pickering.
Report to Council CL 14-02
Date: May 6, 2002
003
Subject: 2002 APT A Current & Capital Budgets
Page 2
The details of the 2002 APT A Current and Capital are set out in APT A Report 07-02, which is
attached to the letter iÌ'om the APT A General Manager.
-
ATTACHMENTS:
1.
Letter dated April 2, 2002 iÌ'om General Manager of APT A
Prepared By:
Á ¿~
Bruce Taylor, City Clerk
Attachments
Copy: Director, Corporate Services & Treasurer
Recommended for the consideration of Pickering
City Council
-
-
Of)4
AJAX PICKERING
i1ili.1mm
AUTHORITY
ATTACHMENT#L TO REPORT#~ 1'1- 61..-
Ajax Pickering Transit Authority
110 Westney Road South
Ajax, ON
Canada L 1 S 2CB
April 2, 2002.
_.
Bruce Taylor
City of Pickering
One The Esplanade
Pickering, Ontario.
LIV 6K7
REceIVED
CITY OF PICKERING
APr~ 0 4 2002
CL.ERI('S DIVISION
Please be advised that the following resolution was passed by the Board of the Ajax Pickeimg
Transit Authority at its Board Meeting held on March 26, 2002.
RECOMMENDATION:
I. That the Report to the APT A Board of Management APT A 07-02 concerning the APT A
2002 Budget be received;
2. That the APT A Board of Management approve the APTA 2002 Current and Capital Budgets;
3. That the APT A Board of Management approve fare increase and fare harmonization changes
contained in this report for implementation effective July 2, 2002.
4. That the Report and Recommendations of the APTA Board of Management regarding the
2002 APTA Current and Capital Budgets be forwarded to the Councils of the Town of Ajax
and the City of Pickering for approaval; and
.-.
5. The appropriate officials of the Ajax Pickering Transit Authority be given authority to give
effect hereto.
Should you have any inquiries with respect to this matter, please do not hesitate to contact me. I
may be contacted by telephone at (905) 427-5710.
Yours Truly,
Attachment: Report Number APT A 07-02
Copy:
Gil Paterson, Treasurer, APT A
Telephone 905-427-5710 . 905-683-4111 . Fax 905-427-3473
www.townofajax.com . www.cityofpickering.on.ca
-
ß\TTACHfv1E1\!T#.._.,C..TO REÞORT# c¿ ;'1- 0 2-
-
005
A1 .. AJAX PICKERING
. liI:f'l1~J.:i1l1
. AUTHORITY
.TA
REPORT TO THE BOARD
-
FROM:
. Ted Galinis
General Manager, Ajax Pickering Transit Authority
REPORT NUMBER: APTA07-02
DATE: March 19,2002
SUBJECT:
APTA 2002 Budget
RECO M:M:END A TI ON:
1. Thàt the Report to the APTA Board of.Management APTA '07-02 conce111Îi1g the APTA
2002 Budget be received; .
2. That the APTA Board of Management approve the APTA 2002 Current and Capital Budgets;
3. That the APTA Board of Management approve fare increase and fare hannonization changes
contamed in this report for imp1e1nentation effective July 2,2002;
4. That the Report and Recommendations of the APTA Board of Manageme~t regarding the
2002 APT A Current & Capital Budgets be forwarded to the Councils of the Town of Ajax
and City of Pickering for approval; and, . ..
-
5. The appropriate officials of the Ajax Pickering Transit Authority be given authority to give
effect thereto.
ORIGIN:
General Manager, Ajax Pickering Transit Authority
AUTHORITY:
Not applicable
-
006
Report to Board 07-02
ATTACHI'1ENTtt.J__.ro REPORT #5:-':--., /4- 0.1-
Date: March 11, 2002
Subject: 2002 APIA Budget
Page 2
FINANCIAL IMPLICA TlaNS:
CURRENT BUDGET
-
APTA 2002 Net Current Core Budget: $ 4,477,294
Increase over 2001 Net Current Expenditures: $ 391,599 .
Percentage Increase over 2001: . 9.58%
Total 2002 Current Transitional Budget:
Total 2002 Additional Requirements Budget:
163,322
53.141
Ajax
Pickering
Total 2002 APTA Current Budget: ~ 4,693,7571
Increase over 2001 Net Current Expenditures: $ 608,069
Percentage Increase over 2001: 14.88% .
~1,996,2551 ~2,697,502
CAPITAL BUDGET:
APTA 2002 Net Capital Core Budget: . . $ 2,109,900
Increase over 2001 Net Capital Expenditures: $ 1,299,700
Total 2002 Capital Transitional Budget:
339,100
~1,224,50~
Total 2002 APTA Capital Budget: 1$ 2,449,0001
Increase over 2001 Net Capital Expenditures: $ 1,299,700
Percentage Increase over 2001: 113.09%
~ 1,224,5001
* NOTE: Refer to Item (c) in "Funding Sources" below
-
CURRENT & CAPITAL BUDGET:
Total 2002 APTA Capital & Curren~Budget: 1$ 7,142,7571
Increase over 2001 Net Capital & Current Budget: $1,907,762
Percentage Increase over 2001: 36.44%
1$3,220,7551
1$3,922,0021
FUNDING SOURCES:
a) Municipal Funding - Being provided by the Town of Ajax and City of Pickering at levels that
are in line with the 2001 budgets plus a general increase in line with other municipal
departments.
b) Regional Funding - Funds were repatriated from the Region and should be used by the
municipalities for 2002 Budget needs. Pickering will receive $1.6 million and Ajax will
receive $1.2 million. Regional funding in excess of APT A 2002 Budget fInancing
requirements shQuld be placed in Transit Reserves Accounts established by Ajax and
Pickering. Region funding is being treated as a one-time event to be utilized for required fleet
replacement and transit merger transitional costs.
-
Report to Board 07..02
A IT ACH MEf\!l" # ".~_L
RF:O"'RT # C t. l'ý~ 0'1...- 0 n 7
r:.(\"h"\.. ,.~._".,_. Date: March 11, 2002 "
Subject: 2002 APT A Budget
Page 3
~
c) Provincial Funding Request - On February 20, 2002, Tra;nsp.ortation Minister Brad Clark
announced $100 million for the first year of the Ontario Transit Renewal Program. The
municipalities of Ajax and Pickering are. eligible for $873,126 for replacement of buses and
major fleet refurbishing. Funding is based on. a 1/3 provincial contribution. The amount of
$873,000 includes other capital items thRt have been requested by APTA. Clarification has
not yet been provided concerning which projects the Province has deemed eligible or the
process for accessing funding. At the direction of the APT A Board, correspondence has been
sent to the Province requesting clarification on these issues.
. . .
d) Provincial Fundin~ Requests - Golden Horseshoe Transit mvestment Partnerships (GTIP) -
APTA has made two applications under GTIP and is supporting three other applications:
1.
Transit Merger Funding - Total $3.7 million. Please note this includes all of our costs
associated with the 1raÎ1sit merger for a three year period.
n.
Replacement Telephone System and Microwave Communications Link - Total
$172,800.
111.
Regional Requests - APTA is supporting two Region of Durham requests. "Taunton
Road Bus Rapid Transit Implementation" and the development of a "Transit
Improvements Implementation Plan". .
IV.
GO 'Transit Request - APT A is supporting the GO Transit application for
"Implementation of a Smartcard-based Fare Collection System in the GTA".
-
e) Federal Funding - No support to date.
-
0 n 8 Report to Board 07..02
'.'"I.l"At~H. !Vi !.-""f....:.
/J., \,~ d! (.I" .
!
# CL /'1- ú'l---
Date: March 11, 2002
. S~bject: 2002 APTA Budget
Page 4
FARE INCREASE AND HARMONIZATION:
.Recommended Fare Increase/Harmonization -.Effective July 2, 2002.
-
Part A Current Current APTA % Inc. 2002 Annual
Fare Harmonization Ajax Pickering 02/07/02 Revenue Revenue
Senior Cash Fare $0.65 $0.50 $0.65 (60 0-30% 3,000 6,000
(55up) (65 up) up)
Student Cash Fare $1.25 $1.00 . $1.25 0-25% 17,000 34,000 .
Adult Monthly Pass $46.00 $50.00 $50,00. ' 0-8% 5,000 10,000
GO Co-fare (no change) $0.50 $0.50 $0.50 0% 0 0
Child Fare $0.65 $1.00 $1.00 0-53% 3,500 7,000
Part B
Fare Increase
Adult Cash Fare $1.50 $1.50 $1.75 16% 24,000 48,000
(Conventional & Sp. Serv.)
Senior Pass (no change) $13,00 . N/A $13.00 0% 0 Ö
Student Restricted $33.00 N/A $35.00 9% 3,000 6,000
. Student Umestricted Pass $36.00 $38.00. $40.00 5-11% 4,500 9,000
- Separate School Brd. Pass $33.00 $33-.00 $35.00 6% 25,000 50,000
Total Projected Revenue $85,000 $170,000
Fare harmonization between Ajax and Pickering is required to create a common fare structurè for
APTA operations. A C9mmon fare structure and discontinuing the Ajax smartcard system are the
required fust steps 19 permit APTA buses to be used interchangeably ill Ajax or Pickering.
APT A is proposing that a combined process of fare incre<l$es and fare harmonization take effect
upon the completion of the school year in June 2002. By that time, the use of smartcards in Ajax
will be phased out and replaced with a temporary paper ticket/pass system until such time as the
. GO Transit GTA-wide smartcard fare collection system can be introduced in 2003.
Fare increases are required to meet our 2002 revenue and cost targets without impacting on the
cost to t8.?'-payers of sustaining our core transit service. As new transit routes are introduced,
APT A will be required to offset a miIrimum of 50% of the cost with fare box revenue. The
-
';.I...'"AC. H'¡y<e..".,..'.'..,'.
l\ .. h:> \1 ~
nng
Report to Board 07...02
{L !tf-()v
. Date: March 11, 2002
Subject: 2002 APT A Bùdget
Page 5
armualized impact of fare increases will provide the necessary revenue to sustain. additional
service without a significant impact on the rate of taxation for transit in the futur~. .
-
Fare increases are primarily directed at discretionary transit llsers and will have little or no impact
. on the majority of our ftequent customers. Approximately 1/3 of our ,ridership consists of GO
Transit rail passengers who will continue to pay $0.50 (co-fare) for trips to and ftom the iram. A
further 1/3 of our customers are students who are issued pre~paid passes by the Separate School
Board for travel to and ITom school. This group will also feel no fare increase impact for daytime
transit use. Students however, will be required to pay an additional $5.00 per month töuse transit
services evenings and weekends. This approach is prefeITed by the Separate School Board and is
now practiced throughout Durham Region with the exception ofPicke$g.
Over time, APTA would benefit ftom a gradual move toward fare harmonization with \Vhitby
and Oshawa. The proposed APTA adult cash fare of $1.75 remams Under the. Whitby and.
Oshawa $2.00 adult cash fare rate. APTA child and student ticket and pass rates are' also
significantly less than Oshawa and Whitby. A common fare structure throughout. Durham Region
would p.ermit the introduction of a GT A or Regional Pass with reduced requirements for.
reconciling intennunícipal trips and fare integration revenue-sharing payments. .
EXECUTIVE SUMMARY:
At the APTA Board of Management Meeting of January 29, 2002 staff were directed to take
action to both reduce our 2002 budget requirements and pursue funding potential ftom a variety
external funding sources.
-
Based ån a review of 2001 actual costs and revenue, as well as a recommended fare increase to
ta1ce effect ill June 2002, the total requested net APTA budget has been reduced by. $346,974
since our last presentation of summary budget figures to the Board. .
External APTA funding n-om the Region of Durham and the Province of Ontario has been
announced. APT A has made application for additional funding support through the Provincial
GTIP inltiative and continues to . pursue funding that may be available related to transitional
merger costs. The Canadian Urban Transit Association (CT,JTA) and the Ontario Community
Transportation Association (aCTA) are pursuing additional funding potential at the Federal and
Provincial levels on our behalf.
Additional grant funding has been applied for. If one application is successful, the other two
applications will be reduced where there is overlapping capital requests. The additional funds
fi:om these grant applications could be trans felTed to the municipality's respective "Transit
Reserves" or used to reduce the amounts otherwise payable by the respective municipalities.
Those reserves are a critical element in financial planning and will be used to offset future capital
. related expenditures. .
-
(] 1 0 Report to Board 07-02
ATTACH M E!\n
I
(L- /1.{-O1-.
Date: March 11, 2002
Subj ect: 2002 APT A Budget.
Page 6
-
The 2002 APTA Budget has been presented to and dis~ussed with the Chief Administrative
Officers and Treasurers for the Town of Ajax and the City of Pickering. Adequate funds are
available through a combmation of municipal contribution, the Province of Ontario and one-time
Region of Durham funding to sustain the complete 2002 APTA Current. and Capital Budget.
APT A. is requestmg support from the Board of Management and municipal Councils to approve
the 2002 Current and Capital Budgets. In order to sustain current transit serVice levels and .
remain fully eligible for recently announced Capital funding, APTA requires Board of
Management and municipai Co~cil approval of our Core and Capital budget requirements.
Beyond 2002, APTA and our municipal funding partners will need to actively pursue sustainable
funding sources in order to maximize provincial matching funds and achieve our equipment
replacement and growth related objectives.
ArT ACHMENTS:.
1.
2.
2002 APT A Budget
APT A Budget Reduction Summary
Prepared / Approved I Endorsed By:
Approved / Endorsed By:
-
~~
Gillis Paterson, Treasurer
Ajax Pickering Transit Authority
-
(
2002 CURRENT BUDGET
i\fTACHIVIEr',n
/
1.1
REPORT #- ~I '-1- ð;:rTACHMENT # - TO REPORT #fJf.fAij1
AJAX PiCKERING. TRANSIT AUTHORITY
APTABUDGET REDUCTIONS
March 6, 2002.
Account
Net Change
Highlights of Change Items
2910 - Administration
-
2920 - Maintenance
2930 - Conventional
. 2940 - Specialized
ervices
2945 - Transition Costs
$101,498 New Inspector/Trainer position deferred, approx. $10K reduction in
instructional training and conference expenses, insurance reduced $10K
to reflect 2001 actual costs, smartcard supplies deferred @ $1 OK, various
administration equipment and supplies deleted/reduced. .
61,472 Approx. $50K reduction in urgent body repair, brake repair and shop
supplies, On-call Mechanic replaced by Servicepersons, Mechanic
training reduced 50%, building utility costs reduced approx. $1 OK to
reflect 2001 actual costs.
174,768 New Parts/Inventory Supervisor position deferred, reduction in uniforms.
Pickering GO office renovations deleted, increased costs for "2"
endorsement training, snow removal (reflect new contract). $50K added
in general revenue to reflect 2001 actual, $85K added in farebox revenue
to reflect recommended fare increase/harmonization effective June 2002.
2,920 Reduction in contracted taxi service - automated trip reservation
efficiency.
52,261 Cross-training costs reduced $25K, scope of contracted route review
reduced $30K, various supervisory staff training costs reduced approx. .
$7K. World Youth Day charter costs added @ $15K..
Total Budget Change
.~
<
$392,919
-
J02 CAPITAL BUDGET
. Account
Net Change
Highlights of Change Items
2910 - Administration
2920 - Maintenance
2390 - Conventional
-$ 42,100 Costs added to reflect emergency replacement of office server and
datacard fare evasion equipment/supplies.
-360 Minor reduction in computer equipment.
-3,485 Costs added to reflect current equipment quotes. Reductions in computer
equipment. .
Total Budget Change
-$45,945
(
-
$346,974
Total Current and Capital Budget Net Change