Loading...
HomeMy WebLinkAboutOES 24-05PICKERING REPORT TO EXECUTIVE COMMITTEE Report Number: OES 24-05 Date: June 17, 2005 From: Richard Holborn, P.Eng. Division Head Municipal Property & Engineering Subject: Tender No. T-3-2005 - Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Recommendation: That Report OES 24-05 regarding the tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements be received and that; Tender No. T - 3 - 2005 submitted by Mopal Construction Limited for Liverpool Road Nautical Village Boulevard & Streetscape Improvements in the amount of $700,715.18 (G.S.T. included) for Option 1 and a net cost after G.S.T. rebate of $654,874.00 be accepted; The total project cost of $903,159 including the tender amount, and other associated costs and a net total project cost of $844,074 (after G.S.T. rebates) be approved; Council authorize the Director, Corporate Services & Treasurer to finance the project through the issuance of debentures through the Region of Durham; and a) debt financing not exceeding the amount of $700,000 for a period not exceeding 20 years, at a rate to be determined; and b) the unspent amount of $40,755 from the 2003 budgeted project Liverpool Road Millennium Square project code 03-2320-008-02, originally debt- financed in 2004 together with, the unspent amount of $103,319 from the completed project Audley Road south of Highway #7; (10-Year Debt, financed in 2004) be applied to the project; and c) annual repayment charges in the amount of approximately $58,333 be included in the annual Current Budget for the City of Pickering commencing in 2006, and any financing cost, continuing thereafter until the loan is repaid; and d) the Director, Corporate Services & Treasurer has certified that this loan and the repayment thereof falls within the City's Debt and Financial Obligations approved Annual Repayment Limit for debt and other financial obligations for 2005 as established by the Province for municipalities in Ontario; and Report OES 24-05 Date: June 17, 2005 Subject: Tender T-3-2005 Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Page 2 e) the Treasurer is authorized to take any actions necessary in order to effect the foregoing; and o The appropriate City of Pickering officials be authorized to take necessary action to give effect thereto. Executive Summary: As part of the 2005 Capital Budget, boulevard and streetscape improvements for Liverpool Road was identified and approved as a construction project. Tender T-3-2005 was issued on Friday, June 3, 2005 and closed on Thursday, June 16, 2005. The total project cost is estimated to be $903,159 for an estimated net cost to the City of $844,074 (net of G.S.T. rebate). Tender costs came in higher than anticipated in the 2005 Capital Budget of $700,000 and approximately $41,000 of the increase is for the final topcoat of asphalt pavement. Staff has been directed to report to Council on the results of the tender and financing in order to proceed with this project in a timely manner. In the 2003 Capital Budget, included for road works on Liverpool Road from Wharf Street to Millennium Square. The road works were completed in 2003 with the exception of the final lift of asphalt pavement, which is valued at $40,000, which was postponed pending this contract. As the final lift of asphalt will be applied to this project, the Director, Corporate Services & Treasurer has determined that is it appropriate to apply these funds now. The Director has also determined that the balance of $103,319 will come from any other capital under expenditures or general revenues available at year-end as approved by Council as part of the annual budget recommendations. The majority of the utility relocations required for this project had been undertaken by Veridian Connections for the underground conversion of the existing hydro plant. Council approval for this portion of the utility relocation was received at the May 2, 2005 Council meeting, in conjunction with approval of the City's 2005 Budget through Report CS 30-05. Report OES 24-05 Subject: Tender %3-2005 Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Date: June 17, 2005 Page 3 FINANCIAL IMPLICATIONS: 1. Tendered Amount T-3-2005 654,874.00 G.S.T. 45,841.18 Sub Total 700,715.18 G.S.T. Rebate (45,841.18) Total $654,874.00 APPROVED SOURCE OF FUNDS 2. 2005 Capital Budget Roads Account 2320-6003 Locations Liverpool Road Nautical Village Liverpool Road/Millennium Sq. Capital under expenditures/Current Funds Proiect Code 05-2320-008-00 03-2320-008-02 FUNDS AVAILABLE Amount 700,000 40,755 103,319 844,074 Source Debt (20 Year) 1. Debt (10 Year) 2. 1. To be Debt financed. 2. External Debt undertaken in 2004. 3. Excess Funds Raised. ESTIMATED PROJECT COSTING SUMMARY 3. T-3-2005 - Liverpool Road Nautical Village Boulevard Streetscape Improvements Associated Costs Utility Relocations (Veridian underground conversions) Materials Testing Miscellaneous Costs Project Contingency Total G.S.T, Total Gross Project Cost Less - G.S.T. Rebate Total Net Project Cost 654,874 173,200 2,500 3,500 10,000 844,074 59,085 903,159 (59,085) 844,074 Report OES 24-05 Date: June 17, 2005 Subject: Tender T-3-2005 Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Page 4 Project Cost over (under) Approved Funds $(o) The Director, Corporate Services & Treasurer has reviewed the budgetary implications and the financing of the expenditures contained in this report and has provided the financing recommendations. Background: Bids for Tender No T-3-2005 were received Thursday, June 16, 2005. Three (3) companies submitted bids at the time of closing. The Iow bidder, for Option 1 (preferred option) is Mopal Construction Limited. Liverpool Option 1 -This is the preferred option for streetscape construction. This option is derived from the original Planning Study as referenced in the "Liverpool Road Waterfront Node Development Guidelines". The intent is to have the boulevard surfaced with a "cobble look", interlocking pavers is the preferred treatment. Therefore interlocking pavers are used for the majority of the boulevard (both the parking and pedestrian areas). A narrow strip of concrete is introduced as a "Furniture Strip" both to fasten the street furniture to, and to visually separate the parking / pedestrian areas. Liverpool Option 2 - This option was considered for economic reasons only. Instead of having the majority of the boulevard covered in interlocking pavers, more concrete was substituted as a cheaper solution. The concrete was used for the pedestrian walkway. As well, the "Furniture Strip" (concrete in Option 1), was changed to interlocking pavers for aesthetic reasons. All other elements (i.e. street lighting, street furniture etc.) are the same for both options. References for Mopal Construction Limited have been checked and are deemed acceptable by the Supervisor, Engineering & Capital Works. The Health & Safety Policy, a list of personnel trained in Confined Space, and the CAD 7 form issued by Workplace Safety & Insurance Board, as submitted by Mopal Construction Limited's Safety & Training Coordinator and are deemed acceptable. Credit information as provided by D & B for Mopal Construction Limited has been reviewed by the Purchasing Analyst and in conjunction with staff's review of reference information and the bonding available on this project, is deemed acceptable. Upon careful examination of all tenders, and relevant documents received the Operations & Emergency Services Department, Municipal Property & Engineering Division recommends the Iow bid Tender No. T-3-2005 submitted by Mopal Construction Limited in the amount of $654,874 (G.S.T. extra) for Option1 and that the net total project cost of $844,074 be approved. This report has been prepared in conjunction with the Manager of Supply & Services who concurs with the foregoing. Report OES 24-05 Subject: Tender %3-2005 Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Date: June 17, 2005 Page 5 Attachments: 1. Location Map 2. Record of Tenders Opened and Checked 3. Supply & Services Memorandum Prepared By: I~arrell B. Selsky ¥ ~ Supervisor, Engineering & C~tal Works Yera A. Felgemacher Manager, Supply & Services Director, Operatieds & Emergency Services Gillis A. Paterson Director, Corporate Services & Treasurer Ric id ~V~.'~oI-. ~rn- E~on Head, Municipal Property & Engineering DS:ko Attachments Copy: Chief Administrative Officer Recommended for the consideration of Pickering City, Council . ./- 4-----\ , ':...-,- T~ J. Quin~ Chi~nistr~~e~~ MUNICIPAL PROPERTY & ENGINEERING Attachment For Tender: T-03-2005 LIVERPOOL ROAD STREETSCAPING F/~£/VCH/WAA/ 'S STREET J WHARF STREET O i 0 0 LIVERPOOL BEACHFRONT PARK LOCATION MAP PROPOSED CONSTRUCTION INCLUDES: Streetscaping and Boulevard Works for Liverpool Nautical Village Construction of decorative sidewalks - Construction of decorative off-street parking - Installation of decorative street lighting - Installation of decorative street furniture Complete Restoration (fine grading and sodding where required) - To all areas affected. PROJECT CODE: 05-2320-008-00 IAAttachmenls for Tenders~OO5lT-3-2005 Liverpool Streetscaping.doc = m o i ~0 CORPORATE SERVICES DEPARTMENT MEMORANDUM June 16, 2005 To: Richard Holborn Division Head Municipal Property & Engineering Darrell Selsky, Supervisor Engineering & Capital Works From: Vera A. Felgemacher Manager, Supply & Services Subject:: Tender for Liverpool Road Nautical Village Boulevard & Streetscape Improvements Tender No. T-3-2005 CLOSING: Thursday, June 16, 2005, 2:00 p.m. Tenders have been received for the above project. Fourteen (14) companies were invited to participate. An advertisement was placed in the Daily Commercial News, News Advertiser (Friday, June 3) and on the City's Website all of which yielded interest from additional bidders. Eleven (11) bidders picked up tendering documents for a non-refundable fee of $100.00 per set of which three (3) responded. One (1) tender was withdrawn prior to the competition closing. A copy of the Record of Tenders Opened and Checked used at the public tender opening is attached. Tenders shall be irrevocable for 60 days after the official closing date and time. Purchasing Procedure No. PUR 010-001, Item 10.03 (r) provides checking tendered unit prices and extensions; unit prices shall govern and extensions will be corrected accordingly, which has been done. Richard Holborn T-3-2005 -- ~)~- o',~'~--- June 16,2005 Page 2 Summary (PST included, GST included) Company OPTION 1 OPTION 2 After Total Tendered Total Tendered Calculation Amount $ Amount $ Check $ Mopal Construction 700,715.18 684,932.68 SAM E Ltd. Rutherford 761,537.82 755,327,01 SAM E Contracting Ltd. CRCE Construction 773,513.70 748,903.70 SAME Ltd. D/g-Con International Tender withdrawn prior to competition closing. Ltd. P. Gabriele & Sons Tender received late and returned to vendor unopened. Ltd. In accordance with Tendering Specifications, Bidding Conditions Item 10: (a) "Option 1" is the City's preferred method of construction for this project, whereas "Option 2" is a secondary consideration. As such, City staff will evaluate bids on "Option 1" first to recommend for consideration and acceptance. (b) City staff will only evaluate bids on "Option 2" for consideration and acceptance if budget constraints for this project deem it necessary. Therefore, pursuant to Information to Bidders Item 21, the following are being requested of the Iow bidder for "Option 1" for your review during the evaluation stage of this tender call: (a) (b) (c) (d) (e) (f) a copy of the Confined Space Entry Procedure document to be used on this project; a list of employees trained in the Confined Space Entry Procedure who will be working on this project; a copy of the Health & Safety Policy to be used on this project; a copy of the current Cost and Frequency Report issued by Workplace Safety & insurance Board (in lieu of the Cost and Frequency document, a copy of the current CAD 7, NEER, or MAP reports may be submitted); a copy of the current Clearance Certificate issued by Workplace Safety & Insurance Board; the City's certificate of insurance shall be completed by the bidder's agent, broker or insurer; A Dun & Bradstreet report for Mopal Construction will be requested of the Purchasing.Analyst and a summary will be provided to you during the evaluation phase of this tender call. Richard Holborn %3-2005 June 3,2005 Page 3 Please review the copy of the bids. Include the following items in your Report to Council: (a) include Coordinator, Health & Safety comments; (b) any past work experience Mopal Construction including work location; (c) without paSt work experience, if reference information is acceptable; (d) the appropriate account number(s) to which this work is to be charged; (e) the budget amount(s) assigned thereto; (f) Treasurer's confirmation of funding- including reference to Debt Financing if applicable; (g) related departmental approvals; (h) any reason(s) why the Iow bid of Mopal Construction is not acceptable; (i) and related comments specific to the project. If you require further information, please feel free to contact me. Vera A. Fel'gemacher Manager, Supply & Services /bt Attachments Copy for: Director, Operations & Emergency Services