HomeMy WebLinkAboutOES 09-05PICKERING
REPORT TO
EXECUTIVE COMMITTEE
Report Number: OES 09-05
Date: May 3, 2005
From:
Richard Holborn, P. Eng.
Division Head
Municipal Property & Engineering
Subject:
Tender No. T-1-2005 - Tender for Asphalt Overlay Works for
Rougemount Drive & Sandy Beach Road
Recommendation:
That Report OES 09-05 regarding the Asphalt Overlay Works for Rougemount
Drive & Sandy Beach Road be received and that;
Tender No. T - 1 - 2005 submitted by D. Crupi & Sons Ltd. for Asphalt Overlay
Works for Rougemount Drive and Sandy Beach Road in the amount of
$151,434.75 (G.S.T. included) and a net cost after G.S.T. rebate of $141,527.80
be accepted;
The total project cost of $173,905 including the tender amount, and other
associated costs and a net total cost after rebates of $162,528 be approved;
The total costs of $90,026 for Rougemount Drive to be funded from Public
Works Services Reserve Fund, and the amount of $72,502 for Sandy Beach
Road being an unfinished work from 2001, to be funded by Development
Charges Reserve Fund ($36,251) and Internal Loan ($36, 251) be approved;
The appropriate City of Pickering officials be authorized to take necessary action
to bring effect thereto.
Executive Summary: As part of the 2000 External Subdivision Works Capital
Budget and 2005 Roads Capital Budget, asphalt overlay works for Rougemount Drive
and Sandy Beach Road respectively were identified as construction projects. Tender T-
1-2005 was issued on April 5, 2005 and closed on April 22, 2005 with five bidders
responding. The total project cost is estimated to be $173,905 for an estimated net
cost to the City of $162,528 (net of G.S.T. rebate). Staff have been directed to report to
Council on the results of the tender and financing in order to proceed with this project in
a timely manner.
Report OES 09-05
Subject: Tender T-1-2005
Tender for Asphalt Overlay Works
Date:
May 3, 2005
Page 2
Financial Implications:
1.
TENDERED AMOUNT
T-1-2005 $141,527.80
G.S.T. 9,906.95
Sub-Total 151,434.75
G.S.T. Rebate (9,906.95)
Total $141,527.80
APPROVED SOURCE OF FUNDS:
2000 External Subdivision Works Capital Budget Account 2321-6181 and
2005 Roads Capital Budget Account 2320-6003
Location
Rougemount Drive
Sandy Beach Road
Proiect Code Source of funds Available
05-2320-008- Public Works Services 100,000
03
Internal Loan 39,300
ES-2000-B-11 Development Charges 39,301
FUNDS AVAILABLE $178,601
Required
90,026
36,251
36,251
$162,52
ESTIMATED PROJECT COSTING SUMMARY
T-1-2005 - Asphalt Overlay Works for
Rougemount Drive
Sandy Beach Road
Sub-Total
$79,526
$62,002
$141,528
Associated Costs
Materials Testing
Miscellaneous Costs
Project Contingency
Total
G.S.T.
Total Gross Project Cost
2,500
3,500
15,000
162,528
11,377
173,9O5
G.S.T. Rebate
Total Net Project Cost
(11,377)
162,528
Report OES 09-05
Subject: Tender T-1-2005
Tender for Asphalt Overlay Works
Date: May 3, 2005
Page 3
Project Cost over (under) Approved Funds
$(16,073)
The Director, Corporate Services & Treasurer has reviewed the budgetary implications
and the financing of the expenditures contained in this report and has provided the
financing recommendations.
Background: In the year 2000, Go Transit Authority proposed to expand their
existing parking lot on the west side of Sandy Beach Road, north of BaylY Street. This
section of roadway adjacent to the proposed parking lot works, was identified in the
City's Development Charges Study as an Urbanization Project. The City determined
that this would be an excellent opportunity to partner with Go Transit Authority. The
road works associated with the urbanization, would be combined in a joint tender with
the Go Transit parking lot works. The project received Council Approval under the 2000
External Subdivision Works Capital Budget. The road works and parking lot works
were completed the following year, with the exception of the final lift of asphalt. The
time has now come to complete this project. Staff have combined this project with the
completion of asphalt overlay works for Rougemount Drive, a project identified in the
2005 Roads Capital Budget. By combining both projects, there have been considerable
savings and both projects have come in under budget.
Bids for Tender No T-1-2005 were received on Friday, April 22, 2005. Five (5)
companies submitted bids at the time of closing. The Iow bidder, D. Crupi & Sons Ltd.,
has completed similar projects for the City in the past, the most recent under Quote No
Q-17-2004 Progress Frenchman's Bay Park Parking Lot, and are deemed acceptable
by the Supervisor, Engineering & Capital Works. The Health & Safety Policy, a list of
personnel trained in Confined Space, and the CAD 7 form issued by Workplace Safety
& Insurance Board, as submitted by D. Crupi & Sons Ltd., have been reviewed by the
Safety & Training Coordinator and are deemed acceptable. Credit information as
provided by D & B for D. Crupi & Sons Ltd. has been reviewed by the Purchasing
Analyst and in conjunction with staff's review of reference information and the bonding
available on this project, is deemed acceptable.
Upon careful examination of all tenders, and relevant documents received, the
Operations & Emergency Services Department, Municipal Property & Engineering
Division recommends the Iow bid submitted by D. Crupi & Sons Ltd. for Tender No. T-1-
2005 in the amount of $151,434.75 (G.S.T. included) and that the net total project cost
of $162,528 be approved.
This report has been prepared in conjunction with the Manager of Supply & Services
who concurs with the foregoing.
Report OES 09-05
Subject: Tender T-1-2005
Tender for Asphalt Overlay Works
Date:
May 3, 2005
Page 4
Attachments:
Location Map
Record of Tenders Opened and Checked
Supply & Services Memorandum
Prepared By:
Da,ltelPl~. Selsky {/./
Supervisor, Engineering & Cap'~al Works
i:~. A. Fd,~emacher
Manager, Supply & Services
,~~~Ever~,~untsm~..
Director, Operations & Emergency
Services
Gillis A. Paterson
Director, Corporate Services & Treasurer
Rich, a W. Hol~,-P.Eng.
DiviTion Head,flVlunicipal Property & Engineering
/
DS:ko
Attachments
Copy: Chief Administrative Officer
Recommended for the consideration of
Pickering City Council
ThOrr)as J. O~i~n, C_,~ief Admifi~t,a~e ~ficer
//
.~T~",~CNHENT~__J. TO REPORT# (~E ~
MUNICIPAL PROPERTY & ENGINEERING
Attachment For Tender T-1-2005
ROUGEMOUNT DRIVE / SANDY BEACH ROAD ASPHALT OVERLAY
SUBJECT
AREA
u :,
ROUGEMOUNT DRIVE
SUBJECT
AREA
SANDY BEACH ROAD
PROPOSED CONSTRUCTION INCLUDES:
Asphalt Overlay
I.'lA#achments for Tenders12005~Rougemount Drive. doc
C)
0
Z
rO REPORT# Oe %
CORPORATE SERVICES DEPARTMENT
MEMORANDUM
April 25, 2005
To:
Richard Holborn
Division Head
Municipal Property & Engineering
Darrell Selsky /
Supervisor, Engineering & Capital Works
From: Barbara Tran
Buyer
RE:
T-1-2005, Tender for Overlay Asphalt
Rougemount Dr. & Sandy Beach Rd.
CLOSING: Friday, April 22, 2005, 2:00 p.m.
Tenders have been received for the above project. Seven (7) companies were
invited to participate. An advertisement was placed in the Daily Commercial
News, News Advertiser Community Page and on the City's Website all of which
yielded interest from additional bidders. Seven (7) bidders picked up tendering
documents for a non-refundable fee of $40.00 per set of which five (5)
responded. A'copy of the Record of Tenders Opened and Checked used at the
public tender opening is attached.' Tenders shall be irrevocable for 60 days
after the official closing date and time.
Purchasing Procedure No. PUR 010-001, Item 10.03 (r) provides checking
tendered unit prices and extensions; unit prices shall govern and extensions will
be corrected accordingly, which has been done.
All deposits other than the Iow three bidders may be returned to the applicable
bidders as provided for by Purchasing Procedure No. PUR 010-001, Item
10.03(w). Therefore, the tenders of the Iow three (3) bidders are attached for
review.
Richard Holborn _~ .
Darrell Selsky
ro REPORT '---A-pril 25, 2005
O¢'-- Page 2
Summary
(PST included, GST included)
D. Crupi & Sons Limited 151,434.75 151,434.75
Harnden & King Construction 163,460.50 163,460.50
Vaughan Paving 181,080.81 181,080.81
A1 Asphalt Maintenance 192,367.76 192,367.76
Miller Paving Limited 202,521'. 19 202,521.19
Pursuant to Information t° Bidders Item 21, the following are being requested of
the Iow bidder for your review during the evaluation stage of this tender call:
(a) a copy of the Health and Safety Policy to be used on this project;
(b) a copy of the current Cost and Frequency Report issued by Workplace
Safety & Insurance Board (in lieu of the Cost and' Frequency document, a
copy of the current CAD 7, NEER, or MAP reports may be submitted);
(c) a copy of the current Certificate of Clearance issued by Workplace Safety
& Insurance Board;
(d) the City's certificate of insurance shall be completed by the bidder's agent,
broker or insurer.
Please review the copies of the bids. Include the following items in your Report
to Council:
(a) if items (a) through (c) noted above, are acceptable to the Safety & Training Co-
ordinator;
(b) any past work experience D. Crupi & Sons Limited including work location;
(c) without past work experience, if reference information is acceptable;
(d) the appropriate account number(s) to which this work is to be charged;
(e) the budget amount(s) assigned thereto;
(f) Treasurer's confirmation of funding;
(g) related departmental approvals;
(h) any reason(s) why the Iow bid of D. Crupi & Sons Limited is not
acceptable; and
(i) related comments specific to the project.~'
If you require further information, please feel free to contact mei
Barbara Tran /
/bt [
Attachments
Copy for: Director,.Operations & Emergency Services
Construction Coordinator/Inspector