HomeMy WebLinkAboutOES 25-04PICKERING
REPORT TO
EXECUTIVE COMMITTEE
Report Number: OES 25-04
Date: September 3, 2004
From:
Stephen Reynolds
Division Head, Culture & Recreation
Subject:
Tender No. T-3-2004
Tender for Pickering Recreation Complex
Pickering Civic Complex Chiller Conversion
File: CO3000
Chiller Replacement and
Recommendation:
That Report OES 25-04 regarding the Pickering Recreation Complex Chiller
Replacement and Pickering Civic Complex Chiller Conversion be received and
that:
Tender No. T-3-2004 submitted by Harold R. Stark, Division of William Stark
Group Inc. for the replacement of the Pickering Recreation Complex Chiller and
the Pickering Civic Complex Chiller Conversion in the amount of $599,169.00
(G.S.T. extra) be accepted;
The total gross project cost of $676,795.33 and a net project cost of $632,519.00
including tender amount and other project costs identified in this report be
approved;
That Council authorize the Director, Corporate Services & Treasurer to finance
the project as included in the approved 2004 Capital Budget as follows:
a) Issuance of debt not exceeding the amount of $425,000 for a period not
exceeding 10 years, at a rate to be determined;
b) Issuance of debt not exceeding the amount of $130,000 for a period not
exceeding 5 years, at a rate to be determined;
c) The balance of funding for the above project in the estimated amount of
$77,500 plus financing costs, be financed from 2004 current funds;
d)
Financing and repayment charges in the amount of approximately $82,600 be
included in the annual Current Budget for the City of Pickering commencing in
2005 and continuing thereafter until the loans are repaid;
e)
The Director, Corporate Services & Treasurer has certified that these loans
and the repayment thereof falls within the City's Debt and Financial
Obligations approved Annual Repayment Limit for debt and other financial
Report OES 25-04
Subject: Chiller Replacement and Conversion
Tender T-3-24
Date: September 3, 2004
Page 2
obligations for 2004 as established by the Province for municipalities in
Ontario;
f) The Treasurer be authorized to take any actions necessary in order to effect
the foregoing; and,
Staff at the City of Pickering be given the authority to give effect thereto.
Executive Summary:
The Pickering Recreation Complex Chiller Replacement and Pickering Civic Complex
Chiller Conversion were approved by Council in the 2004 Capital Budget. Tenders have
been received and the total net project cost is estimated to be $632,519.00 (net of
G.S.T. rebate).
Supply & Services and Totten Sims Hubicki Associates have confirmed that Iow bidder
Harold R. Stark, Division of William Stark Group Inc. have satisfied their tender
requirements and is qualified to undertake this project.
Financial Implications:
APPROVED SOURCE OF FUNDS:
1.
2004 Capital Budget- 5 Year Debt
2004 Capital Budget - 10 Year Debt
2004 Capital Budget- Current Levy
Account
2124-6181
2731-6181
2735-6181
Project Code
04-2124-005-05
04-2731-005-07
04-2735-005-02
Amount
$130,000
$425,000
$ 85,000
Total Approved Funds $640.000
Report OES 25-04
Subject: Chiller Replacement and Conversion
Tender T-3-24
Date: September 3, 2004
Page 3
Estimated Project Costing Summary
T-3-2004 Tender for Pickering Recreation Complex Chiller
Replacement and Pickering Civic Complex Conversion
Consulting Fees
Subtotal
GST
Total Gross Project Cost
GST Rebate
Total Net Project Cost
$599,169.00
$ 33,350.00
$632,519.00
$ 44,276.33
$676,795.33
(44,276.33)
$632,519.00
Project Cost under (over) Approved Funds $7,481.00I
The Director, Corporate Services and Treasurer has reviewed the budgetary
implications and the financing of the expenditures contained in this report and concurs.
Background:
The Pickering Recreation Complex Chiller Replacement and Pickering Civic Complex
Chiller Conversion were approved by Council in the 2004 Capital Budget. Tenders have
been received and the total net project cost is estimated to be $632,519.00 (net of
G.S.T. rebate).
The tOtal budget allocation available for this project is $640,000.00. Totten Sims
Hubicki Associates developed the specifications for the Pickering Recreation Complex
Chiller Replacement and Civic Complex Conversion. Council is also advised that the
$85,000 listed under "Approved Source of Funds" (Project Code 04-2735-005-02) was
originally intended for the replacement of the chiller in the Delaney Rink with a high
energy efficient Plate Chiller. This project will be re-budgeted in 2005 proposed budget
submissions. This will allow the work for T-3-2004 to proceed this year to meet
legislated requirements.
A mandatory site visit was held on Wednesday, August 24, 2004, at which seventeen
companies (17) were in attendance. The City received seven (7) bids at the time of
closing. The seven (7) bids for T-3-2004 were opened on Wednesday, August 11,
2004. A copy of the Records of Tenders Opened and Checked used at the public
tender opening and the memorandum from Supply and Services is attached.
Report OES 25-04
Subject: Chiller Replacement and Conversion
Tender T-3-24
Date: September 3, 2004
Page 4
The Iow bidder, Harold R. Stark, Division of William Stark Group Inc. have not
performed previous work for the City of Pickering. References have been checked by
Totten Sims Hubicki Associates and are deemed acceptable.
The Health & Safety Policy, the WSIB Clearance Certificate, the CAD 7 Form issued by
the Workplace Safety and Insurance Board as submitted by Harold R. Stark, Division of
William Stark Group Inc. have been reviewed by the Coordinator, Health & Safety and
are deemed acceptable. A comprehensive business report as provided by Dun &
Bradstreet for William Stark Group Inc. has been reviewed by the Senior Financial
Analyst and in conjunction with staff's review of reference information and the bonding
requirement on this project, is deemed acceptable.
Upon careful examination of all tenders and relevant documents received, Totten Sims
Hubicki Associates and the Culture & Recreation Division recommend the acceptance
of the Iow bid submitted by Harold R. Stark, Division of William Stark Group Inc. in the
amount of $599,519.00 (G.S.T. extra) and that the total net project cost of $632,519.00
be approved.
This report has been prepared in conjunction with Supply & Services who concurs with
the foregoing.
Attachments:
2.
3.
4.
Supply & Services memorandum dated August 11,2004
Record of Tenders Opened and Checked
Recommendation from Totten Sims Hubicki Associates dated August 19, 2004
Location Maps
Prepared By:
......
Supervisor, Facilities Operations
B/ob KU~zr~] ~ '-
Purchasing Anfllyst
Direct6r, Operations & Emergency
Services
Division Fieed~, Culture & Recreation
Report OES 25-04
Subject: Chiller Replacement and Conversion
Tender T-3-24
Date: September 3, 2004
Page 5
Funding Approved:
'('(~il'~ A. Paterson
Director, Corporate Services & Treasurer
SR:Ig
Attachments
Copy: Chief Administrative Officer
Director, Corporate Services & Treasurer
Recommended for the consideration of
Pickering C, ity Counc~,~..-,
f.Thomas J. Quinn, Chief Administrative Officer
CORPORATE SERVICES DEPARTMENT
MEMORANDUM
August 11, 2004
To:
From:
Subject:
c/Steve Reynolds
Division Head
Culture & Recreation
Len Hunter
Facility Superintendent
Vera A. Felgemacher
Manager, Supply & Services
Tender for PRC Chiller Replacement, PCC Chiller Conversion
Tender No. T - 3 - 2004
Closing: Wednesday, August 11, 2004 2:00 pm
Tenders have been received for the above project. Four companies were
invited to participate. An advertisement was placed in the Daily Commercial
News, News Advertiser Community Page and on the City's Website all of
which yielded interest from additional bidders. Nine bidders picked up
tendering documents for a non-refundable fee of $50.00 per set of which
seven have responded by the closing date and time. Seventeen companies
signed in at the Mandatory Site visit held Wednesday, August 4, 2004.
A copy of the Record of Tenders Opened and Checked used at the public
tender opening is attached.
Purchasing Procedure No. PUR 010-001, Item 10.03 (r) provides checkin9
tendered unit prices and extensions; unit prices shall govern and extensions
will be corrected accordingly, which has been done.
Tender No. %3-2004
Steve ReYnolds
August 1 1,2004
Page 2
SUMMARY
PST included* / GST extra
The amounts do not include any amount for the Goods & Services Tax (GST).
Other taxes and duties either included or excluded are in accordance with the
contract documents.
* confirmed with Totten Sims Hubioki
Harold R. Stark, Div of William Stark Group 599,169.00 599,169.00
Ganadian Tech Air Systems 617,924.00 617,924.00
849060 Ontario Inc. - Air Con Systems 658,104.00 658,104.00
York International 679,413.00 679,413.00
Nekison Engineering & Contractors Ltd. 893,000.00 .893,000.00
LCD Mechanical Rejected: Bid bond insufficient.
Reference: lB 17, 18, 19, TS 3,
Addendum #1- Item 1.1, PUR 010-
001,10.04 Item 9(d)
RTIC Technology Unable to Bid
Pursuant to Information to Bidders Item 21, the following are being requested of the
Iow bidder for your review during the evaluation stage of this tender call:
a) A copy of the Health & Safety Policy to be used on this project;
b) A copy of the current Cost and Frequency Report issued by Workplace
Safety & Insurance Board (in lieu of the Cost and Frequency document, a
copy of the current CAD 7, NEER, or MAP reports may be submitted);
c) A copy of the current Certificate of Clearance issued by Workplace Safety
& Insurance Board; and
d) The City's certificate of insurance completed by the bidder's agent, broker
or insurer. (Received w/th tenden;ng document for review purposes)
Dun & Bradstreet mpod for Haroid R, Stark, a division of \/Villiarn Stark Group,
Tender No. T-3-2004
.Steve Reynolds
August 1 1,2004
Page 3
Please review the copies of the bids. Include the following items in your Report to
Council:
(a) if items (a) through (c) noted above, are acceptable to the Safety &
Training Co-ordinator;
(b) any past work experience Harold R. Stark, a division of William Stark
Group, including work location;
(c) without past work experience, if reference information is acceptable;
(d) the appropriate account number(s) to which this work is to be charged;
(e) the budget amount(s) assigned thereto;
(f) Treasurer's confirmation of funding - including reference to Debt
Financing if applicable;
(g) related departmental approvals;
(g) any reason(s) why the Iow bid of Harold R. Stark, a division of William
Stark Group is not acceptable;
(i) and related comments specific to the project.
Totten Sims Hubicki & Associates as the oonsultants on this project will be
reviewing submissions and making recommendations to you. The consultant
should also review carefully all submittal information based on tendering
instructions. If the consultant notices any infractions or information missing during
the evaluation, please contact me or a member of Supply & Services as soon as
possible.
If you require further information, please feel free to contact me.
·
Ve cher
Manager, Supply & Services
/V
Attachments
Copy for: Director, Operations & Emergency Services
C
Ld Z
engineers
architects
planners
oq
Totten Sims Hubicki Associates
300 Water Street
WMtby, Ontario, Canada L1N SJ2
(90E) 668-~383 Fax: (905) 668-0221
E-maih tsh~tsh.ca www.tsh,ca
August 19, 2004
Leu Hunter
Supervisor, Facilities Operations
Cullure and Recreation Division
City of ?~ekering
One the Esplanade
Picketing, ON
LIV 6K7
Dear Mr, Hunter:
Re: Reference review of Low Tender for T-3-2004
Picketing Recreation CompLex Chiller Replacement and Civic Centre Chiller Convrsion
TSI-I Prolect No.22-14274
TSH has been requested to perform a review of the three references, which were listed in the Tendc'r
submitted by H.R. Stark Mechanical Ltd. for the above -acted project.
We }tare contacted 'the establishments of the Corporation of the Town of Cobo'urg, Sir Sanford Fleming
College and Dacon Construction in an attempt to discuss matters with the listed contact person.
It appears that vacations have interfered in our attempts to gain direct discussions with the listed contact
personnel however we have end=avoured to contact additional persons involved with each of the
referenced projects with results as follows:
Town of Cobourg
Both, the contract aAministmtor, Mr. Steve Robinson, and the building maintenance foreman Mrs. Sally
Lablanc have indicated ~hat from an administrative perspeotive II.P... Stark Mechanical has performed
well, on time and without incident. Their technical workmanship was good and met .~atisfactory
completion dates for the buildings staff. Co-ordination was conducted effectively and co-operation was
excellent. H.R. Storks' work ibrces organized the completion of their project and met the cooling needs of
the Town Hall, which is also a Heritage Building.
Name, Muni¢ipalil'y
August 19, 2004
Sir Sandford Fleming College
Mr. MacPherson reports that the college was vea-y pleased w~th the workmanship and the timely
completion of their new Natural Resources Wing, Few problems arose during construction and any
equipment warr~ issues were dealt with immediately. They can not give any negative accounts or
issues, which they recollect, concerning H.R.Star~' performance. Mr. Msc?herson would recommend
H.R.Stark Mechanical for any furore mechanical work they may require.
H.R. Stark has s~,tisfactorily completed projects with TSI-I in the past and it is expedited that this record
will continue. The listed sub contractors for this project have also been utilized on the previous projects
completed for TSH,
We therefore recommend that the City of Picketing award the tender for T-3-2003 to H.K. Stark in the
tot~l m-noun.t of $599,169.00 (GST included).
'We trust this information is satisfactory for your purposes.
Yours very truly,
Mark A. Be-nedet, P.Eng.
Mechanical Manager
,qT'l ACHMI':N i q
SUBJECT
BUILDING
OPERATIONS & EMERGENCY
SERVICES DEP,A_P,.TMENT.
MUNICIPAL PROPERTY K
SCALE:
ENGINEERING DIVISION
1:3000 August 27/2004
REPORT
TO COUNCIL
CHILLER SYSTEM CONVERSION
PtCKERING CIVIC COMPLEX
,/
SUBJECT
OPERATIONS & EMERGENCY
· SERVICES DEPARTMENT
MUNICIPAl PROPER'FY' &
ENGINEERING DIVISION
1:3000 j August 27~2004
~N B,&KER C,,OU FR~~~__
REPORT TO COUNCIL
CHILLER SYSTEM REPLACEMENT
PICKERING RECREATION COMPLEX