HomeMy WebLinkAboutINF 08-26
Report to
Council
Report Number: INF 08-26
Date: April 27, 2026
From: Kevin Heathcote
Director, City Infrastructure
Subject:
Finch Avenue New Sidewalk Construction
Request for Quotation No. Q2026-4
File: A-1440-001
Recommendation:
1. That the quotation submitted by Avion Construction Group Inc. in response to Request for
Quotation No. Q2026-4 for the Finch Avenue New Sidewalk Construction, in the amount of
$86,283.00 (net HST) or $95,813.00 (HST included) be accepted;
2. That the total gross project cost of $131,469.00 (HST included), including the quotation
amount, a construction contingency and other associated costs, and the total net project
cost of $118,392.00 (net HST) be approved;
3. That the Director, Finance & Treasurer be authorized to finance the total net project cost of
$118,392.00 as follows:
a. That the sum of $75,000.00 as approved in the 2024 Sidewalks Capital Budget be
increased to $118,392.00 and be funded from the Canada Community Building Fund
(CCBF) Reserve Fund; and,
4. That the appropriate officials of the City of Pickering be authorized to take the actions
necessary to implement the recommendations in this report.
1.0 Executive Summary:
The purpose of this report is to obtain Council approval to award Request for Quotation No.
Q2026-4 for the Finch Avenue New Sidewalk Construction to Avion Construction Group Inc.
As part of the 2024 Sidewalks Capital Budget, the construction of a new sidewalk along the
north boulevard of Finch Avenue from Altona Road to the existing sidewalk terminus, east of
Altona Road, was approved to improve pedestrian safety and connectivity in a rapidly
developing area. Request for Quotation No. Q2026-4 was advertised on the City’s
bids&tenders portal on Monday, February 2, 2026, and closed on Wednesday, February 25,
INF 08-26 April 27, 2026
Page 2
2026 with 32 bidders responding. The lowest compliant bid of $86,283.00 (net HST) or
$95,813.00 (HST included) submitted by Avion Construction Group Inc. is recommended for
approval.
The total gross project cost which includes the quotation amount, a construction contingency,
and other associated costs is estimated at $131,469.00 (HST included) with an estimated total
net project cost of $118,392.00 (net HST).
2.0 Relationship to the Pickering Strategic Plan:
The recommendations in this report respond to the Pickering Strategic Plan Priority of Advance
Innovation & Responsible Planning to Support a Connected, Well-Serviced Community.
3.0 Financial Implications:
1. Quotation Amount
Quotation No. Q2026-4 $84,790.00
HST (13%)
Total Gross Quotation Amount
HST Rebate (11.24%)
Total Net Quotation Cost
11,023.00
$95,813.00
($9,530.00)
$86,283.00
2. Estimated Project Cost Summary
Quotation No. Q2026-4 $84,790.00
Associated Costs
Topographic Survey and Base Plan
TRCA Permit Fees
Materials Testing
Pedestrian Signal Upgrades
CCBF Sponsor Signage
3,975.00
4,070.00
3,000.00
8,000.00
2,334.00
Construction Contingency (12%) 10,175.00
Sub Total – Project Costs $116,344.00
HST (13%) 15,125.00
Total Gross Project Cost $131,469.00
HST Rebate (11.24%) (13,077.00)
Total Net Project Cost $118,392.00
INF 08-26 April 27, 2026
Page 3
3. Approved Expense Account
Expenditure Account Source of Funds Budget Required
C10515.2403.504600 CCBF Reserve Fund $75,000.00 $118,392.00
Net project cost (over) under approved funds ($43,392.00)
4.0 Discussion:
The purpose of this report is to obtain Council approval to award Request for Quotation No.
Q2026-4 for the Finch Avenue New Sidewalk Construction to Avion Construction Group Inc.
The City previously completed sidewalk construction along both Altona Road and Finch
Avenue in 2023 in response to ongoing community concerns regarding pedestrian safety.
Rapid residential growth in the area significantly increased pedestrian activity, particularly
among students walking to Westcreek Public School. Prior to these improvements, pedestrians
were required to walk along gravel shoulders adjacent to high-speed traffic. The new sidewalk
is set back from the roadway with an appropriate safety buffer and has established a safer and
more defined pedestrian corridor. The Finch Avenue project also connects with the ongoing
Altona Road sidewalk, forming a more continuous and accessible walking network in the area.
As part of the 2024 Sidewalks Capital Budget, Finch Avenue New Sidewalk Installation –
Intersection Connectivity Project has been identified as a priority construction initiative to
enhance pedestrian mobility and safety in the area surrounding Finch Avenue and Altona
Road. The original scope consisted of a sidewalk connection from the existing sidewalk
terminus on the north side of Finch Avenue, west of Mapleview Court, to the northeast corner
Altona Road and Finch Avenue. During design, it was identified that accessibility
improvements at the intersection were required to provide safe pedestrian connectivity through
the intersection and to sidewalks at the northwest corner. This includes tactile plates, improved
pedestrian signals and push buttons and additional line paint. The proposed works will
continue to improve the Finch / Altona corridor for pedestrians, reducing the need for
pedestrians to walk along roadway shoulders.
Request for Quotation No. Q2026-4 was advertised on the City’s bids&tenders portal on
Monday, February 2, 2026, and closed on Wednesday, February 25, 2026 with 32 bidders
responding. The lowest compliant response of $86,283.00 (net HST) or $95,813.00 (HST
included) submitted by Avion Construction Group Inc. is recommended for approval. The total
gross project cost which includes the quotation amount, a construction contingency, and other
INF 08-26 April 27, 2026
Page 4
associated costs is estimated at $131,469.00 (HST included) with an estimated total net
project cost of $118,392.00 (net HST).
Upon careful examination of all bids and relevant documents received, the City Infrastructure
Department recommends acceptance of the lowest compliant response submitted by Avion
Construction Group Inc. for Request for Quotation No. Q2026-4 in the amount of $86,283.00
(net HST) or $95,813.00 (HST included), and that the total net project cost of $118,392.00 (net
HST) be approved.
Attachment:
1. Location Map
Prepared By: Cynthia Islam, Manager, Capital Projects & Infrastructure
Approved/Endorsed By: Kevin Heathcote, Director, City Infrastructure
Approved/Endorsed By: Cathy Bazinet, Manager, Procurement
Approved/Endorsed By: Stan Karwowski, Director, Finance & Treasurer
CI:mjh
Recommended for the consideration of Pickering City Council By:
Marisa Carpino, M.A.
Chief Administrative Officer
Attachment 1 to Report INF 08-26