HomeMy WebLinkAboutINF 05-26 Report to Executive Committee Report Number: INF 05-26 Date: April 7, 2026 From: Kevin Heathcote Director, City Infrastructure Subject: Pike Court Storm Sewer Works Request for Quotation No. Q2026-3 File: A-1440-001 Recommendation: 1. That the quotation submitted by Zilli Construction Ltd. in response to Request for Quotation No. Q2026-3 for Pike Court Storm Sewer Works, in the amount of $76,015.00 (net HST) or $84,411.00 (HST included) be accepted; 2. That the total gross project cost of $96,235.00 (HST included), including the tendered amount, a construction contingency and other associated costs, and the total net project cost of $86,663.00 (net HST) be approved; 3. That Council authorize the Director, Finance & Treasurer to finance the total net project cost of $86,663.00 as follows: a. that the amount of $50,000.00 for capital project C10525.2505 Pike Court Storm Sewer Works as approved in the 2025 Capital Budget to be funded by a transfer from Stormwater Management Reserve Fund; b. that additional funds of $36,663.00 for capital project C10525.2505 to be approved by a transfer from the Stormwater Management Reserve Fund; and, 4. That the appropriate officials of the City of Pickering be authorized to take the actions necessary to implement the recommendations in this report. 1.0 Executive Summary: The purpose of this report is to award Request for Quotation No. Q2026-3 for Pike Court Storm Sewer Works to Zilli Construction Ltd. As part of the 2025 Stormwater Management Capital Budget, Pike Court Storm Sewer Works was approved as a construction project. The scope of this project includes installation of a rear yard catchbasin to relieve associated flooding on private property and connect to the existing storm sewer on Rosebank Road. This will also provide storm sewer connection for future residential development on Pike Court. INF 05-26 April 7, 2026 Page 2 To facilitate the installation of these works, an easement is required over the vacant Pike Court lot. This easement will allow for the installation of a catchbasin that can connect to the existing pipe between the properties and provide access to the rear yards of 464 and 466 Rosebank Road as well as future maintenance access. Request for Quotation No. Q2026-3 was advertised on the City’s bids&tenders portal on Monday, January 12, 2026, and closed on Tuesday, February 3, 2026, with 26 bids submitted. The lowest compliant bid of $76,015.00 (net HST) or $84,411.00 (HST included) submitted by Zilli Construction Ltd. is recommended for approval, subject to the receipt and approval of all pre-conditions of award required in accordance with the bid document. The total gross project cost which includes the tendered amount, a construction contingency, and other associated costs is estimated at $96,235.00 (HST included) with an estimated total net project cost of $86,663.00 (net HST). 2.0 Relationship to the Pickering Strategic Plan: The recommendations in this report respond to the Pickering Strategic Plan Priority of Advance Innovation & Responsible Planning to Support a Connected, Well-Serviced Community. 3.0 Financial Implications: Quotation Amount Quotation Q2026-3 HST (13%) $74,700.00 9,711.00 Total Gross Quotation Cost HST Rebate (11.24%) Total Net Quotation Cost $84,411.00 (8,396.00) $76,015.00 Estimated Project Cost Summary Quotation Q2026-3 Associated Costs Material Testing Construction Contingency (12%) Sub-total $74,700.00 1,500.00 8,964.00 $85,164.00 HST (13%) Total Gross Project Cost 11,071.00 $96,235.00 HST Rebate (11.24%) (9,572.00) Total Net Project Cost $86,663.00 INF 05-26 April 7, 2026 Page 3 Approved Source of Funds Description Account Code Source of Funds Available Budget Required Pike Court Storm Sewer Works C10525.2505 504550 SWM Reserve Fund $50,000.00 $86,663.00 Total Funds $50,000.00 $86,663.00 Project Cost under (over) approved funds by ($36,663.00) 4.0 Discussion: The purpose of this report is to award Request for Quotation No. Q2026-3 for Pike Court Storm Sewer Works to Zilli Construction Ltd. The project addresses a longstanding rear‑yard drainage issue affecting properties on Rosebank Road and Pike Court, where a temporary drainage configuration established during the 2016 subdivision build‑out is no longer functioning as intended. The proposed works will provide an interim engineered solution to mitigate flooding impacts until full redevelopment of Pike Court occurs. The project supports the City’s ongoing efforts to address localized drainage concerns and maintain safe and reliable stormwater infrastructure. The drainage configuration affecting the Pike Court and south Rosebank neighbourhood existed prior to the development of Staghorn Drive, Maitland Drive, and Pike Court. While the subdivision development intercepted much of the overland flow north of Staghorn Drive, drainage impacts south of Staghorn Drive remain. In 2016, the properties at 464 and 466 Rosebank Road were developed with a temporary swale system. At that time, a pipe capped at both ends was installed between these two properties to allow for the future installation of a storm sewer that would capture drainage from the lands behind the lots once Pike Court was extended further south. The rear yard catch basin (RYCB) system could not be connected to the Rosebank Road storm sewer due to downstream capacity constraints and full storm system upgrades were anticipated as part of the future redevelopment and extension of Pike Court. However, the anticipated redevelopment has not progressed as originally expected. Over time, drainage conditions have progressively worsened, resulting in severe flooding impacts on nearby properties. As a result, staff have identified the need for an interim engineered solution, including the installation of a ditch inlet and storm sewer connection, to help mitigate flooding risks until long-term redevelopment occurs. To facilitate the installation of these works, an easement is required over a portion of the vacant Pike Court lot. This easement will allow for the installation of a catchbasin that can INF 05-26 April 7, 2026 Page 4 connect to the existing pipe between the properties and provide access to the rear yards of 464 and 466 Rosebank Road. Request for Quotation No. Q2026-3 was advertised on the City’s bids&tenders portal on Monday, January 12, 2026, and closed on Tuesday, February 3, 2026, with 26 bids submitted. The lowest compliant bid of $76,015.00 (net HST) or $84,411.00 (HST included) submitted by Zilli Construction Ltd. is recommended for approval, subject to the receipt and approval of all pre-conditions of award required in accordance with the bid document. The total gross project cost which includes the tendered amount, a construction contingency, and other associated costs is estimated at $96,235.00 (HST included) with an estimated total net project cost of $86,663.00 (net HST). Upon careful examination of all bids and relevant documents received, the City Infrastructure Department recommends acceptance of the lowest compliant bid submitted by Zilli Construction. Ltd. for Request for Quotation No. Q2026-3 in the amount of $76,015.00 (net HST) or $84,411.00 (HST included), and that the total net project cost of $86,663.00 (net HST) be approved. Attachments: 1. Location Map Prepared By: Cynthia Islam, Manager, Capital Projects & Infrastructure Approved/Endorsed By: Cathy Bazinet, Manager, Procurement Approved/Endorsed By: Kevin Heathcote, Director, City Infrastructure Approved/Endorsed By: Stan Karwowski, Director, Finance & Treasurer CI:mjh Recommended for the consideration of Pickering City Council By: Marisa Carpino, M.A. Chief Administrative Officer Attachment 1 to Report INF 05-26