HomeMy WebLinkAboutCS 08-26
Report to
Council
Report Number: CS 08-26
Date: March 23, 2026
From: Laura Gibbs
Director, Community Services
Subject:
Construction for Dunbarton Indoor Pool Roof & Structure Replacement
Request for Tender No. T2026-1
File: A-1440-001
Recommendation:
1. That the bid submitted by Triumph Roofing & Sheet Metal Inc. in response to Request for
Tender No. T2026-1 for the Construction for Dunbarton Indoor Pool Roof Replacement, in
the amount of $2,765,836.80 (net HST) or $3,071,340.00 (HST included) be accepted;
2. That the total gross project cost of $3,719,508.00 (HST included), including the amount of
the tender, construction contingency, and other associated costs, and the total net project
cost of $3,349,532.00 (net HST) be approved;
3. That the Director, Finance & Treasurer be authorized to finance the net project cost of
$3,349,532.00 to be funded from Casino Reserve as approved in the 2025 and 2026
Capital Budgets;
4. That the Director, Community Services be authorized to execute the CCDC-2, 2020
Stipulated Price Contract with the above-mentioned contractor pursuant to Request for
Tender No. T2026-1; and,
5. That the appropriate officials of the City of Pickering be authorized to take the actions
necessary to implement the recommendations in this report.
1.0 Executive Summary:
The purpose of this report is to award construction services and related work for the Roof &
Structure Replacement at Dunbarton Indoor Pool (DIP).
Construction work is required for the DIP roof, including full replacement of the existing
reinforced autoclaved aerated concrete (RAAC) roof decking. As identified in previous
engineering assessments, the original roof structure—constructed in 1971 and composed of
RAAC panels—is at the end of its serviceable life span and requires replacement.
CS 08-26 March 23, 2026
Page 2
Request for Tender No. T2026-1 was advertised on the City’s bids&tenders portal on January
14, 2026, and closed on February 13, 2026. Three contractors were pre-qualified under
RFSQ2025-5. All three pre-qualified proponents submitted bids. Subject to receipt and
approval of all pre-conditions of award required in accordance with the bid document, the
lowest compliant bid submitted by Triumph Roofing & Sheet Metal Inc. in the amount of
$2,765,836.80 (net HST) or $3,071,340.00 (HST included), is recommended for approval. The
total gross project cost is estimated to be $3,719,508.00 (HST included), and the total net
project cost is estimated at $3,349,532.00 (net of HST rebate).
2.0 Relationship to the Pickering Strategic Plan:
The recommendations in this report respond to the Pickering Strategic Plan Priority of
Advocate for an Inclusive, Welcoming, Safe & Healthy Community.
3.0 Financial Implications:
Tender Amount
Tender T2026-1
$2,718,000.00
HST (13%) $353,340.00
Total Gross Tender Cost $3,071,340.00
Estimated Project Costing Summary
Tender T2026-1
$2,718,000.00
Consulting Contingency Costs 30,000.00
Contingency (20%) 543,600.00
Total Project Cost $3,291,600.00
HST (13%) 427,908.00
Total Gross Project Cost $3,719,508.00
HST Rebate (11.24%) (369,976.00)
Total Net Project Cost $3,349,532.00
CS 08-26 March 23, 2026
Page 3
Approved Source of Funds – Community Services Capital Budget
Approved Code Source of Funds Funds Available Funds Required
C10210.2501 Casino Reserve 4,010,000.00 3,349,532.00
Total Funds 4,010,000.00 $3,349,532.00
Project Cost under (over) approved funds by $660,468.00
A higher-than-normal contingency has been included in the Estimated Project Costing
Summary to allow for concealed conditions that could affect the work, due to the age and
condition of the building, and the time-sensitive nature of this work. Unspent funds will be
returned to source.
Consulting contingency in the amount of $30,000 has been included in the budget. The original
project budget awarded for design consultation in Report OPS 03-25 has been exhausted.
Additional funds have been included in the total project budget to complete design consultation
should any unforeseen circumstances arise through the construction phase of this project.
4.0 Discussion:
The purpose of this report is to award construction services and related work for the Roof &
Structure Replacement at DIP. DIP was constructed in 1971, internally renovated in 2008, and
miscellaneous repairs were completed in 2015. The pool roof structure is constructed of
reinforced autoclaved aerated concrete (RAAC) roof decking spanning between laminated
timber beams. The Ministry of Education issued a 2023 memorandum stating that buildings
that contain RAAC shall require investigation, assessment and a management strategy for the
RAAC due to concerns for potential spontaneous structural failure. In many cases, the product
is being removed altogether because of risks associated with potential sudden structural
failure.
4.1 Project Background
Professional structural reviews were performed in 2020 and 2023 by Barry Bryan Associates
(BBA), concluding that the structure was in good condition at the time of inspection. The 2023
report additionally noted that professional engineering inspections of the DIP roof structure be
conducted annually.
During the 2024 annual inspection, also conducted by BBA, they concluded that immediate
repairs were required due to large ponding on the pool roof, supported by the RAAC structure.
Ponding could freeze during colder seasons. Combined with a full snow load, this added
CS 08-26 March 23, 2026
Page 4
weight could cause failure of the roof deck or supporting structure. Accordingly, immediate
emergency repairs were conducted in fall 2024 as authorized in Resolution #612/24 (Report
OPS 21-24). The 2024 annual inspection also concluded that the RAAC system was
approaching or at the end of its serviceable life span and required intervention. Given the age
and condition of the building, the process for full roof replacement was initiated. Design was
authorized in Resolution #693/25 (Report OPS 03-25).
4.3 Procurement Process
Contractors were prequalified through RFSQ2025-5, to ensure that bidders would have
sufficient expertise in the handling of these types of structures, and depth of resources
required to undertake sensitive work in proximity to Dunbarton High School. The pool roof is
physically connected to the school. Staff have coordinated efforts with the Durham District
School Board (DDSB) during the design phase to minimize potential risk or disruptions to the
school as a result of this work. Coordination will continue in the construction phase. The award
of this contract now will help ensure that required materials will arrive on site in advance of
construction commencing in early July. The work is expected to be completed by October
2026.
Request for Tender No. T2026-1 was advertised on the City’s bids&tenders portal on January
14, 2026, and closed on February 13, 2026. Three contractors pre-qualified under RFSQ2025-
5. All three pre-qualified proponents submitted bids. Subject to receipt and approval of all pre-
conditions of award required in accordance with the bid document, the lowest compliant bid
submitted by Triumph Roofing & Sheet Metal Inc. in the amount of $2,765,836.80 (net HST) or
$3,071,340.00 (HST included), is recommended for approval. The total gross project cost is
estimated to be $3,719,508.00 (HST included), and the total net project cost is estimated at
$3,349,532.00 (net of HST rebate).
4.4 Service Disruptions and Communications with DDSB
Dunbarton Pool is owned by the City of Pickering and operates from 5:30 am to 9:30 pm from
September to June, with reduced hours of operation during the summer months. The pool
accommodates swimming lessons, accommodating 2,530 participants in 2025 with a waitlist of
614 people. The Pickering Swim Club and Masters Swim Club rentals accommodate
approximately 250 swimmers. Four hours of open swim and lane swim are also offered
weekly.
To accommodate the service disruption due to construction, learn to swim programs will be
added on Sunday mornings at Chestnut Hill Developments Recreation Complex (CHDRC).
Some lane swim times will be cancelled at CHDRC to allow aquatic certification courses.
These classes provide required training for employment as a lifeguard or an instructor.
The City has an existing Reciprocal use of Facilities Agreement (CS 27-25) with the DDSB that
allows for shared use of parks and facilities in Pickering. With respect to Dunbarton Indoor
Pool and Dunbarton High School, the arrangement allows for the Board to use the pool for
CS 08-26 March 23, 2026
Page 5
educational, athletic and recreational purposes from Monday to Friday during the school day
and year. Dunbarton High School specifically uses the pool for gym classes, swim team
practices and outdoor education water safety orientations. In exchange, the City uses the
Dunbarton High School gym to provide recreation programs to residents including volleyball,
badminton and a summer sports camp that has operated in this location for decades. During
this service disruption, City programs will be relocated to Eastshore Community Centre for
summer 2026.
Staff have held several meetings with the Principal of Dunbarton High School and the DDSB
Project Supervisor through project design and planning to ensure that service disruption to the
school is minimized. Meetings and communication will continue through construction.
Attachment: None.
Prepared By:
Dennis Yip, Manager, P.Eng., PMP®, CEM, LEED® AP, Facilities Capital Projects
Vince Plouffe, OAA, MRAIC, Division Head, Facilities Management & Construction
Approved/Endorsed By:
Laura Gibbs, MBA, MSc., Director, Community Services
Cathy Bazinet, CPPB, NIGP-CPP, Manager, Procurement
Stan Karwowski, MBA, CPA, CMA, Director, Finance & Treasurer
LG:vp
Recommended for the consideration of Pickering City Council By:
Marisa Carpino, M.A.
Chief Administrative Officer