HomeMy WebLinkAboutCS 34-25Report to
Executive Committee
Report Number: CS 34-25
Date: December 1, 2025
From: Laura Gibbs
Director, Community Services
Subject: Additional Funds for Chestnut Hill Developments Recreation Complex Roof and
Skylight Replacement
Second-Stage Request for Quotation No. RFQQ2025-5
File: A-1440-001
Recommendation:
1. That Report CS 34-25 regarding Additional Funds for Quotation No. RFQQ2025-5 for the
Chestnut Hill Developments Recreation Complex Roof and Skylight Replacement be
received;
2.That additional costs in the amount of $303,260.00 (net of HST rebate) over the original
estimated project cost f or RFQQ2025-5 (Report CS 08-25) for Chestnut Hill
Developments Recreation Complex Roof and Skylight Replacement resulting in a revised
total net project cost of $2,074,189.00 (net of HST rebate) be approved;
3.That the Director, Finance & Treasurer be authorized to finance the net project cost of
$2,074,189.00 to be funded from the Canada Community Building Fund (CCBF) (FGT)
Oblg RF as approved in the 2025 Capital Budget; and,
4.That the appropriate officials of the City of Pickering be authorized to take the necessary
actions as indicated in the report.
Executive Summary: The purpose of this report is to request additional funding for the
Chestnut Hill Developments Recreation Complex (CHDRC) Roof and Skylight Replacement,
as originally awarded under Report CS 08-25, Resolution #743/25. The additional funding is
required to address flaking ceiling materials that arose during the course of construction.
During the replacement of roof area D, ceiling materials were observed to be flaking down
below the construction areas. Out of an abundance of caution, all construction activities were
immediately suspended to prevent potential exposure of ceiling materials to staff, contractors,
and facility users.
To allow the project to safely proceed, additional funding is required to implement appropriate
measures. This includes the installation of plastic tarping to capture any materials dislodged
from the ceiling, and testing air/dust during construction for hazardous materials. These
measures are necessary to ensure full compliance with health and safety requirements and to
protect all occupants and workers during the continuation of the project.
CS 34-25 December 1, 2025
Page 2
Approval of this report will authorize an increase to the project funds, thereby enabling staff to
implement these health and safety measures and to resume the CHDRC Roof and Skylight
Replacement project in a safe and compliant manner.
Relationship to the Pickering Strategic Plan: The recommendations in this report respond
to the Pickering Strategic Plan Priorities of Advocate for an Inclusive, Welcoming, Safe &
Healthy Community; and, Advance Innovation & Responsible Planning to Support a
Connected, Well-Serviced Community.
Financial Implications:
1. Council Report Number CS 08-25 Approved Amount
RFQQ2025-5
Testing and inspection
Consulting
Contingency
$1,470,300.00
30,000.00
65,000.00
175,000.00
Total Project Cost
HST (13%)
$1,740,300.00
226,239.00
Total Gross Project Costs
Less : HST Rebate (11.24%)
Total Net Project Cost
$1,966,539.00
($195,610.00)
$1,770,929.00
2. Estimated Project Costing Summary
Original Award (RFQQ2025-5), May 26, 2025 $1,470,300.00
Committed testing and inspection 10,370.00
Committed consulting 35,500.00
Committed contingency 99,535.00
Original Award (RFQQ2025-5) and commitments to-date $1,615,705.00
Remaining contingency , testing/inspection and consulting 124,595.00
Sub-total (CS 08-25) $1,740,300.00
Additional Costs
Additional Testing and Inspection Costs 20,000.00
Additional Consulting Costs 20,000.00
Estimated Additional Tarping Costs 158,015.00
Additional Contingency 100,000.00
Total Project Cost $2,038,315.00
HST (13%) 264,981.00
Total Gross Project Costs $2,303,296.00
HST Rebate (11.24%) (229,107.00)
CS 34-25 December 1, 2025
Page 3
Total Net Project Cost $2,074,189.00
3. Approved Source of Funds – Community Services Capital Budget
Approved Code Source of Funds Funds Available Funds Required
C10225.2406 CCBF (FGT) Oblg RF $2,600,000.00 $2,074,189.00
C10225.2406 Facilities Reserve 40,000.00 0.00
Total Funds $2,640,000.00 $2,074,189.00
The unused funds of $565,811.00 will be “Returned to Source” and therefore, will be available
to fund future Capital projects. These capital accounts will be closed after the construction
period.
While preliminary testing and investigation was conducted, the precise conditions within the
roof assembly could not be confirmed prior to tender. Due to the potential high cost of repairing
any existing roof conditions that might be encountered and maintaining appropriate health and
safety measures, a higher than standard contingency has been requested for this project.
Discussion: The purpose of this report is to request additional funds for construction and
related costs for the CHDRC Roof and Skylight Replacement project, as originally awarded
under Report CS 08-25, Resolution #743/25. The additional funding is required to address
flaking of ceiling materials that arose during the course of construction.
1. Project Background
The purpose of this project is to replace the roof and skylights over areas “D, D1, and I4” at the
CHDRC as they are at end of life and require replacement. This includes the roofs and
skylights over the main lobby, banquet hall, fitness area and adjoining spaces. Most were
installed in 2002 and have already seen extensive localized repairs. Full replacement is now
required.
As per Report CS 08-25 (CHDRC Roof and Skylight Replacement), Resolution #743/25, a
construction contract was awarded to Solar Roofing & Sheet Metal Ltd. for the replacement of
roof and skylights at areas D, D1, and I4. The project involves providing all necessary labour,
materials, and equipment to replace the aged roofing systems. Work was carried out primarily
over the summer, with efforts made to minimize disruptions to facility operations, and some
short-term localized closures expected for safety during skylight replacement. The project
budget includes consulting and design costs, with additional site inspections planned to ensure
quality control and adherence to contract specifications for this critical building infrastructure.
Project Cost under (over) approved funds by
$565,811.00
CS 34-25 December 1, 2025
Page 4
2.Containment and Control Measures
During replacement of roof area D, loose ceiling paint was seen to be flaking down below the
construction areas. As lead is a designated substance under the Occupational Health and
Safety Act, all construction activities were immediately suspended to prevent potential
exposure to staff, contractors, and facility users.
Staff engaged Chem Solv , a designated substances testing firm, who tested the materials that
fell from the ceiling. Chem Solv confirmed the presence of lead in large strips of paint that
became disengaged from the ceiling. Chem Solv and the project consultant have confirmed
that tarping and HVAC isolation measures are appropriate and effective mitigation strategies to
manage the flaking ceiling materials.
To safely resume work, the project requires the implementation of containment and control
measures. This includes the installation of plastic tarping to capture any potentially hazardous
materials and safe disposal of the tarp/lead flakes in accordance with regulatory requirements.
A quote for $158,015.00 for tarping was received from Solar Roofing & Sheet Metal Ltd. A
third-party cost review has verified that the contractor’s proposed pricing for the tarping
solution is fair and reasonable. HVAC isolation measures include disabling localized air vent
inlets to prevent entrainment into the ducting and disabling localized diffuser outlets to prevent
dispersing dust fall. Additional air and dust testing will also be conducted during the project to
confirm that the air and dust is free of lead. Extending the construction schedule will also incur
additional contract administration fees from the project consultants to ensure compliance with
the design and tender documents.
3.Project Timing
Approval of this report will authorize an increase to the project’s funds, allowing the project to
be completed in a safe manner compliant with health and safety requirements.
Work will continue in phases, with efforts made to minimize service disruptions and provide
advance notice of any short-term , localized closures. Completion of the roof and skylight
replacement project is scheduled for summer 2026.
Attachment: None.
Prepared By: Approved/Endorsed By:
Original Signed By Original Signed By
Dennis Yip, P.Eng., PMP®, CEM, LEED® AP Vince Plouffe, OAA, MRAIC
Manager, Facilities Capital Projects Division Head, Facilities Management
& Construction
CS 34-25 December 1, 2025
Page 5
Approved/Endorsed By:
Original Signed By
Cathy Bazinet, CPPB, NIGP-CPP
Manager, Procurement
Original Signed By
Laura Gibbs, MBA, MSc.
Director, Community Services
Original Signed By
Stan Karwowski, MBA, CPA, CMA
Director, Finance & Treasurer
LG :dy
Recommended for the consideration
of Pickering City Council
Original Signed By
Marisa Carpino, M.A.
Chief Administrative Officer