HomeMy WebLinkAboutENG 10-23Report to Council
Report Number: ENG 10-23
Date: June 26 2023
From: Richard Holborn
Director, Engineering Services
Subject: Asphalt Resurfacing on Various City Streets (Phase 2)
- Tender No. T2023-9
- File: A-1440
Recommendation:
1.That Tender No. T2023-9 for Asphalt Resurfacing on Various City Streets (Phase 2) as
submitted by Four Seasons Site Development Ltd. in the total tendered amount of
$654,678.61 (HST included) be accepted;
2.That the total gross project cost of $779,728.00 (HST included), including the tendered
amount, material testing, a contingency and other associated costs, and the total net
project cost of $702,169.00 (net of HST rebate) be approved;
3.That Council authorize the Director, Finance & Treasurer to finance the total net project
cost of $702,169.00 as approved in the 2023 Roads Capital Budget to be funded by a
transfer from the Federal Gas Tax Reserve Fund; and,
4.That the appropriate officials of the City of Pickering be authorized to take the necessary
actions as indicated in this report.
Executive Summary: As part of the 2023 Roads Projects Capital Budget, asphalt
resurfacing for the following four locations were approved as construction projects:
•Gwendolyn Street;
•Fuschia Lane;
•Petunia Place; and
•Falconcrest Drive.
As part of the 2016 Road Needs Study endorsed by Council through Report ENG 25-17
(Council Resolution #374/17), these streets have been identified and recommended for
resurfacing improvements. The 2016 Road Needs Study is used by staff as a resource
document for identifying and planning maintenance, rehabilitation and reconstruction
strategies, programs and projects for all Pickering roads. The roads selected for asphalt
resurfacing in 2023 align with the priorities of the 2016 Road Needs Study.
Tender No. T2023-9 was advertised on the City’s Bids & Tenders portal on Tuesday, May 2,
2023, with a tender closing date of Thursday, June 1, 2023. Six companies have submitted a
bid for this project. The low bid of $654,678.61 (HST included) submitted by Four Seasons Site
Development Ltd. is recommended for approval. The total gross project cost is estimated at
ENG 10-23 June 26, 2023
Subject: Asphalt Resurfacing on Various City Streets (Phase 2)
Tender No. T2023-9 Page 2
$779,728.00 (HST included) with an estimated total net project cost of $702,169.00 (net of
HST rebate).
Financial Implications:
1. Tender Amount
Tender No. T2023-9 $579,361.60
HST (13%) 75,317.01
Total $654,678.61
2. Estimated Project Costing Summary
Tender No. T2023-9 – Tender for Asphalt Resurfacing on Various
City Streets (Phase 2) $579,362.00
Associated Costs
Geotechnical Investigation Reports
Materials Testing Services
11,120.00
27,520.00
Federal Gas Tax Sponsor Signage 2,500.00
Construction Contingency (12%) 69,523.00
Sub Total – Costs $690,025.00
HST (13%) 89,703.00
Total Gross Project Cost $779,728.00
HST Rebate (11.24%) (77,559.00)
Total Net Project Cost $702,169.00
3. Approved Source of Funds
Location Expense Code Source of Funds Budget Required
Gwendolyn Street C10570.2319.01-
504400
Federal Gas Tax $270,000.00 $257,062.00
Fuschia Lane C10570.2320.01-
504400
Federal Gas Tax 115,000.00 110,656.00
Petunia Place C10570.2321.01-
504400
Federal Gas Tax 105,000.00 90,738.00
Falconcrest Drive C10570.2322.01-
504400
Federal Gas Tax 255,000.00 243,713.00
$745,000.00 $702,169.00
Net project cost (over) under approved funds $42,831.00
ENG 10-23 June 26, 2023
Subject: Asphalt Resurfacing on Various City Streets (Phase 2)
Tender No. T2023-9 Page 3
Discussion: As part of the 2023 Roads Projects Capital Budget, asphalt resurfacing for
the following locations were approved as construction projects:
•Gwendolyn Street – from Rouge Valley Drive to Fawndale Road;
•Fuschia Lane – from Grenoble Boulevard to Modlin Road;
•Petunia Place – from Gwendolyn Street to North Terminus; and
•Falconcrest Drive – from Dunbarton Road to Rambleberry Avenue.
These streets are indicated in the 2016 Road Needs Study as priority streets for asphalt
resurfacing.
Tender No. T2023-9 was issued on Tuesday, May 2, 2023 and closed Thursday, June 1, 2023.
Six companies submitted a bid for this project. The low bid of $654,678.61 (HST included)
submitted by Four Seasons Site Development Ltd. is recommended for approval. The total
gross project cost is estimated at $779,728.00 (HST included) with an estimated total net
project cost of $702,169.00 (net of HST rebate).
Engineering Services invited material testing companies to provide unit rates for both
Geotechnical Investigation Reports and Materials Testing Services, which the City uses on
various capital projects throughout the year. Based on the unit rates submitted by GHD Ltd.,
their fees estimated for this project are $38,640.00 (HST extra).
Further, in accordance with Purchasing Policy Item 10.03 (b), where written proposals are
obtained by the Director without going through a competitive process, and funds are available
in the approved Budget:
(b)an award between $30,000 and $50,000 is subject to the additional approval of the
Treasurer and the CAO.
The Waste Management Plan submitted by Four Seasons Site Development Ltd. has been
reviewed and is deemed acceptable by the Manager, Capital Projects & Infrastructure. The
City’s Health & Safety Policy form and current Certificate of Clearance issued by the
Workplace Safety & Insurance Board have been submitted by Four Seasons Site Development
Ltd. The Certificate of Insurance has been reviewed by the Division Head, Finance, and is
deemed acceptable. Four Season Site Development Ltd. has previously completed Tender No.
T-4-2018, Asphalt Resurfacing and Tender No. T-4-2019, Asphalt Resurfacing contracts to the
satisfaction of the City. Staff have deemed the company’s experience and professionalism to
be acceptable.
Upon careful examination of all tenders received, the Engineering Services Department
recommends acceptance of the low bid submitted by Four Seasons Site Development Ltd. for
Tender No. T2023-9 in the amount of $654,678.61 (HST included), and that the total net
project cost of $702,169.00 (net of HST rebate) be approved.
ENG 10-23 June 26, 2023
Subject: Asphalt Resurfacing on Various City Streets (Phase 2)
Tender No. T2023-9 Page 4
Attachment:
1.Location Maps
Prepared By: Approved/Endorsed By:
Scott Booker Richard Holborn, P. Eng.
Manager, Capital Projects & Infrastructure Director, Engineering Services
Cathy Bazinet, NIGP-CPP Stan Karwowski, MBA, CPA, CMA
Manager, Procurement Director, Finance & Treasurer
DL:mjh
Recommended for the consideration
of Pickering City Council
Marisa Carpino, M.A.
Chief Administrative Officer
Original signed by:Original signed by:
Original signed by:Original signed by:
Original signed by:
Attachment #1 to Report ENG 10-23
Location Maps
Project Area No. 1 – Gwendolyn Street
Gwendolyn Street – from Rouge Valley Drive to Fawndale Road. The proposed work includes
asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall
be removed and replaced as required.
Project Area No. 2 – Fuschia Lane
Fuschia Lane – from Grenoble Boulevard to Modlin Road. The proposed work includes asphalt
resurfacing. All existing concrete barrier curbs shall be removed and replaced with new
concrete curbs and gutters.
Project Area No. 3 – Petunia Place
Petunia Place – from Gwendolyn Street to North Terminus. The proposed work includes asphalt
resurfacing. Existing concrete curbs and gutters that are deficient shall be removed and
replaced as required.
Project Area No. 4 – Falconcrest Drive
Falconcrest Drive – from Dunbarton Road to Rambleberry Avenue. The proposed work includes
asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall
be removed and replaced as required.