Recommendation:
1.That the additional fee proposal and project costs as submitted by TS Engineering Inc. in
the gross amount of $84,750.00 (HST included), and the net amount of $76,320.00 (net
HST rebate) for the increase in scope of work the replacement of the backup power
generator at the Chestnut Hill Developments Recreation Complex (CHDRC), and
associated costs, be accepted;
2.That the total estimated consulting costs including the amount referenced in
recommendation 1 above, in the amount of $124,819.00, as presented in Table 2, be
approved;
3.That the Director, Finance & Treasurer be authorized to finance the total net consulting
costs of $124,819.00 by undertaking an internal loan for period not exceeding 5 years, and
this source be revised up to 100 per cent funding through a transfer from the Federal Gas
Tax Reserve Fund if deemed eligible by the Association Municipalities of Ontario; and,
4.That the appropriate City of Pickering officials be authorized to take the necessary action to
give effect hereto.
Executive Summary: TS Engineering Inc. was retained by the City in December 2020 under
PO 700753 to develop design and construction documents for replacement of the existing backup
power generator at the Chestnut Hill Developments Recreation Complex (CHDRC). The existing
generator was installed in 2002 and has reached the end of its serviceable life. Backup power is
essential for sustained operation of the building, including maintaining life safety systems, critical
lighting, preserving ice in arenas and for the HVAC systems.
It has been determined that greater generator capacity than originally envisioned is required to
address growing demand and to improve functionality of CHDRC’s banquet hall as an emergency
heating and cooling shelter. This will necessitate an increase in generator size and capacity from
100 kW to 750 kW. Higher equipment capacity also increased its size, requiring that it be mounted
outside of the building, incurring additional costs. For this reason, an additional fee proposal and
project has been submitted by TS Engineering Inc. and is recommended to be approved by way of
this report.
CS 20-21 April 26, 2021
Subject: Request for Additional Funding for Consulting Services
CHDRC Generator Replacement Page 2
Financial Implications:
1. Estimated Project Costing Summary
Original scope of work
(PO 700753, Dec 11, 2020)
$47,660.00
Additional Funding Request:
Construction Contract Admin
$25,000.00
Air and Noise Assessment 20,000.00
Electrical Coordination and Arc Flash Study 10,000.00
Cost Sub-Consultant 8,000.00
Contingency 12,000.00
Subtotal (Additional Costs)
$75,000.00
Total Cost $122,660.00
HST (13%) 15,946.00
Total Gross Project Costs $138,606.00
HST Rebate (11.24%) (13,787.00)
Total Net Project Costs $124,819.00
2. Approved Source of Funds - Community Centres Capital Budget
Approved Code
5731.1902.6500
Total Funds
Source of Funds
Debt - 10-Year
Internal Loan 5-Year
or Fed Gas Tax
Reserve Fund
Funds Available
$1,100,000.00
Funds Required
$0.00
124,819.00
$124,819.00
Project Cost under (over) approved funds by ($975,181.00)
Staff recommend the approval of an increase in the total net HST project cost to $76,320.00
($75,000 plus by net HST) from the amount that was approved by the Chief Administrative Officer
in a memo dated November 25, 2020. Due to the increase in scope, the award to TS Engineering
Inc. will exceed $50,000 and in accordance with the Purchasing Policy, item 10.03 (c), consulting
and professional services above $50,000 is subject to the additional approval of Council. The
initiating Director shall submit the Report to Council to obtain approval.
CS 20-21 April 26, 2021
Subject: Request for Additional Funding for Consulting Services
CHDRC Generator Replacement Page 3
In accordance with the Purchasing Policy item 10.03 (b), the original award of PO 700753 in the
amount of $47,660.00 (HST extra) to TS Engineering Inc. was previously approved by the
Manager, Supply & Services, (Acting) Director, Community Services, Treasurer and the Chief
Administrative Officer. Council approval is being sought at this time for the increase in the total net
project cost amount of $76,320.00 in order to address an increase in the scope of work and
associated costs.
The estimated total consulting costs presented in the report will be financed by an internal loan.
Staff will be in contact with the Association Municipalities of Ontario (AMO) to determine if these
costs can be either funded 100 per cent or partially by Federal Gas Tax (FGT) funding. The City’s
established business process is to seek approval from AMO regarding the use of FGT funding.
Discussion: The existing 100kW backup power generator at CHDRC was installed in 2002
and supplies only a small number of life safety systems throughout the recreation complex. The
unit has reached the end of its serviceable life. Essential components for its ongoing maintenance
are no longer readily available. The City retained TS Engineering Inc. in December 2020 to review
existing system capacity and demand, including projecting for current and future needs not
covered by the existing generator.
A peak demand design load was confirmed and will require a 750 kW generator in order to fully
accommodate all identified needs. The most significant source of increase are critical heating and
cooling systems that must be on backup power for CHDRC to serve as a viable emergency
warming and cooling centre. Provision has been included for the addition of a second generator in
the future, in a temporary or permanent capacity, in order to improve overall infrastructure
capacity and futureproof the system, including built-in climate resiliency. The larger unit will be too
large to fit inside the building, where the current generator is located. It will be located outside, in
the back-of-house area where the main electrical and mechanical plant for CHDRC are directly
accessible.
An air and noise assessment will be needed to ensure that the decibel level of the generator is
within thresholds set by applicable standards, and to minimize disruption to neighbouring buildings
and properties. These additional services significantly increase the original scope of work, which
was based on replacement of the existing interior generator.
Upon careful examination of the received proposal and relevant documents received, the
Community Services Department recommends approval of the proposed increases in consulting
costs for replacement of the backup power generator at CHDRC, in the gross amount of
$84,750.00 (HST included), and the net amount of $76,320.00 (net HST rebate).
Attachment: None
CS 20-21 April 26, 2021
Subject: Request for Additional Funding for Consulting Services
CHDRC Generator Replacement Page 4
Prepared By: Approved/Endorsed By:
Vince Plouffe, OAA, RAIC Ray Rodrigues, CPPB
Manager, Facilities Capital Projects Manager, Supply & Services
Brian Duffield Stan Karwowski, MBA, CPA, CMA
(Acting) Director, Community Services Director, Finance & Treasurer
BD:vp
Recommended for the consideration
of Pickering City Council
Marisa Carpino, M.A.
Chief Administrative Officer
Original Signed By:Original Signed By:
Original Signed By:Original Signed By:
Original Signed By: