Loading...
HomeMy WebLinkAboutCS 11-21Report to Council Report Number: CS 11-21 Date: January 25, 2021 From: Brian Duffield (Acting) Director, Community Services Subject: Pre-budget Approval - Don Beer Arena, Rink 3 Refrigeration Plant Upgrades (Phase 1) -File: A-1440 Recommendation: 1.That Report CS 11-21 from the (Acting) Director, Community Services for pre-budget approval of the Rink 3 Refrigeration Plant Rebuild at Don Beer Arena be received; 2.That Council grant pre-2021 Capital Budget approval and authorize the Director, Finance & Treasurer to fund the sum of $240,000.00 from Federal Gas Tax (FGT) Reserve Fund; and, 3.That the appropriate City of Pickering officials be authorized to take the necessary action to give effect hereto. Executive Summary: In light of an incident in Fernie, British Columbia in 2017, which cost 3 workers their lives, the City has been reviewing the status of all of its arena refrigeration plants for compliance with applicable codes and standards. An engineering review of the refrigeration plant serving Rink 3 at Don Beer Arena, received from TS Engineering Inc. in December 2020, has identified several remedial repairs and recommended the replacement of equipment deemed to be at the end of its useful life. The plant is currently functional and can be maintained until the end of the current ice season, but the recommended work must be completed before it can resume operation for the next ice season. Design work must begin immediately if there is to be any chance of meeting this timeline, and the work must be tendered early enough to allow for the prompt ordering of any equipment with long lead times for delivery. Pre-budget approval is being requested to make available the required funds to proceed with this project, as waiting for the anticipated approval of the 2021 Capital Budget would make it impossible to complete the work in time for the 2021-22 ice season. Estimated costs for the project include $30,000.00 for related consulting and $210,000.00 for construction, including related contingencies, inspection, and related project costs. The total estimated project cost of $240,000.00 (net HST rebate) is to be funded from Federal Gas Tax . A second phase of equipment replacements identified by TS Engineering Inc.’s report will appear in the capital forecast budget for future consideration. The equipment noted for replacement in the second phase was deemed to have several more years of serviceable life. CS 11-21 January 25, 2021 Subject: Pre-Budget Approval – DBA, Rink 3 Refrigeration Plant Upgrades (Phase 1) Page 2 Financial Implications: 1.Sourced of Funds Approved Code 5715.2104.6230 5715.2104.6500 Prof/Consulting Fees Building Related Source of Funds Federal Gas Tax Federal Gas Tax Total Funds 2021 Budget $ 30,000.00 210,000.00 $240,000.00 Discussion: Following the release of the final report investigating the 2017 deaths of 3 workers at Fernie Memorial Arena, staff began a preventative safety and maintenance review of the City’s existing refrigeration plants. Work completed on the Delaney Arena plant at the Chestnut Hill Developments Recreation Complex (CHDRC) in 2016 had already addressed any outstanding concerns. Additional work was completed in 2019 on the O’Brien Arena plant at CHDRC, as well as the single plant serving Rinks 1 and 2 at Don Beer Arena. Both were the result of findings from these condition assessments. A review of the final plant, serving rink 3 at Don Beer Arena, was completed after the replacement of dehumidification equipment in that rink in late 2020. The resulting report identifies a number of improvements required, including upgrades to existing ventilation and the replacement of an existing condenser, pump, and piping. Existing use can be maintained through to the end of the current season, but this work must be completed before the refrigeration plant can resume operations for the 2021-22 season. The Rink 3 refrigeration plant is typically started in mid-August, though this could be pushed back to early September if other pads are available. Once awarded, design work is expected to take 6-8 weeks to complete, to be followed by a formal tender process. There is typically a significant lag time while awaiting the delivery of major equipment on these types of projects. While this normally ranges from 10-12 weeks, the current pandemic has significantly impaired and caused delays to supply chains, and could extend this timeline. Staff will explore options to mitigate the risk of long lead times for delivery. Rink 3 at Don Beer Arena was constructed in 2002. Most of the addition’s major systems are in fair to good condition. Mechanical equipment experiences the greatest wear in these types of facilities and typically starts to reach end of life in the 20-25 year range. The findings of the report provided by TS Engineering Inc. are consistent with these expectations. CS 11-21 January 25, 2021 Subject: Pre-Budget Approval – DBA, Rink 3 Refrigeration Plant Upgrades (Phase 1) Page 3 Prepared By: Approved/Endorsed By: Vince Plouffe Brian Duffield Manager, Facilities Capital Projects (Acting) Director, Community Services Stan Karwowski, MBA, CPA, CMA Director, Finance & Treasurer BD:vp Recommended for the consideration of Pickering City Council Marisa Carpino, M.A. Interim Chief Administrative Officer Original Signed By: Original Signed By: Original Signed By: Original Signed By: