HomeMy WebLinkAboutENG 02-20clia �f DICKERING Report to Council Report Number: ENG 02-20 Date: April 27, 2020 From: Richard Holborn Director, Engineering Services Subject: Asphalt Resurfacing on Various City Streets - Tender No. T2020-4 - File: A-1440 Recommendation: 1. That Tender No. T2020-4 for Asphalt Resurfacing on Various City Streets as submitted by Forest Contractors Ltd. in the total tendered amount of $3,062,321.75 (HST included) be accepted; 2. That the total gross project cost of $3,595,910.00 (HST included), including the tendered amount, a contingency and other associated costs, and the total net project cost of $3,238,228.00 (net of HST rebate) be approved; 3. That the 2020 Capital Budget approved source of funds for the Granite Court and Redbird Crescent projects to be revised from Federal Gas Tax Reserve Fund to Ontario Community Infrastructure Fund Grant and Federal Gas Tax Reserve Fund; 4. That Council authorize the Director, Finance & Treasurer to finance the net project cost of $3,238,228.00 as follows: a) the sum $1,970,355.00 as approved in the 2020 Capital Budget to be funded by a transfer from the Federal Gas Tax Reserve Fund; b) the sum of $850,000.00 as approved in the 2020 Capital Budget to be funded from the Ontario Community Infrastructure Fund Grant to be increased to $880,357.00 for the four designated projects presented in Table 4, and the sum of $335,352.00 by a transfer from the Federal Gas Tax Reserve Fund; c) the sum of $52,164.00 as approved in the 2020 Capital Budget to be funded by a transfer from the Rate Stabilization Reserve; and, 5. That the appropriate officials of the City of Pickering be authorized to take the necessary actions as indicated in this report. ENG 02-20 April 27, 2020 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 Page 2 Executive Summary: As part of the 2020 Roads Projects Capital Budget, asphalt resurfacing for the following locations were approved as construction projects: • Gablehurst Crescent • Oklahoma Drive • New Street • Fieldlight Boulevard • Redbird Crescent • Rambleberry Avenue • Jaywin Circle • Sheppard Avenue • Hoover Drive • Sideline 24 • Sideline 22 • Granite Court • Dellbrook Avenue • Shadybrook Drive • Clements Road • Naroch Boulevard As part of the 2016 Road Needs Study endorsed by Council through Report ENG 25-17, these streets have been identified as a priority for resurfacing improvements. The 2016 Road Needs Study is used by staff as a resource document for identifying and planning maintenance, rehabilitation and reconstruction strategies, programs and projects for all Pickering roads. The 2020 roads selected for asphalt resurfacing align with the priorities of the Road Needs Study. Tender No. T2020-4 was issued on Wednesday, February 26, 2020 with a tender closing date of Wednesday, March 18, 2020. Five companies submitted a bid for this project. The low bid of $3,062,321.75 (HST included) submitted by Forest Contractors Ltd. is recommended for approval. The total gross project cost is estimated at $3,595,910.00 (HST included) with an estimated total net project cost of $3,238,228.00 (net of HST rebate). Due to the ongoing concerns and new business practices related to the COVID-19 virus pandemic, Engineering Services and Corporate Services staff will work with Forest Contractors Ltd., to ensure that proper procedures and protocols are in place to provide a safe work environment for Pickering residents, the contractor, sub -contractors, and City staff. These measures may include a delay to the start date of the project. ENG 02-20 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 April 27, 2020 Page 3 Financial Implications: 1. Tender Amount Tender No. T2020-4 HST (13%) Total $2,710,019.25 352,302.50 $3,062,321.75 2. Estimated Project Costing Summary Tender No. T2020-4 — Tender for Asphalt Resurfacing on Various City Streets Associated Costs Materials Testing Federal Gas Tax Sponsor Signage Provincial OCIF Sponsor Signage CP Rail Flag Person Construction Contingency (12% ) Sub Total — Costs HST (13%) Total Gross Project Cost HST Rebate (11.24%) Total Net Project Cost $2,710,019.00 130,000.00 2,500.00 2,500.00 12,000.00 325,202.00 $3,182,221.00 413,689.00 $3,595,910.00 (357,682.00) $3,238,228.00 ENG 02-20 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 April 27, 2020 Page 4 3. Approved Source of Funds Location Gablehurst Crescent New Street Redbird Crescent Jaywin Circle Hoover Drive Sideline 22 Dellbrook Avenue Clements Road Oklahoma Drive Fieldlight Boulevard Rambleberry Avenue Sheppard Avenue Sideline 24 Granite Court Shadybrook Drive Naroch Boulevard Expense Code 5320.2008.6251 5320.2010.6251 5320.2011.6251 5320.2012.6251 5320.2013.6251 5320.2014.6251 5320.2015.6251 5320.2016.6251 5320.2017.6251 5320.2018.6251 5320.2019.6251 5320.2020.6251 5320.2021.6251 5320.2022.6251 5320.2023.6251 5320.2024.6251 Source of Funds Budget Required Rate Stabilization $70,000 $52,164.00 Federal Gas Tax 220,000 171,398.00 Federal Gas Tax 271,000 210,376.00* Federal Gas Tax 242,000 190,659.00 Federal Gas Tax 225,000 167,768.00 Federal Gas Tax 16,000 41,363.00 Federal Gas Tax 418,000 304,613.00 Federal Gas Tax 260,000 194,891.00 Federal Gas Tax 254,000 203,964.00 Federal Gas Tax 160,000 146,302.00 Federal Gas Tax 354,000 277,432.00 Federal Gas Tax 325,000 230,602.00 Federal Gas Tax Federal Gas Tax OCIF Grant OCIF Grant Rate Stabilization 16,000 390,000 350,000 500,000 105,000 $4,176,000.00 41,363.00 335,077.00* 259,448.00 410,808.00 0.00 $3,238,228.00 * Will be applying a combination of OCIF grant and FGT funds. Net project cost (over) under approved funds $937,772.00 ENG 02-20 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 April 27, 2020 Page 5 4. OCIF Grant — Bundling of Projects Location Expense Code Budgeted Source Amount Source of Funds To of Funds Draw from Shadybrook Drive 5320.2023.6251 OCIF Grant $259,448.00 OCIF Grant Naroch Boulevard 5320.2024.6251 OCIF Grant 410,808.00 OCIF Grant Granite Court 5320.2022.6251 Federal Gas Tax 335,077.00 OCIF Grant and FGT Redbird Crescent 5320.2011.6251 Federal Gas Tax 210,376.00 OCIF Grant and FGT Total Net Project Cost including Contingency $1,215,709.00 Source of Funding OCIF Grant $880,357.00 Federal Gas Tax 335,352.00 Total Funds Required $1,215,709.00 Traditionally, the City's annual road resurfacing program has been funded by Federal Gas Tax funds at a level of approximately $1.5 million to $2.0 million. However, in 2019 the Federal Government announced a one-time top of Federal Gas Tax funds for municipalities, resulting in an additional $2.7 million for the City of Pickering. Some of these funds were allocated to the 2020 road resurfacing projects through the 2020 Capital Budget process. The Ontario Community Infrastructure Fund (OCIF) was launched in 2014 and provides formula based funding to help small, rural and northern communities build and repair critical infrastructure. All small municipalities (populations less than 100,000) are eligible. This program was scheduled to end in 2019. However, on January 16, 2020, the Province announced additional funding for municipalities in 2020. Pickering's formula based allocation from this grant is $880,357.00, and these funds are being used to add more streets to the road resurfacing program. In the 2020 Roads Capital Budget, two projects were budgeted to be funded from OCIF grant. Due to favourable tender results, the net tender cost for the two approved OCIF grant projects came in below the OCIF allocation of $880,357.00. In order to maximize the entire 2020 OCIF allocation, two additional projects have been added in order to provide a total net tender cost exceeding the OCIF grant amount. The balance of funds required for these combined four projects in excess of $880,357.00 will be funded from Federal Gas Tax Reserve (FGT) funds. Note that the budget provision of $105,000.00 from Rate Stabilization Reserve for Naroch Boulevard (OCIF project) is no longer necessary as the primary source of funding from OCIF grant in the amount of $410,808.00 is sufficient to cover the estimated net project cost of $410,808.00. ENG 02-20 April 27, 2020 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 Page 6 The four projects as presented in Table 4 will be bundled as one project: "Asphalt Resurfacing on Multiple Streets -Name of Streets", to be submitted to the province as the designated project for the 2020 OCIF allocation. In order to draw the maximum funds from OCIF grant, funding of the total net project cost (included contingency provision), in the amount of $1,215,709 for the four OCIF projects will be done in the following order: Shadybrook Drive, Naroch Boulevard, Granite Court and Redbird Crescent until the maximum of $880,357.00 is fully utilized. The balance of funds required for the Granite Court and Redbird Crescent project will be funded from the FGT. Maximizing the draw from OCIF grant will ensure we fully utilize grant funding, as 2020 is the final year of OCIF, and at this time we are uncertain of the province's position with regard to any unspent funds beyond 2020. Discussion: As part of the 2020 Capital Budget, asphalt resurfacing, for the following locations were approved as construction projects: • Gablehurst Crescent — from Brookshire Square to 90m west (to the new infill section) • New Street — from Parkside Drive to Cricket Lane • Redbird Crescent — from Huntsmill Drive to Huntsmill Drive • Jaywin Circle — from Denmar Road to Denmar Road • Hoover Drive — from Twyn Rivers Drive to Littleford Street • Sideline 22 — at the CP Rail Crossing north of Regional Road #5 • Dellbrook Avenue — from Valley Farm Road to Meriadoc Drive • Clements Road — from Brock Road (RR#1) to Rail Line Spur • Oklahoma Drive — from Hillcrest Road to West Shore Boulevard • Fieldlight Boulevard — from Rosefield Road to Glenview Road • Rambleberry Avenue — from Dixie Road to Kelvinway Lane (south leg) • Sheppard Avenue — from Edmund Drive to Whites Road (RR#38) • Sideline 24 — at the CP Rail Crossing south of Regional Road # 5 • Granite Court — from Rosebank Road to Ironstone Manor • Shadybrook Drive — from Belinda Court to south of Edgewood Road (to the road bend at Shadybrook Park) • Naroch Boulevard — from Grenoble Boulevard (west leg) to Modlin Road These streets are indicated in the 2016 Road Needs Study as priority streets for asphalt resurfacing. The at -grade rail level crossings on Sideline 22 and Sideline 24 have been identified by staff as deficient, and in an effort to enhance vehicular safety, the existing gravel approaches will be upgraded to asphalt under this program. All protocols and safety procedures (including the use of a flag person) for trackside protection will be followed as a requirement of Canadian Pacific Rail. ENG 02-20 April 27, 2020 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 Page 7 Tender No. T2020-4 was issued on Wednesday, February 26, 2020 with a tender closing date of Wednesday, March 18, 2020. Five companies submitted a bid for this project. The low bid of $3,062,321.75 (HST included) submitted by Forest Contractors Ltd. is recommended for approval. The total gross project cost is estimated at $3,595,910.00 (HST included) with an estimated total net project cost of $3,238,228.00 (net of HST rebate). References for Forest Contractors Ltd., their Waste Management Plan and list of sub -contractors have been reviewed and are deemed acceptable by the Manager, Capital Projects & Infrastructure. The City's Health & Safety Policy form, and a current Clearance Certificate issued by the Workplace Safety & Insurance Board has been submitted to the City by Forest Contractors Ltd.. The Certificate of Insurance has been reviewed by the Manager, Budgets & External Audit and is deemed acceptable. In conjunction with staff's review of the contractor's previous work experience the tender is deemed acceptable. Upon careful examination of all tenders and relevant documents received, the Engineering Services Department recommends acceptance of the low bid submitted by Forest Contractors Ltd. for Tender No. T2020-4 in the amount of $3,062,321.75 (HST included), and that the total net project cost of $3,238,228.00 (net of HST rebate) be approved. Attachments: 1. Supply & Services Memorandum dated March 19, 2020 2. Record of Tenders Opened and Checked 3. Location Maps ENG 02-20 April 27, 2020 Subject: Asphalt Resurfacing on Various City Streets Tender No. T2020-4 Page 8 Prepared By: Scott Booker Manager, Capita; Projects & Infrastructure Ray Rodrigues, CPPB Manager, Supply & Services SB:mjh Approved/Endorsed By: Rich d Hallo. n, P.Eng, Dir tor, Engineering Services Stan Karwowski, MBA, CPA, CMA Director, .Finance & Treasurer Recommended for the consideration of Pickering City Council Tony Prevedel, P.Eng. Chief Administrative Officer +61 20( ZA2D cd - y4 DICKERING Attachment #1 to Report # ENG 02-20 Memo To: Richard Holborn March 19, 2020 Director, Engineering Services From: Lisa Chang Buyer, Supply & Services Copy: Administrative Assistant, Engineering Services Manager, Supply & Services Manager, Capital Projects Coordinator, Infrastructure Design Subject: Tender No. T2020-4 Tender for Asphalt Resurfacing on Various City Streets Closed: Wednesday, March 18, 2020 — 2:OOpm File: F-5400-001 Tender No. T2020-4 was advertised on the City's website on February 26, 2020. Five companies have submitted a bid for this project. A copy of the Record of Tenders Opened and Checked used at the public tender opening is attached. Tenders shall be irrevocable for 60 days after the official closing date and time. Purchasing Procedure No. PUR 010-001, Item 13.03 (r) provides checking tendered unit prices and extensions unit prices shall govern and extensions will be corrected accordingly, which has been completed below. The unsuccessful Bidder's tendering deposit, other than a bid bond, shall be returned to the applicable bidders as provided for by Purchasing Procedure No. PUR 010-001, Item 13.03 (w). Three (3) bids have been retained for review at this time and are attached. Summary Harmonized Sales Tax Included Bidder Total Tendered Amount After Calculation Check Forest Contractors Ltd. $3,062,321.75 $3,062,321.75 Four Seasons Site Development Ltd. $3,839,022.45 $3,839,022.45 C. Valley Paving Ltd. $3,953,138.32 $3,953,138.33 Viola Management Inc. $3,977,006.21 $3,977,006.21 Dufferin Construction Company; A Division of CRH Canada Group Inc. $5,356,890.43 $5,356,890.43 Pursuant to Information to Bidders Item 26 Pre -Condition of Award and Item 20 Tendering Specifications, the following documentation will be requested of Forest Contractors for your review during the evaluation stage of this tender call. Please advise if Supply & Services is to proceed with collecting the following documentation: (a) A copy of the City's Health and Safety Policy currently dated and signed; (b) A copy of the current Clearance Certificate issued by Workplace Safety & Insurance Board; (c) The City's certificate of insurance or approved alternative form shall be completed by the Bidder's agent, broker or insurer and; (d) A Waste Management Plan; A budget of $3,000,000.00 was provided to Supply & Services for this procurement. If the recommendation to award exceeds the budgeted amount, refer to Financial Control Policy Item 11 for additional instructions. In accordance with Purchasing Policy Item 06.04, the authority for the dollar limit as set out below excludes HST. As such, in accordance with Purchasing Policy Item 06.11, where the compliant quotation or tender meeting specifications and offering best value to the City is acceptable or where the highest scoring proposal is recommended and the estimated total purchase price is: (c) Over $250,000, the Manager may approve the award, subject to the approval of the Director, Treasurer, CAO and Council. Please include the following items in your report: 1. if Items (a) through (b) noted above are acceptable to the Co-ordinator, Health & Safety or designate, if required; 2. if Item (c) is acceptable to the Manager, Budgets & Internal Audit; 3. if the list of subcontractors is acceptable to Engineering Services; 4. if Item (d) is acceptable to Engineering Services; 5. any past work experience with low bidder Forest Contractors including work location; 6. without past work experience, if reference information is acceptable to Engineering Services; 7. the appropriate account number(s) to which this work is to be charged; 8. the budget amount(s) assigned thereto; 9. Treasurer's confirmation of funding; 10. related departmental approvals; and 11. related comments specific to the project. After receiving Council's approval, an approved "on-line" requisition will be required to proceed. Tender No. T2020-4 Page 2 Enquiries can be directed to the City's website for the unofficial bid results as read out at the public tender opening or to Supply & Services. Bidders will be advised of the outcome in due course. If you require further information, please feel free to contact me or a member of Supply & Services. RR/Ic Attachments Tender No. T2020-4 Page 3 PICKERING (44 Attachment #2 to Report # ENG 02-20 City of Pickering Record of Tenders Opened and Checked Tender Description: Asphalt Resurfacing on Various City Streets Tender No.: Date: Time: T2020-4 Wednesday, March 18, 2020 Approx. 2:30 pm Local Time Bidder Name Total Tendered Amount Bidder Sign In Comments Dufferin Construction Company $ -} ll C .,11 .-~--;= _ Y J C. Valley Paving Ltd. $ W`6, 1 �,� 4 2_ C t Forest Contractors $ , J 5 . n T -. --3 . -.41,-Y--e_ .Y ,._,\I-k.,ri...A. Lk I $ 0-: 1)s \r".: City Staff Present Other The information is strictly preliminary, pending review and verification of conformance to terms, conditions and specifications. Attachment #3 to Report # ENG 02-20 f f • SL BJE T ARE 44-1,40 Location Map — Dellbrook Avenue Dellbrook Avenue — from Valley Farm Road to Meriadoc Drive. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Clements Road Clements Road — from Brock Road (RR #1) to Rail Line Spur. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Oklahoma Drive Oklahoma Drive — from Hillcrest Road to West Shore Boulevard. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Fieldlight Boulevard Fieldlight Boulevard — from Rosefield Road to Glenview Road. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Rambleberry Avenue Rambleberry Avenue — from Dixie Road to Kelvinway Lane (south leg). The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Sheppard Avenue Sheppard Avenue — from Edmund Drive to Whites Road (RR #38). The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters that are deficient shall be removed and replaced as required. Location Map — Granite Court Granite Court — from Rosebank Road to Ironstone Manor. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters that are deficient shall be removed and replaced as required. Location Map — Sideline 22 Sideline 22 — from 15m northbound and 15m southbound of the approach to the CP Railway on Sideline 22 north of Regional Road #5. The proposed work includes asphalt resurfacing. Location Map — Sideline 24 Sideline 24 — from 15m northbound and 15m southbound of the approach to the CP Railway on Sideline 24 south of Regional Road #5. The proposed work includes asphalt resurfacing. Location Map — New Street New Street — from Parkside Drive to Cricket Lane. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Redbird Crescent Redbird Crescent — from Huntsmill Drive to Huntsmill Drive. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Jaywin Circle Jaywin Circle — from Denmar Road to Denmar Road. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Hoover Drive Hoover Drive — from Twyn Rivers Drive to Littleford Street. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Shadybrook Drive Shadybrook Drive — from Belinda Court to south of Edgewood Road (to the road bend at Shadybrook Park). The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required. Location Map — Naroch Boulevard Naroch Boulevard — from Grenoble Boulevard (west leg) to Modlin Road. The proposed work includes asphalt resurfacing. All existing concrete barrier curbs shall be removed and replaced with new concrete curbs and gutters. SUBJECT AREA \ Location Map — Gablehurst Crescent Gablehurst Crescent — from Brookshire Square to 90m west to New Infill Section. The proposed work includes asphalt resurfacing. The proposed work includes asphalt resurfacing. Existing concrete curbs and gutters and sidewalks that are deficient shall be removed and replaced as required.