HomeMy WebLinkAboutCS 04-19cl--� 4
BICKERING
From: Marisa Carpino
Director, Community Services
Report to Council
Report Number: CS 04 -19
Date: February 25, 2019
Subject: Tender for Brock Ridge Community Parks and S.M. Woodsmere Park
- Baseball Diamond Improvements Project
- Tender No. T-9-2019
- File: A-1440-001
Recommendation:
That the Brock Ridge Community Park - Baseball Diamond Improvements and S.M.
Woodsmere Park - Baseball Diamond Improvements projects be combined as the "Brock
Ridge Community Park and S.M. Woodsmere Park - Baseball Diamond Improvements"
project for debenture financing for an estimated total net project cost of $1,005,418.00;
2. That Tender No. T-9-2019 submitted by Anthony Furlano Construction Inc. in the amount
of $969,571.07 (HST included) be accepted;
3. That the total gross project cost of $1,116,472.00 (HST included), including the amount of
tender, contingency and other associated costs, and the total net project cost of
$1,005,418.00 (net of HST rebate) be approved;
4. That the Director, Finance & Treasurer be authorized to finance the total net project cost
of $1,005,418.00 as follows:
a) the sum of $815,000.00 as provided for in the 2019 Parks Capital Budget be
increased to $919,000.00 to be financed by the issuance of debentures by The
Regional Municipality of Durham over a period not to exceed ten years;
b) the sum of $85,000.00 to be funded by a transfer from the Self -Insurance Reserve;
c) the sum of $1,418.00 to be funded from property taxes;
d) the annual repayment charges in the approximate amount of $110,500.00 be
included in the Current Budget for the City of Pickering commencing in 2019, or such
subsequent year in which the debentures are issued, and continuing thereafter until
the debenture financing is repaid, and any financing cost to be paid out of Current
Budget;
e) the Treasurer be authorized to make any changes, adjustments, and revisions to
amounts, terms, conditions, or take any actions necessary in order to effect the
foregoing;
CS O4-19 February 25, 2019
Subject: Brock Ridge Community Park and S.M. Woodsmere Park Page 2
- Baseball Diamond Improvements Project
5. That the draft By-law attached to this report be enacted; and,
6. That the appropriate officials of the City of Pickering be authorized to take the necessary
actions as indicated in this report.
Executive Summary: Baseball diamond improvements to Brock Ridge Community Park
and S.M. Woodsmere Park were approved in the 2019 Parks Capital Budget. GHD Ltd. was
retained for engineering consulting services, including the provision of geotechnical reports
and preparation of drawings and specifications, in advance of tendering the project in 2019.
Tender No. T-9-2019 was issued on January 15, 2019, with an optional site visit held on
January 23, 2019 with four companies responding by the closing date of Thursday, February 7,
2019. The low bid submitted by Anthony Furlano Construction Inc. in the amount of
$969,571.07 (HST included) is recommended for approval. The total gross project cost is
estimated to be $1,116,472.00 (HST included) and the total net project cost is estimated at
$1,005,418.00 (net of the HST rebate).
Financial Implications:
1. Tender Amount
Tender No. T-9--2019 $858,027.50
HST (13%) 111,543.57
Total Gross Project Cost969.571.07
2. Estimated Project Costing Summary
5780.1920.6129
Brock Ridge
Community Park
Tender No. T-9-2019 $455,750.00
Contingency 53,116.00
Consulting — GHD Material 15,935.00
Testing, Quality Assurance
Total Costs 524,801.00
HST (13%) 68,224.00
Total Gross Project Costs $593,025.00
HST Rebate (11.24%) (58,988.00)
Total Net Project Costs $534,037.00
5780.1921.6129
S.M. Woodsmere Total
Park
$402,278.00 $858,028.00
46,884.00 100,000.00
14,065.00 _ 30,000.00
463,227.00 $988,028.00
60,220.00 �128,444.00
$523,447.00 $1,116,472.00
(52,066.00) (111,054.0
$471,381.00 $1.005,418.00
CS O4-19 February 25, 2019
Subject: Brock Ridge Community Park and S.M. Woodsmere Park Page 3
- Baseball Diamond Improvements Project
3. Approved Source of Funds
2019 Parks Capital Budget
Description
Brock Ridge
Community Park -
Baseball Diamond
Improvements
S.M. Woodsmere
Park- Baseball
Diamond
Improvements
Property Taxes
Total Funds
Account Code Source of Funds Budget Required
5780.1920.6129 Debt — 10 years $365,000.00 $449,000.00
Self Insurance 85,000.00 85,000.00
Reserve
5780.1921.6129 Debt - 10 years $450,000.00 470,000.00
4. Source of Funds by Park
Source of Funds
Debt — 10 years
Self Insurance Reserve
Property Taxes
Total Funds
5780.1920.6129
Brock Ridge
Community Park
$449,000.00
85,000.00
.17 nn
$534,037.00
0.00 1,418.00
$900,000.00 $1.005.418.00
5780.1921.6129
S.M. Woodsmere
Park
$470,000.00
0.00
1,381.00
$471,381.00
Total
$919,000.00
85,000.00
1,418.00
$1,005,418.00
Net Project Cost under (over) Approved Funds ($105,418.00)
Additional funds are required as a contingency. A contingency has been provided to cover
possible additional construction costs in the event that poor soil conditions are encountered. If
no issues are encountered, these funds will not be spent.
For the purpose of debenture financing, the Brock Ridge Community Park - Baseball Diamond
Improvements and the S.M. Woodsmere Park - Baseball Diamond Improvements will be
combined into one project and named "Brock Ridge Community Park and S.M. Woodsmere
Park - Baseball Diamond Improvements" project.
Discussion: The 2019 Capital Budget includes $450,000 for baseball diamond improvements
in Brock Ridge Community Park and $450,000 for baseball diamond improvements in S.M.
Woodsmere Park. The baseball backstops of these parks experienced catastrophic collapse
as a result of a 20mm ice storm event on April 14 and 15, 2018. Due to the condition of the
existing baseball backstops, full replacement was recommended by staff and was submitted as
capital projects in the 2019 Capital Budget. Included in the scope of work is the replacement of
CS O4-19
February 25, 2019
Subject: Brock Ridge Community Park and S.M. Woodsmere Park Page 4
- Baseball Diamond Improvements Project
player benches, new bleachers with concrete pads, replacement of the chain link on the wing
and outfield fences, and replacement of the asphalt paving around the backstop. GHD Ltd.
was retained in 2018 to prepare drawings and specifications in advance for this project. They
will also be retained as a consultant for material and structural quality testing and assurance
during construction.
Kirkey Field at Brock Ridge Community Park is the home field of Pickering Baseball
Association and is mostly used by their competitive Rep League in the Eastern Ontario
Baseball Association. The baseball diamond and backstop was originally installed in 1986 and
years later, had the backstop poles extended and additional netting installed above the
backstop fencing to contain foul balls. The extra loading on the fencing poles contributed to the
eventual failure of the posts and collapse of the backstop. The new backstop is taller and
structurally engineered to withstand present wind and ice loading conditions.
The baseball diamond at S.M. Woodsmere Park was installed in 1997 and again had the
backstop poles extended and additional netting installed above the backstop fencing leading to
similar results as Kirkey Field. The same engineered design will also be applied to this
backstop.
References for Anthony Furlano Construction Inc., their Waste Management Plan and list of
sub -contractors have been reviewed and are deemed acceptable by the Manager, Capital
Projects & Infrastructure. The City's Health and Safety Policy form, and a current Clearance
Certificate issued by the Workplace Safety & Insurance Board submitted by Anthony Furlano
Construction Inc. have been reviewed and are deemed acceptable. The Certificate of
Insurance has been reviewed by the Manager, Budgets & External Audit and is deemed
acceptable. In conjunction with staff's review of the contractor's previous work experience the
tender is deemed acceptable.
After careful review of all submissions received, the Community Services Department
recommends acceptance of Tender T-9-2019 submitted by Anthony Furlano Construction Inc.
for the Brock Ridge Community Park and S.M. Woodsmere Park - Baseball Diamond
Improvements project in the amount of $969,571.07 (HST included) and that the total net
project cost of $1,005,418.00 be approved.
Attachments:
1. Supply & Services Memorandum dated February 7, 2019
2. Location Map for Brock Ridge Community Park
3. Location Map for S.M. Woodsmere Park
4. Being a By-law to authorize the Brock Ridge Community Park and S.M.
Woodsmere Park - Baseball Diamond Improvements project in the City of
Pickering and the issuance of debentures in the amount of $919,000.00
CS O4-19
Subject: Brock Ridge Community Park & S.M. Woodsmere Park
- Baseball Diamond Improvements
Prepared By:
Rob G en
Supervisor, Parks Operations
Rab Bur i , P. Eng
Manager, Public Works
10
February 25, 2019
Approved/Endorsed By:
Marisa Carpino, MA
Director, Community Services
Page 5
Stan Karwowski, MBA, CPA, CMA
Director, Finance & Treasurer
f �
Ra Rodriigues, CPPB
Manager, Supply & Services
Recommended for the consideration
of Pickering City Council
A"'6 ' "e! z-'' I
Tony Prevedel, P. Eng.
Chief Administrative Officer
ATTACHMENT# I TO REPORT #SOH -T1
C� �f
DICKERING
To
From
Copy
Marisa Carpino
Director, Community Services
Jacqueline Charles
Senior Purchasing Analyst, Supply & Services
Administrative Assistant, Community Services
Manager, Supply & Services
Memo
February 7, 2019
Subject: Tender No. T-9-2019
Tender for Brock Ridge Community Park and S. M. Woodsmere Park — Baseball
Diamond Improvements
Closed: Thursday, February 7, 2019 — 2:00pm
File: F-5400-001
Tender No. T-9-2019 was advertised on the City's website on January 15, 2019. An optional
site visit was held on January 23, 2019 at 10:00 a.m. Four companies have submitted a bid
for this project.
A copy of the Record of Tenders Opened and Checked used at the public tender opening is
attached. Tenders shall be irrevocable for 60 days after the official closing date and time.
Purchasing Procedure No. PUR 010-001, Item 13.03 (r) provides checking tendered unit prices
and extensions unit prices shall govern and extensions will be corrected accordingly, which has
been completed below.
The unsuccessful Bidder's tendering deposit, other than a bid bond, shall be returned to the
applicable bidders as provided for by Purchasing Procedure No. PUR 010-001, Item 13.03 (w).
Three (3) bids have been retained for review at this time and are attached.
Summary
Harmonized Sales Tax Included
Bidder
Total Tendered Amount
After Calculation Check
Anthony Furlano Construction Inc.
$ 969,571.07
$ 969,571.07
Pine Valley Corporation
$ 1,290,618.78
$ 1,290,607.63
Lancoa Contracting Inc.
$ 1,359,118.80
$ 1,359,683.80
Hawkins Contracting Services Limited
$ 1,623,346.44
$ 1,623,346.44
Pursuant to Information to Bidders, Item 29 Pre -Condition of Award, the following
documentation will be requested of Anthony Furlano Construction Inc. for your review during
the evaluation stage of this tender call_ Please advise if Supply & Services is to proceed with
collecting the following documentation:
(a) A copy of the City's Health and Safety Policy form currently dated and signed;
(b) A copy of the current Clearance Certificate issued by Workplace Safety & Insurance
Board;
(c) The City's certificate of insurance or approved alternative form completed by the Bidder's
agent, broker or insurer; and
(d) Waste Management Plan.
A budget of $ 900,000 was provided to Supply & Services for this procurement.
If the recommendation to award exceeds the budgeted amount, refer to Financial Control Policy
Item 11 for additional instructions.
In accordance with Purchasing Policy Item 06.04, the authority for the dollar limit as set out
below excludes HST.
As such, in accordance with Purchasing Policy Item 06.11, where the compliant quotation or
tender meeting specifications and offering best value to the City is acceptable or where the
highest scoring proposal is recommended and the estimated total purchase price is:
(c) Over $250,000, the Manager may approve the award, subject to the approval of the
Director, Treasurer, CAO and Council.
Please include the following items in your report:
1. if Items (a) through (b) noted above are acceptable to the Co-ordinator, Health & Safety or
designate, if required;
2. if Item (c) is acceptable to the Manager, Budgets & Internal Audit;
3. if the list of subcontractors is acceptable to Community Services;
4. if Item (d) is acceptable to Community Services;
5. any past work experience with low bidder Anthony Furlano Construction Inc including
work location;
6. without past work experience, if reference information is acceptable to Community
Services;
7. the appropriate account number(s) to which this work is to be charged;
8. the budget amount(s) assigned thereto;
9. Treasurer's confirmation of funding;
10. related departmental approvals; and
11. related comments specific to the project.
After receiving Council's approval, an approved "on-line" requisition will be required to proceed.
Tender No. T-9-2019
Tender for Brock Ridge Community Park and S. M. Woodsmere Park — Baseball Page 2
Diamond Improvements
Enquiries can be directed to the City's website for the unofficial bid results as read out at the
public tender opening or to Supply & Services. Bidders will be advised of the outcome in due
course.
If you require further information, please feel free to contact me or a member of Supply &
Services.
JC (4)
Attachments
Tender No. T-9-2019
Tender for Brock Ridge Community Park and S. M. Woodsmere Park — Baseball Page 3
Diamond Improvements
LLL
'l ' I 1
Q
R. -Uy
RFA LL
`f OOT j
BRIDG
BLEACHER
• LF O
lP{1A)
t BAGEBALL
q� DMAIONO ,
LP(1T) (Jft.) I
B4TTWG p Cd
CAGE
SPBRT
�� • LA -'9j •' PlnS
S1CHT� ICY .
PmKWGLOT ASP", O
ca
PARKING LOT GHQ j
0 w
CB
'/ "�^ �L^°IIS) 1 ��• p CH 1_4-�
I'IU% O •LM141 BRA irfl�: v V'I
i o GFRB. LA(rl,
SPORT,7 age=%
,/Lic
� GHEOS PUY 4B{µ BENCH B/u^EBALL
DUNoim p'"
.5) � •D�. �� LP(Im
soccer PrrGH
v 50CCE4 PITC" (JR.) p BLOHER
i
® I9Tl.CH
BENCH
OEHCN
BENCH ASPLIALT PATH
(WT Wn TRNL)
PARK INFO,
BROCK RIDGE COMMUNITY PARK
FINCH AVENUE
P-026 SHEET 1 OF 1
lT1
i
3
m
z
1�3
m
a
0
w
/
WOODSMERE CRESCENT
/
GARB.
JR. & I . CAR GARB.
PLAY REA •
,TH RS'O.ya GARB. CAN
ING (T
00 A4lH
GARB. CAN
—_
BENCHES 0 BENCHES
V ❑ CB / / CHERS
Q
O
CHERS
v�
'.
r �
4
i
Q
m
LL I
C)
/
O
M
�
CCB
ASPHALT PATH
0 DICB
PARK INFO.
S.M. WOODSMERE PARK
P-072 SHEET 1 OF 1
w
ATTACHMENT # TO REPORT # 05 01-i -1 I
The Corporation of the City of Pickering
By-law No.
Being a by-law to authorize the Brock Ridge
Community Park and S.M. Woodsmere Park -
Baseball Diamond Improvements project in
the City of Pickering and the issuance of
debentures in the amount of $919,000.00.
Whereas Section 11 of the Municipal Act, 2001, as amended, provides that a lower -tier
municipality may pass by-laws respecting matters within the spheres of jurisdiction
described in that Section; and,
Whereas Subsection 401 (1) of the Municipal Act, 2001, as amended, provides that a
municipality may incur a debt for municipal purposes, whether by borrowing money or in
any other way; and,
Whereas Subsection 401(3) of the Municipal Act, 2001, as amended, provides that a
lower -tier municipality in a regional municipality does not have the power to issue
debentures; and,
Whereas The Regional Municipality of Durham has the sole authority to issue
debentures for the purposes of its lower -tier municipalities including The Corporation of
the City of Pickering (the "City"); and,
Whereas the Council of the City wishes to proceed with debenture financing for the
Brock Ridge Community Park and S.M. Woodsmere Park - Baseball Diamond
Improvements project; and,
Whereas before authorizing the construction in respect of the Brock Ridge Community
Park and S.M. Woodsmere Park - Baseball Diamond Improvements project, the
Council of the City had the Treasurer update the City's Annual Repayment Limit, the
Treasurer calculated the estimated annual amount payable in respect of such project
and determined that such annual amount would not cause the City to exceed the
updated limit and therefore, Ontario Municipal Board approval is not required as per
Section 401 of the Municipal Act, 2001, as amended, and the regulations made
thereunder;
And whereas after determining that Ontario Municipal Board approval is not required,
the Council of the City approved report CS O4-19 on the date hereof and awarded
Tender No. T-9-2019 for the Brock Ridge Community Park and S.M. Woodsmere Park -
Baseball Diamond Improvements project;
BY-LAW NO
Page 2
Now therefore the Council of The Corporation of the City of Pickering hereby enacts as
follows:
1. That the City proceed with the project referred to as "Brock Ridge Community Park
and S.M. Woodsmere Park -- Baseball Diamond Improvements";
2. That the estimated costs of the project in the amount of $1,005,418.00 be financed
as follows:
a) the sum of $919,000.00 be financed by the issue of debentures by The
Regional Municipality of Durham over a period not to exceed ten years,
b) the sum of $85,000.00 be funded from by a transfer from the Self -Insurance
Reserve;
c) the sum of $1,418.00 from property taxes; and
3. That the funds to repay the principal and interest of the debentures be provided for
in the annual Current Budget for the City commencing in 2019 or such subsequent
year in which the debentures are issued and continuing thereafter until the
debenture financing is repaid.
By-law passed this 25th day of February, 2019
David Ryan, Mayor
Susan Cassel, City Clerk