HomeMy WebLinkAboutCS 35-18DICKERING
cdy,/
Report to
Council
Report Number: CS 35-18
Date: December 10, 2018
From: Marisa Carpino
Director, Community Services
Subject: Additional Costs for Concrete Slab and Prefabricated Storage Shed
- Pickering Museum Village Upper Site
- File: A-1440
Recommendation:
1. That additional costs in the amount of $100,000.00 (net of HST rebate) over the original
budgeted amount of $250,000.00 for project 5744.1804.6500 to construct a new Upper Site
Storage Shed at the Pickering Museum Village resulting in a revised budget amount of
$350,000.00 (net HST rebate) be approved;
2. That the Director, Finance & Treasurer be authorized to fund the additional net project cost
of $100,000.00 from property taxes;
3. That the appropriate officials of the City of Pickering be authorized to take the necessary
actions as indicated in this report.
Executive Summary: The Pickering Museum Village required construction of a new,
prefabricated metal storage shed on a concrete slab on grade to temporarily house artifacts from
the Conservation Building during its reconstruction on the lower Museum site. Request for
Quotation Q-12-2018 for the prefabricated metal shed resulted in a low bid of $203,414.70 (HST
included) from Prestige Building 2016 Ltd. The scope of required work was revised and reduced
costs to $172,895.65 (HST included). A separate quotation was issued for provision of the
required slab on grade. Q-23-2018 resulted in a low bid of $124,300.00 (HST included).
Combined costs totaled $267,634.00 (net of HST rebate) and fell within the limits of the Financial
Control Policy for required approvals.
Bids for the prefabricated shed were received just as news broke of United States tariffs on steel,
which could not be projected when the original budget was submitted. Excavation for the slab on
grade also encountered worse soil conditions than had been identified by preliminary testing and
required excavation of an additional 3 foot depth across the entire 6,000 square foot footprint of
the shed, including subsequent backfill with suitable materials. Additional engineering and
installation costs were also incurred during erection of the shed to meet increased snow load
demands.
Delaying the work would have impacted the start date of the Conservation Building Reconstruction
project, endangering the project schedule, which is restricted by conditions and completion
deadlines associated with a $450,000.00 federal grant. Doing so would also have exposed the
City to delay claims by the general contractor for that project and risked incurring winter control
Report CS 35-18
Subject: Additional Funds for Upper Site Storage Shed
at the Pickering Museum Village
December 10, 2018
costs due to a late start. The extent of additional costs were also not known until after Council had
recessed for the 2018 Municipal Election.
The new shed plant is now substantially complete and housing artifacts from the Conservation
Building, which is currently under renovation. Additional funds in the amount of $100,000.00 (net
of HST rebate) are required to cover extra costs encountered during the project.
Financial Implications:
1. Quotation Amounts
Q-12-2018 (Prefab Metal Shed)
Q-23-2018 (Slab on Grade)
HST (13%)
Total Gross Project Cost
$153,005.00
• 110,000.00
$263,005.00
34,190.65
$297,195.65
2.
Estimated Project Costing Summary
Q-12-2018 (Prefab Metal Shed)
Q-23-2018 (Slab on Grade)
Additional Excavation and Fill
Additional Shed Installation Costs
Miscellaneous Minor Costs
Total Cost
HST (1.3%)
Total Gross Project Costs
HST Rebate (11.24%)
Total Net Project Costs
$153,005.00
110,000.00
32,511.80
45,028.20
3,402.00
$343,947.00
44,713.00
$388,660.00
(38,660.00)
$350,000.00
3. Approved Source of Funds
2018 Capital Budget — Rec. Complex — Arenas
Account Code
5744.1804.6500
Source of Funds
Budget
Facilities Reserve $250,000.00
Property Taxes
Total Funds $250,000.00
Required
$250,000.00
100,000.00
$350,000.00
Project Cost under (over) approved funds by
($100,000.00)
Report CS 35-18 December 10, 2018
Subject: Additional Funds for Upper Site Storage Shed
at the Pickering Museum Village
This project has an over -expenditure that exceeds 10% of the approved amount. The over-
expenditure is partially the result of the prefabricated metal shed cost being higher than originally
anticipated due to the implementation of tariffs on steel by the United States. The additional cost
pressure is being funded from property taxes as confirmed by the Treasurer.
In accordance with Section 11.04 of the City's Financial Control Policy, over expenditure
exceeding ten percent of the approved capital expenditures shall require the approval of the
Treasurer, the Chief Administrative Officer, and the Council. Council approval is being sought at
this time for the additional funds required.
Discussion: Storage space at the Pickering Museum Village is insufficient to house all of
the artifacts in its collection and most of the available storage space does not meet minimum
collection standards. This condition generated the need for reconstruction of the existing steam
barn to create the new Conservation Building. The contents of the existing barn, including many of
the Museum collection's larger pieces, such as agricultural equipment and machinery, had to be
relocated elsewhere before those renovations could proceed. A total storage area of 6,000
square feet was needed to house all of the artifacts to be displaced.
Staff investigations, supported by budgetary quotes, determined that it could cost the City over
$200,000.00 to temporarily relocate the affected items to temporary off-site storage. Constructing
of a new on-site storage structure instead would meet short term storage needs and also provide
long term storage for future needs.
The project was split into two scopes for procurement in order to try and save time and reduce
costs. Costs for the prefabricated metal shed were higher than originally anticipated due to the
implementation of tariffs on steel by the United States.. Staff were able to negotiate scope
reductions with the low bidder for Q-12-2018 to find over $50,000.00 in savings from the originally
submitted bid. Artifact transportation costs totaling $59,704.59 (HST included) were funded by the
Pickering Museum Village Foundation to help offset pressures on the project budget.
Despite preliminary testing, poor soils with high organic content were encountered during
excavation for the slab on grade and required excavation to an additional 36" depth across the
entire shed footprint. New fill material had to be provided to replace what was removed.
Additional structural and detailing issues were encountered during erection of the superstructure,
including addition roof reinforcement required to resist higher snow loads applicable in the
northern areas of Pickering.
It was necessary to proceed with the work immediately. Delaying completion of the shed would
impact reconstruction of the Conservation Building, including risks delay claims and added costs
for winter control. The Conservation Building project is also partially funded by a $450,000.00
grant from the Canadian Cultural Spaces Fund, which includes restrictive deadlines for expending
funding. The full cost of the additional project costs were also not known until Council had
recessed for the 2018 Municipal Election.
Report CS 35-18 December 10, 2018
Subject: Additional Funds for Upper Site Storage Shed
at the Pickering Museum Village
The Community Services Department recommends that the amount of $100,000.00 (net of HST
rebate) be added to 5744.1804.6500 for construction of an Upper Site Storage Shed at the
Pickering Museum Village resulting in a revised budget amount of $350,000.00 (net HST rebate)
be approved.
Attachments:
1. Three photographs of storage shed
Prepared, By: Approved/Endorsed By:
Vince Plouffe, OAA, RAIC
Marisa Carpino, A
Manager, Facilities Capital Projects Director, Community Services
Brian Du
Division Head, Operations
Ray 'odrgues
Manager, Supply & Services
MC:vp
-
Stan Karwowski, CPA, CMA, MBA
Director, Finance & Treasurer
Recommended for the consideration
of Pickering City Council
Tony Prevedel, P.Eng.
Chief Administrative Officer
Nal) 3t), Zolg
ATTACHMENT # 1 TO REPORT it t -S --45- ti))
i
1