HomeMy WebLinkAboutCS 09-18DICKERING
,/ 6„/
Report to
Council
Report Number: CS 09-18
Date: May 14, 2018
From: Marisa Carpino
Director, Community Services
Subject: Tender for Conservation Barn Reconstruction at the Pickering Museum Village
- Tender No. T-14-2018
- File: A-1440
Recommendation:
1. That Tender No. T-14-2018 submitted by J.J. McGuire General Contractors Inc. in the
amount of $1,553,000.38 (HST included) be accepted;
2. That the total gross project cost of $1,863,751.00 (HST included), including the amount of
the tender, contingency and other associated costs, and the total net project cost of
$1,678,366.00 (net of HST rebate), be approved;
That Council authorize the Director, Finance & Treasurer to finance the net project cost of
$1,678,366.00 as follows:
a) the sum of $850,000.00, as provided for in the 2018 Museum Capital Budget be
financed by the issue of debentures by the Regional Municipality of Durham over a
period not to exceed 20 years;
b) the annual repayment charges in the amount of approximately $62,545.00 be
included in the annual Current Budget for the City of Pickering (the "City")
commencing in 2018, or such subsequent year in which the debentures are issued,
and continuing thereafter until the debenture financing is repaid, and any financing
cost to be paid out of the Current Budget;
c) The sum of $450,000.00 to be funded from the Canada Cultural Spaces Fund
(CCSF) through the Government of Canada;
d) The sum of $378,366.00 to be funded by a transfer from the Rate Stabilization
Reserve;
e) the Treasurer be authorized to make any changes, adjustments, and revisions to
amounts, terms, conditions, or take any actions necessary in order to effect the
foregoing;
4. That the draft by-law attached to this report be enacted; and
5. That the appropriate officials of the City be authorized to take the necessary actions as
indicated in this report.
Report CS 09-18 May 14, 2018
Subject: Tender for Conservation Barn Reconstruction at the Page 2
Pickering Museum Village
Executive Summary: The City intends to partially demolish and reconstruct the existing
Steam Barn on the lower site of Pickering Museum Village in order to upgrade and repurpose it as
the site's new Conservation Building. The existing building consists of an unheated and
uninsulated metal roof and cladding on wood post and timber construction. The roof and cladding
are at the end of their serviceable life.
The project includes provision of a water and septic system to meet health and safety
requirements, insulation and provision of heating and cooling systems to maintain a tempered
internal environment, the addition of a sprinkler system to better protect irreplaceable historical
artefacts, dedicated large artefact conservation lab and storage, and structural reinforcement of
the roof to accommodate future solar panel installation.
On February 8, 2018, Request for Prequalification RFPQ-5-2018 was publically released for the
Prequalification of General Contractors for the Conservation Barn Reconstruction at the Pickering
Museum Village. A total of twelve proposals were received by the deadline of Thursday, March 1,
2018. Based on the results of the evaluation rated criteria, five General Contractors were
successfully prequalified by the City to submit bids for consideration.
Tender No. T-14-2018 was released to the prequalified General Contractors and was also made
available for information to the public on the City's website on March 23, 2018. A mandatory site
visit was held on April 4, 2018. The tender closed on May 1, 2018. Four companies submitted
bids for this project.
The low bid submitted by J.J. McGuire General Contractors Inc. in the amount of $1,553,000.38
(HST included) is recommended for approval. The total gross project cost is estimated to be
$1,863,751.00 (HST included) and the total net project cost is estimated at $1,678,366.00 (net of
HST rebate). In July 2017, the City was awarded $450,000.00 towards this reconstruction project
from the federal government through the CCSF.
Commencing with this project as soon as possible will help maintain the project schedule of June
to November 2018 and could even accelerate building occupancy. Subject to award, the
contractor can immediately order equipment and materials for fabrication in advance of other key
project milestones (including construction of a shed structure and the relocation of existing
building contents to that shed). Construction can then proceed at a faster pace by avoiding the
risks of late or long delivery times. Faster construction in the early parts of the work will also
facilitate early enclosure of the building, reducing any risks associated with inclement weather in
the fall.
Financial Implications:
1. Tender Amount
Tender No. T-14-2018
HST (13%)
Total Gross Project Cost
$1,374,336.62
178,663.76
$1,553,000.38
Report CS 09-18
Subject: Tender for Conservation Barn Reconstruction at the
Pickering Museum Village
May 14, 2018
Page 3
Estimated Project Costing Summary
Tender No. T-14-2018
Fire Protection System
Contingency
Total Cost
HST (13%)
Total Gross Project Costs
HST Rebate (11.24%)
Total Net Project Costs
$1,374,337.00
125,000.00
150,000.00
$1,649,337.00
214,414.00
$1,863,751.00
(185,385.00)
$1,678,366.00
3. Approved Source of Funds
2018 Capital Budget — Museum
Account Code
5744.1808.6500
Source of Funds
Budget
Debt — 20 Years $850,000.00
CCSF 450,000.00
Rate Stabilization Reserve 0.00
Total Funds $1,300,000.00
Required
$850,000.00
450,000.00
378,366.00
$1,678,366.00
Project Cost under (over) approved funds by
($378,366.00)
The additional cost will be funded by a transfer from the Rate Stabilization Reserve. By adopting
this strategy, the City will be in an enhanced financial position to reach the 2019 budget levy
target of 2.25% as established by Council.
Investigations during the design process confirmed poor soil conditions beneath the existing
building and rot in several of the existing structural members intended to be re -used. Allowances
have been included in the tender price for the reinforcement and replacement of affected
structures, but could not be accounted for at the time of submission of the construction budget.
A separate allowance has been included for the provision of a fire suppression system, including
sprinkler distribution, water storage tanks, pumps, backup power system and related ancillary
works. The system is not required by the Ontario Building Code, and was therefore not included
in the original construction budget, but it is strongly recommended that it be included in the scope
of work. Many artefacts to be stored in this building are unique and irreplaceable parts of the
City's heritage, and valuable public assets in need of added protection. The absence of municipal
water service and hydrants in the vicinity of the museum site increases the cost to provide this
protection.
In accordance with Section 1.1.04 of the City's Financial Control Policy, over expenditure
exceeding 10% of the approved capital expenditures shall require the approval of the Treasurer,
the Chief Administrative Officer, and Council. Therefore, Council approval is being sought at this
Report CS 09-18 May 14, 2018
Subject: Tender for Conservation Barn Reconstruction at the
Pickering Museum Village
Page 4
time for the additional funds required. The Treasurer has concurred that the over expenditures will
be funded by a transfer from the Rate Stabilization Reserve.
Contingency funds of approximately 10% of the construction cost has been included to address
any additional soils or structural costs and to address unforeseen costs common with renovation
projects on older buildings. If the contingency is not required, the funds will be returned to the
Rate Stabilization Reserve.
Discussion: The existing Steam Barn at Pickering Museum Village was constructed in the
late 1970s, shortly after the Museum relocated to its current site from its previous location in
Brougham. Additions were added for workshop spaces on the south side of the main structure in
2007 and 2008.
The original building is approximately 100 feet long by 60 feet wide and of wood post and timber
column construction with prefinished sheet metal cladding. Wood trusses support a sheet metal
roof. The floor is a concrete slab on grade. The interior is uninsulated and unheated. Minimal
lighting is provided by translucent fiberglass panels on the north face and high bay industrial
fixtures. The building is currently monitored by a security alarm, but has no water supply or septic
system.
The building currently houses most of the museum's collection of heritage vehicles and
agricultural equipment, including tractors, steam -powered engines and other machinery. Indoor
storage protects these artefacts from direct exposure to the elements, but they remain vulnerable
to large fluctuations in temperature and humidity, pests, and other factors that negatively impact
efforts to conserve them.
Limited available storage space, compared to the size of the existing collection and other
materials currently stored across the Museum, has been a persistent and growing issue. Museum
staff have been working diligently to update their collection inventory and deaccession redundant
items, or those without provenance to the City's history.
Reconstruction of the Conservation Barn will upgrade the existing facility while retaining as much
of the existing structure as possible, including both existing workshop additions. Construction will
commence in July 2018 and is scheduled for completion by November 2018.
The following tasks and requirements have been included in the scope of work:
• Repurposing existing wall and roof cladding to serve as an interior liner panels. Insulation
and new metal cladding will be added to the building exterior to meet energy conservation
requirements;
• Structural reinforcement of the overall building to meet current codes and sufficient for the
future installation of solar panels on the roof's expansive southern exposure;
• Provision of a single office, large artefact conservation workspace and barrier -free
washroom;
Report CS 09-18 May 14, 2018
Subject: Tender for Conservation Barn Reconstruction at the Page 5
Pickering Museum Village
• Relocation of the main entrance to the east face of the building to eliminate ice and snow
fall hazard over the existing entrance on the south side;
• Provision of permanent potable water and septic systems;
• Provision of a HVAC system capable of maintaining museum -grade class B (tempered) air
quality;
• Provision of a dedicated fume hood for artefact conservation;
• Upgrades to existing electrical service;
• Upgrades to existing lighting systems to the City's current LED standard;
• Upgrades to existing life safety systems, including fire suppression;
• Added protection to the artefact collection against pests and vermin;
• Replacement of the existing racking storage system; and
• Enhanced security systems, including the provision of cameras.
On February 8, 2018, Request for Prequalification RFPQ-5-2018 was publically released for the
Prequalification of General Contractors for the Conservation Barn Reconstruction at the Pickering
Museum Village. A total of twelve proposals were received by the deadline of Thursday, March 1,
2018. Based on the results of the evaluation rated criteria, five General Contractors were
successfully prequalified by the City to submit bids for consideration.
Tender No. T-14-2018 was released to the prequalified General Contractors and was also made
available for information to the public on the City's website on March 23, 2018. A mandatory site
visit was held on April 4, 2018. The tender closed on May 1, 2018. Four companies submitted
bids for this project.
The low bidder, J.J. McGuire General Contractors Inc., has submitted a signed copy of the City's
Health & Safety Regulation form. The Certificate of Insurance is deemed acceptable to the
Manager, Budgets & Internal Audit. Staff reviewed the previous work experience of J.J. McGuire
General Contractors Inc. as part of the pre -qualification process. The references provided were
deemed acceptable.
Upon careful examination of all bids and relevant documents received, the Community Services
Department recommends the acceptance of Tender No. T-14-2018 submitted by J.J. McGuire
General Contractors Inc. in the amount of $1,553,000.38 (HST included) and that the total net
project cost of $1,678,366.00 be approved.
Attachments:
1. Supply & Services Memorandum dated May 1, 2018
2. Design Concept Rendering
3. Being a by-law to authorize the Conservation Barn Reconstruction at the Pickering Museum
Village project and the issuance of debentures in the amount of $850.000.00
Report CS 09-18 May 14, 2018
Subject: Tender for Conservation Barn Reconstruction at the Page 6
Pickering Museum Village
Prepared By:
VincePlouffe, •AA, RAIC
Approved/Endorsed By:
Marisa Carpino, MA
Manager, Facilities Capital Projects Director, Community Services
Brian Dield
Division ead, Operations
Ray R.r„ rigues
Manager, Supply & Services
MC:vp
Stan Karwowski, CPA, CMA, MBA
Director, Finance & Treasurer
Recommended for the consideration
of Pickering City Council
Tony Prevedel, P.Eng.
Chief Administrative Officer
ATTACHMENT #®TO REPORT #,
C!� eh
DICKERING
Memo
To: Marisa Carpino May 1, 2018
Director, Community Services
From: Ray Rodrigues
Manager, Supply & Services
Copy: Administrative Assistant, Community Services
Subject: Tender No. T-14-2018
Tender for Conservation Barn Reconstruction at the Pickering Museum Village
Closing: Wednesday, May 1, 2018 — 2:OOpm
File: F-5400-001
Tender No. T-14-2018 was advertised on the City's website on March 23, 2018. A mandatory
site visit was held on April 4, 2018 at 10:00 am. Four (4) companies have submitted a bid for
this project.
A copy of the Record of Tenders Opened and Checked used at the public tender opening is
attached. Tenders shall be irrevocable for 60 days after the official closing date and time.
Purchasing Procedure No. PUR 010-001, Item 13.03 (r) provides checking tendered unit prices
and extensions unit prices shall govern and extensions will be corrected accordingly, which has
been completed below.
The unsuccessful Bidder's tendering deposit, other than a bid bond, shall be returned to the
applicable bidders as provided for by Purchasing Procedure No. PUR 010-001, Item 13.03 (w).
Three (3) bids have been retained for review at this time and are attached.
Summary
Harmonized Sales Tax Included
Bidder
Total Tendered Amount
After Calculation Check
J.J. McGuire General Contractors Inc.
$1,553,000.38
$1,553,000.38
Stracor inc.
$1,570,370.00
$1,570,370.04
Harbridge & Cross Ltd.
$1,598,950.00
$1,598,950.00
Ultimate Construction Inc.
$1,664,716.00
$1,664,716.00
Pursuant to Information to Bidders Item 29 and Tendering Specifications Item 21, the following
documentation will be requested of J.J. McGuire General Contractors Inc. for your review during
the evaluation stage of this tender call. Please advise if Supply & Services is to proceed with
collecting the following documentation:
(a) The City's certificate of insurance or approved alternative form completed by the Bidder's
agent, broker or insurer; and
(b) Waste Management Plan.
A budget of $1,300,000 was provided to Supply & Services for this procurement.
If the recommendation to award exceeds the budgeted amount, refer to Financial Control Policy
Item 11 for additional instructions.
In accordance with Purchasing Policy Item 06.04, the authority for the dollar limit as set out
below excludes HST.
As such, in accordance with Purchasing Policy Item 06.11, where the compliant quotation or
tender meeting specifications and offering best value to the City is acceptable or where the
highest scoring proposal is recommended and the estimated total purchase price is:
(c) Over $250,000, the Manager may approve the award, subject to the approval of the
Director, Treasurer, CAO and Council.
Please include the following items in your report:
1. if Item (a) is acceptable to the Manager, Budgets & Internal Audit;
2. if the list of subcontractors is acceptable to Community Services;
3. if Item (b) is acceptable to Community Services;
4. any past work experience with low bidder J.J. McGuire General Contractors Inc. including
work location;
5. without past work experience, if reference information is acceptable to Community
Services;
6. the appropriate account number(s) to which this work is to be charged;
7. the budget amount(s) assigned thereto;
8. Treasurer's confirmation of funding;
9. related departmental approvals; and
10. related comments specific to the project.
After receiving Council's approval, an approved "on-line" requisition will be required to proceed.
May 1,2018
Tender No. T-14-2018
Conservation Barn Reconstruction at the PMV
Page 2
Enquiries can be directed to the City's website for the unofficial bid results as read out at the
public tender opening or to Supply & Services. Bidders will be advised of the outcome in due
course.
If you require further information, please feel free to contact me or a member of Supply &
Services.
RR/rr
Attachments (3)
May 1, 2018
Tender No. T-14-2018
Conservation Barn Reconstruction at the PMV
Page 3
# IN3WHDVllb
0
MinXiMmummomommommatioivivmomi
{
iy•
!i
•
�_.: _. .." - :�, - 'fes C .4-=r'•' - - _-.� - :�-_ - --
__-�f;.t4i�Y:._.. __+•+ Z "_'�._`;ci.. y� .y• . ,,�•-:r'S�a•�-�' 3-_-z.-_�^iy-:�.--�^C.�
'_""�iaC`-Y-L�->Y.�'^^.Ya�--`-•�-.4=�Y.Tn �_�yy�r�'�,:� ?' L`
sz' ='mow -._—
z ARCHITECTS
RING SVG THE VENTIN GROUP LTD
PICKERING MUSEUM VI
CONSERVATION BUI
The Corporation of the City of Pickering
By-law No.
Being a by-law to authorize the Conservation
Barn Reconstruction at the Pickering Museum
Village project in the City of Pickering and the
issuance of debentures in the amount of
$850.000.00
Whereas Section 11 of the Municipal Act, 2001, as amended, provides that a lower -tier
municipality may pass by-laws respecting matters within the spheres of jurisdiction
described in that Section; and,
Whereas Subsection 401(1) of the Municipal Act, 2001, as amended, provides that a
municipality may incur a debt for municipal purposes, whether by borrowing money or in
any other way; and,
Whereas Subsection 401(3) of the Municipal Act, 2001, as amended, provides that a
lower -tier municipality in a regional municipality does not have the power to issue
debentures; and,
Whereas The Regional Municipality of Durham has the sole authority to issue
debentures for the purposes of its lower -tier municipalities including The Corporation of
the City of Pickering (the "City"); and,
Whereas the Council of the City wishes to proceed with debenture financing for the
Conservation Barn Reconstruction at the Pickering Museum Village project; and
Whereas before authorizing the construction in respect of the Conservation Barn
Reconstruction at the Pickering Museum Village project, the Council of the City had the
Treasurer update the City's Annual Repayment Limit, the Treasurer calculated the
estimated annual amount payable in respect of such project and determined that such
annual amount would not cause the City to exceed the updated limit and therefore,
Ontario Municipal Board approval is not required as per Section 401 of the Municipal
Act, 2001, as amended, and the regulations made thereunder;
And whereas after determining that Ontario Municipal Board approval is not required,
the Council of the City approved report CS 09-18 on the date hereof and awarded
Tender No. T-14-2018 for the Conservation Barn Reconstruction at the Pickering
Museum Village project;
BY-LAW NO Page 2
Now therefore the Council of The Corporation of the City of Pickering hereby enacts as
follows:
1. That the City proceed with the project referred to as "Conservation Barn
Reconstruction at the Pickering Museum Village";
2. That the estimated costs of the project in the amount of $1,678,366.00 be financed
as follows:
a) the sum of $850,000.00 be financed by the issue of debentures by the
Regional Municipality of Durham over a period not to exceed 20 years;
b) The sum of $450,000.00 be funded from the Canada Cultural Spaces Fund
through the Government of Canada; •
c) The sum of $378,366.00 be funded by a transfer from the Rate Stabilization
Reserve; and
3. That the funds to repay the principal and interest of the debentures be provided for
in the annual Current Budget for the City commencing in 2018 or such subsequent
year in which the debentures are issued and continuing thereafter until the
debenture financing is repaid.
By-law passed this 14th day of May, 2018
David Ryan, Mayor
Debbie Shields, City Clerk