HomeMy WebLinkAboutENG 15-17 U Report to PICKERiNG Council Report Number: ENG 15-17 Date: June 12, 2017 From: Richard Holborn Director, Engineering Services Subject: Request for Additional Funding for Consulting Services - Proposal No. RFP-4-2015 — Palmer Bridge Rehabilitation - File: A-1440 Recommendation: 1. That the additional fee proposal as submitted by AECOM Canada Ltd. in the amount of $114,194.41 (HST included) for the change in scope of work for the Palmer Bridge Rehabilitation detail design, contract administration and field inspection be accepted; 2. That the total revised gross project cost of$372,558.00 (HST included) and the total revised net project cost of$335,500.00 (net of HST rebate) be approved; 3. That the Director, Finance & Treasurer be authorized to finance the total revised net project cost as approved in the 2014 Roads Capital Budget in the amount of $335,500.00 by an additional transfer of$50,500.00 from the York Region Southeast Collector Funding Agreement; and 4. That the appropriate officials of the City of Pickering be authorized to take the necessary actions as indicated in this report. Executive Summary: As part of the Southeast Collector (SEC) Trunk Sewer Project funding agreement for community enhancements in the City of Pickering with the Region of York, one of the approved projects was to rehabilitate the Palmer Bridge at a total estimated cost of $2,185,000.00. As part of the 2014 Roads Capital Budget, $285,000.00 was approved by Council for the completion of design drawings and tender documents. RFP-4-2015 was awarded to AECOM Canada Ltd. in the amount of$175,263.00 (HST included). With reference to Report ENG 14-16 it was noted that there was a change in the scope of the project requiring additional funds. The selection of Design Alternative 3 which included widening the existing bridge deck to provide for a sidewalk on each side of the bridge and bike lanes, resulted in additional fees totaling $71,682.00 (HST included). Due to a change in scope of the work required to address the Toronto and Region Conservation Authority (TRCA) comments and finalize their permit requirements, AECOM Canada Ltd. is requesting an additional fee of$27,931.34 (HST included). Also, due to the chosen methodology of rehabilitating the bridge with one lane open at all times, the construction time has been increased by 50% resulting in an additional fee increase for contract administration and field inspection in the amount of$86,263.07 (HST included). ENG 15-17 June 12, 2017 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015 — Palmer Bridge Page 2 Based on the additional effort required to address Toronto and Region Conservation Authority requirements and the increase in contract administration and field inspection, additional fees in the amount of$114,194.41 (HST included) are required. The total revised net project cost has increased to $335,500.00.00 and there is sufficient funds available to accommodate this change. Financial Implications: 1. Quotation Amount Fee Proposal May 26, 2017 Scope Change Palmer Bridge Widening $101,057.00 HST (13%) 13,137.41 Total Gross Quotation Cost $114,194.41 • 2. Estimated Project Costing Summary Scope Change Palmer Bridge Widening $101,057.00 Additional Fees ENG 14-16 — Council Resolution #178/16 218,535.00 Contingency (10%) 10,105.00 Subtotal $329,697.00 HST (13%) 42,861.00 Total Revised Gross Project Cost $372,558.00 HST Rebate (11.24%) (37,058.00) Total Net Project Cost $335,500.00 3. Approved Source of Funds 2015 Roads Capital Budget Account Code Source of Funds Available Required Budget 5320.1408.6250 York Region SEC Funding Agreement $285,000.00 $285,500.00 Additional Funds Required 0.00 50,000.00 $285,000.00 $335,500.00 Net Project Cost under (over) Approved Funds: ($50,500.00) • CORP0227-07/01 revised ENG 15-17 June 12, 2017 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015 — Palmer Bridge Page 3 Note that with the regard to the contribution from the York Region (SEC) Enhancement Fund, in addition to the approved budget of$285,000.00, there is an option within the Community Enhancement Agreement, Section 2.02 (b), to increase the project's funding by 20%, which is $57,000.00 for this project, as long as there is sufficient funds available that can be transferred from other SEC enhancement projects that have been implemented under budget. A review of the completed SEC enhancement projects costs has been confirmed that there is sufficient savings from other projects to cover the additional $50,500.00 required. After incorporating a contingency provision, the project exceeded 10% of the original approved amount. In accordance with Section 11.04 of the City's Financial Control Policy, over expenditures exceeding 10% of the approved capital expenditures shall require the approval of the Treasurer, the Chief Administrative Officer, and Council. Council approval is being sought at this time for the additional funds required. Discussion: As part of the SEC Trunk Sewer Project funding agreement for community enhancements in the City of Pickering with the Region of York, one of the approved projects is to rehabilitate the Palmer Bridge, located on Valley Farm Road, north of Finch Avenue. As part of the 2014 Roads Capital Budget, $285,000.00 was approved by Council for the completion of design drawings and tender documents in preparation for tenders to be called for rehabilitation of the Palmer Bridge. RFP-4-2015 was awarded to AECOM Canada Ltd. in the amount of$175,263.00 (HST included). Due to a change in scope of the project to widen the bridge deck to allow for sidewalk and bike lanes on both sides of the bridge, additional fees in the amount of $71,682.00 (HST included) were approved through Report ENG 14-16. Due to a change in scope of the work required to address the Toronto and Region Conservation Authority comments and finalize their permit requirements, AECOM was required to complete the following additional tasks at an additional cost of$27,931.34 (HST included): • Completion of a Meander Belt Width Assessment and 100 Year Erosion Limit by AECOM fluvial geomorphologists. • Updates to drawings to provide additional details regarding the arrangement and installation of the proposed cofferdam. • Preparation of detailed fill calculations and sketches. • Additional Hydraulic Analysis for storm sewer outfall and erosion protection. • Additional written and verbal correspondence with TRCA CORP0227-07/01 revised ENG 15-17 June 12, 2017 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015 — Palmer Bridge Page 4 The contract administration and field inspection has increased for the following tasks at an additional cost of$86,263.07 (HST included): • The estimated contract administration and field inspection time has been increased to 24 weeks from 12 weeks( original proposal was for 12 weeks). • Consultant hourly rates have been adjusted to 2017 rates ( compared to 2016 rates in the original proposal). • Additional time has been added for shop drawing review due to the bridge deck being widened. • Additional fees have been included for weekly site visits for an Environmental Monitor as required by TRCA. As such, AECOM Canada Ltd. submitted a proposal dated May 26, 2017 outlining the scope change and the additional fees of$114,194.41 (HST included) required to address them. The proposal has been accepted by City staff. The Engineering Services Department recommends acceptance of the additional fee proposal for a change in scope of work for the Palmer Bridge Rehabilitation submitted by AECOM Canada Ltd. in the amount of $114,194.41 (HST included) and recommends a total revised net project cost of $335,500.00 be approved. Attachments: 1. Report ENG 14-16 2. Council Resolution # 178/16 CORP0227-07/01 revised ENG 15-17 June 12, 2017 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015 — Palmer Bridge Page 5 Prepared By: Approved/Endorsed By: ("--..Act,"(2/6 //i ie ; i Darrell Selsky, C.E.T., CMM Ri hard H. born, P.Eng. Manager, Capital Projects & • rastructure rector, Engineering Services Stan Karwowski, MBA, CPA, CMA Director, Finance & Treasurer DS:mjh Recommended for the consideration of Pickering City Council S$ 2, Z0(7 Tony Prevedel, P.Eng. Chief Administrative Officer • CORP0227-07/01 revised ATTACHMENT# TOREPORT# ? /5-/7- . • Obio? Report to Executive Committee I KERIN Report Number: ENG 14-16 Date: June 20, 2016 From: Richard Holborn Director, Engineering & Public Works • Subject: Request for Additional Funding for Consulting Services - Proposal No. RFP-4-2015 - Palmer Bridge - File: A-1440 • Recommendation: 1. That the additional fee proposal as submitted by AECOM Canada in the amount of$71,682.00 (HST included)for the change in scope of work for the Palmer Bridge design and specifications be accepted; 2. That the total revised gross project cost of$271,640.00 (HST included) and the total revised net project cost of$244,620.00 (net of HST rebate) be approved; • 3. That the Division Head, Finance &Treasurer be authorized to finance the total revised net project cost as approved in the 2014 Roads Capital Budget in the amount of$244,620.00 by an additional transfer of$71,008.00 from the York Region SEC Funding Agreement; and 4. That the appropriate officials of the City of Pickering be authorized to take the necessary actions as indicated in this report. Executive Summary: As part of the SEC.Trunk Sewer enhancement funding agreement with the Region of York, one of the approved projects was to rehabilitate the Palmer Bridge, which included the design and approvals. As part of the 2014 Roads Capital Budget, $285,000.00 was approved by Council for the completion of design drawings and tender documents. • Proposal No. RFP-4-2015 submitted by AECOM Canada Ltd. In the amount pf $155,100.00 (HST extra) and the total estimated net project cost of$173,612.00 was approved by the CAO on September 3, 2015. Due to a change in scope of work based on preliminary engineering design concepts and alternatives, additional fees in the amount of$71,682.00 (HST included) are required. The total revised net project cost. has increased to $244,620.00 and there is sufficient funds approved to accommodate this change. . 120 ATTACHMENT#_,.I TO REPORT# CNC? IS-fl- ENG 14-16 • June 20, 2016 Subject: Request for Additional Funding for Consulting Services Proposal.No. RFP-4-2015— Palmer Bridge Page 2 • Financial implications: • • 1. Quotation Amount Fee Proposal May 9, 2016 Scope Change Palmer Bridge Widening —Alternative 3. $63,435.00 HST (13%) 8.247.00 Total Gross Quotation Cost $71,682.00 2. Estimated Project Costing Summary Scope Change Palmer Bridge Widening—Alternative 3 $63,435.00 Request for Proposal,No. RFP-4-2015 155,100.00 Contingency (10%) 21,854.00 Subtotal $240,389.00 HST (13%) 31,251.00 Total Revised Gross Project Cost 271,640.00 HST Rebate (11.24%) (27,020.00) Total Net Project Cost $244,620,00 3. Approved Source of Funds 2015 Roads Capital Budget Description Account Code Source of Available Required Funds Budget Fee Proposal 5320.1408.6250 York Region SEC Funding Agreement $285,000.00 $244,620.00 • • Total Funds $285,000.00 $244,620.00 • Net Project Cost under(over)Approved Funds: $40,380.00! • Staff are recommending approval of an increase in the net project cost of$71,008.00 • . from the amount that was approved by the Chief Administrative Officer in a memo dated September 3, 2015. Due to the increase exceeding the threshold of 10%, Council approval is required. • . CORP0227-07/01 revised • • 121 ATTACHMENT#.=_TOJ�REPORT#_� 3 of ENG 14-16 June 20, 2016 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015— Palmer Bridge Page 3 Discussion: • As part of the SEC Trunk Sewer enhancement funding agreement with the Region of York, one of the approved projects is to rehabilitate the Palmer Bridge, which included the design and approvals. As part of the 2014 Roads Capital Budget, $285,000.00 as approved by Council for the completion of design drawings and tender documents in preparation for tenders to be called in the fall of 2016 for construction to follow in the spring of 2017. Proposal No. RFP-4-2015 submitted by AECOM Canada Ltd. In the amount pf $155,100.00 (HST extra) and the total estimated net project cost of$173,612.00 was approved by the CAO on September 3, 2015. AECOM Canada Ltd. provided the City with a Preliminary Design Report for the Palmer Bridge. Staff recently reviewed the report and met with AECOM Canada Ltd. to discuss the three alternatives that were being proposed in the report. Upon careful review, staff elected to proceed with Alternative 3, which included widening the existing bridge deck • • to provide for a sidewalk on each side of the bridge and bike lanes. This alternative requires the consultant to perform additional design work over and above what was approved in the original proposal. The change in scope of work also includes an evaluation of the existing streetlights in the.vicinity of the bridge for potential upgrades. The Engineering & Public Works Department recommends acceptance of the additional • fee proposal for a change in scope of work for the Palmer Bridge submitted by AECOM Canada Ltd in the amount of$71,682.00 (HST included) and recommends a total revised net project cost of$244,620.00 be approved. • • • • • • CORP0227-07/01 revised 122 . ATTACHMENT# " TOREPORT#_N� /S / - y of�.. ENG 14-16 June 20, 2016 Subject: Request for Additional Funding for Consulting Services Proposal No. RFP-4-2015— Palmer Bridge • Page 4 • Prepared By: Approved/Endorsed By: Darrell Selsky, CET, CMM III Richard Holborn, P. Eng. Manager, Capital Projects &Infrastructure Director, Engineering & Public Works • Stan Karwowski, MBA, CPA, CMA Division Head, Finance & Treasurer Vera A. Felgema/cher CSCMP, CPPO, CPPB, CPM, CMM III Manager, Supply& Services DS:mjh Recommended for the consideration of Pickering City Council L7)3r;;IZ jeix.e ZOi • • Tony Prevedel, P.Eng. Chief Administrative Officer • CORP0227-07/01 revised • 123 ATTACHMENT#, TOREPORT#s,_„_ Legislative Services Division Clerk's Office Directive Memorandum June 29, 2016 To: Richard Holborn Director, Engineering & Public Works From: Debbie Shields City Clerk Subject: Direction as per Minutes of the Meeting of City Council held on June 27, 2016 Director, Engineering'& Public Works, Report ENG 14-16 Request for Additional Funding for Consulting Services -Proposal No. RFP-4-2015-Palmer Bridge Council Decision Resolution #178/16 1. That the additional fee proposal as submitted by AECOM Canada in the amount of$71,682.00 (HST included) for the change in scope of work for the Palmer Bridge design and specifications be accepted; 2. That the total revised gross project cost of$271,640.00 (HST included) and the total revised net project cost of$244,620.00 (net of HST rebate) be approved; • 3. That the Division Head, Finance & Treasurer be authorized to finance the total revised net project cost as approved in the 2014 Roads Capital Budget in the amount of$244,620.00 by an additional transfer of$71,008.00 from the York Region SEC Funding Agreement; and 4. That the appropriate officials of the City of Pickering be authorized to take the necessary actions as indicated in this report. Please take any action deemed necessary. Debbie Shields hlr Copy: Chief Administrative Officer Director, Corporate Services & City Solicitor