HomeMy WebLinkAboutFIR 03-16 C4 O Report to
PiCKERiNG Council
Report Number: FIR 03-16
Date: November 21, 2016
From: John Hagg
Fire Chief
Subject: Fire Hall #2 Outdoor Diesel Generator
- Request for Quotation No. Q-26-2016
- File: A-1440
Recommendation:
1. That Quotation No. Q-26-2016 submitted by Standby Generator Services Inc. in the
amount of$76,235.45 (HST included) be accepted;
2. That the total gross project cost of$85,275.00 (HST included), including the amount of the
proposal and other associated costs, and the total net project cost of$76,793.00 (net of
HST rebate), be approved;
3. That Council authorize the Director, Finance & Treasurer to finance the net project cost as
follows:
a) The sum of $60,000.00, as provided for in the 2016 Capital Budget Fire Services, to
be funded by a transfer from the Rate Stabilization Reserve;
b) The sum of $16,793.00 to be funded from property taxes; and
4. That the appropriate officials of the City of Pickering be authorized to take the necessary
actions as indicated in this report.
Executive Summary: Fire Hall #2, located at 553 Kingston Road, currently relies on a
portable backup power generator to provide it with electricity in the event of a power failure. This
generator must be manually connected to the building during an outage, has limited power
generation capability and fuel capacity, and would not meet the operational needs for a long-term
power outage.
Request for Quotations No. Q-26-2016 was issued on June 28, 2016 to supply and install a new,
permanent outdoor diesel generator at Fire Hall #2 and closed on July 19, 2016. The lowest
quotation in the amount of$73,521.00 plus HST submitted by Standby Generator Services Inc.
exceeded the approved 2016 capital budget. The City engaged this vendor in negotiations and
obtained a revised price of$67,465.00 plus HST. This price also exceeds the approved 2016
Capital Budget by 14.4%. As per Financial Control Policy 11.02, capital expenditures that exceed
the budget by 10.0% require Council approval. Staff explored additional reductions to the
proposed scope of work and determined that the resulting cost savings were negligible, whereas
the impact on service reliability at one of the City's key emergency services facilities grew
FIR 03-16 November 21, 2016
Subject: Fire Hall #2 Outdoor Diesel Generator Page 2
Quotation No. Q-26-2016
significantly by making any additional cuts. The revised quotation No. Q-26-2016 submitted by
Standby Generator Services Inc. in the amount of$76,235.45 (HST included) is recommended for
approval. The total gross project cost is estimated to be $85,275.00 and the total net project cost
is estimated at $76,793.00 (net of HST rebate), including $8,000.00 in contingency allowance.
Financial Implications:
1. Quotation Amount
Quotation No. Q-26-2016 $67,465.00
HST (13%) 8,770.45
Total Gross Project Cost $76,235.45
2. Estimated Project Costing Summary
•
•
Quotation No. 0-26-2016 $67,465.00
Contingency 8,000.00
Total Cost $75,465.00
HST (13%) 9,810.00
Total Gross Project Costs $85,275.00
HST Rebate (11.24%) (8,482.00)
Total Net Project Costs $76,793.00
3. Approved Source of Funds
2016 Capital Budget— Fire Services
Expense Account Source of Funds Budget Required
5340.1607.6178 Rate Stabilization Reserve $60,000.00 $60,000.00
Additional Funds Property Taxes $0.00 $16,793.00
Required .
Total Funds $60,000.00 $76,793.00
Project Cost under (over) approved funds by ($16,793.00)
The estimated net project cost after factoring a contingency provision has resulted to an over-
expenditure of $16,793.00, and exceeded the approved budget by more than 10%. As per Item
11.02 of the Financial Control Policy, Council approval is being sought at this time in order to
proceed with the project.
C0RP0227-07/01 revised
FIR 03-16 November 21, 2016
Subject: Fire Hall #2 Outdoor Diesel Generator Page 3
Quotation No. Q-26-2016
The additional funds required will be funded from property taxes through savings realized from the
Fire Services Department operating costs.
Discussion: Fire Hall #2 is one of four fire stations operated by the City of Pickering Fire
Services, and is the only location not currently equipped with a permanent backup power
generator. In the event of a disruption of electrical service at Fire Hall #2, Fire Services staff must
manually connect a small portable generator with limited generation capacity and service duration
due to limited fuel capacity and supply on site. In case of an extended power outage or related
crisis, operation of this facility would be vulnerable to periodic disruptions for refueling and due to
the aging nature of the existing backup generator, which is approaching the end of its serviceable
life.
Interior installation was dismissed due to additional costs that would be incurred to create a fire
rated enclosure and by prolonging the installation as individual components would have to be
transported and assembled in the basement. Outdoor installation, surface mounted on a concrete
pad, is preferable from a cost perspective and a combined generator set with integrated double-
wall fuel tank eliminates the risk of soil contamination that accompany the use of underground
tanks, while also simplifying refueling operations.
The 2014 approved capital budget included project 5340.1401 for $35,000.00 for provision of a
permanent backup power generator at this facility. Request for Quotations No. Q-17-2014 and
No. Q-30-2014 were issued without success of obtaining acceptable quotations. The project was
re-budgeted and approved in the 2016 Capital Budget as project 5340.1607 for $60,000.00.
The lowest quotation No. Q-26-2016 submitted by Standby Generator Services Inc. exceeded the
2016 Capital Budget. Staff undertook negotiations with the Standby Services Generator Inc. to
obtain cost savings and obtained a further cost reduction of $6,056.00 (plus HST). Any further
reductions in scope will produce marginal savings, but risks compromising the required level of
service.
A contingency allowance of$8,000.00 has been added to this funding request to avoid the need
for further council approvals in case of small scale unforeseen conditions, that may be required to
complete the work.
The Health & Safety Regulations form, current WSIB Clearance Certificate, as submitted by
Standby Generator Services Inc., have been reviewed by the Coordinator, Human Resources and
are deemed acceptable. The Certificate of Insurance is deemed acceptable to Manager, Budgets
& Internal Audit. In conjunction with the foregoing approvals, staff have reviewed the Waste
Management Plan, the previous work experience of Standby Generator Services Inc. and the
references provided and all are deemed acceptable.
Upon careful examination of all quotations and relevant documents received, Fire Services
recommends the acceptance of Quotation No. Q-26-2016 submitted by Standby Generator
Services Inc. in the amount of $76,235.45 (HST included) and that the total net project cost of
$76,793.00 be approved.
CORP0227-07/01 revised
FIR 03-16 November 21, 2016
Subject: Fire Hall #2 Outdoor Diesel Generator Page 4
Quotation No. Q-26-2016
Attachments:
1. Supply & Services Memorandum dated July 19, 2016.
2. Supply & Services Memorandum dated November 3, 2016
Prepared By: Approved/Endorsed By:
i (RJ
Vince Plouffe John Hagg
Supervisor, Facilities Operations Fire Chief
Bn. . • _ d Marisa ino
Division ead, Operations Director, Community Services
Vera A. Felg: acher Stan Karwowski, CPA, CMA, MBA
C.P.P., CPPO, CPPB, C.P.M., CMM III Director, Finance & Treasurer
Manager, Supply & Services
Caryn Kong, CPA, CGA
Senior Financial Analyst
Capital & Debt Management
BD:mc
Recommended for the consideration
of Pickering City Council
/ ,„l// Woo-- . /o, Zoi
Tony Prevedel, P.Eng.
Chief Administrative Officer
CORP0227-07/01 revised
•
ATTACHMENT#„ TO REPORT#�0 3-l4
city .
m
NNE410 Memo
To: Marisa Carpino July 19, 2016
Director, Culture'& Recreation
•
From: Vera A. Felgemacher
Manager, Supply& Services
• Copy: Manager, Culture & Recreation
Supervisor, Culture & Recreation
Supervisor, Supply& Services
•
• Subject: Quotation No. Q-26-2016
Fire Hall #2 Outdoor Diesel Generator
File: F-5300-001
•
Quotation Q-26-2016 was sent to seven (7) potential bidders via email and three (3)
submissions were received by the official closing date and time of Tuesday, July 19, 2016 at
12:00 Noon.
There are 2 stages in the evaluation process which are outlined in Part 2—Evaluation of
Quotations of the quotation document.
Stage I determines which submissions satisfy all the mandatory submission requirements and
provides Respondents the opportunity to rectify deficiencies. Three (3) quotations proceeded'to
Stage II evaluation.
A summary of the Stage II evaluation results for each quotation is attached.
Price Quoted Total
Points 'Amount
Points •
Vendor Name • Awarded (excluding Awarded
HST)
Standby Generator Services 100 $73,521.00 100
Inc.
Northern Generators Company 82.15 $89.495.00 82.15
Ltd.
Genrep Ltd. 64.10 $114,700.00 64.10
Standby Generator Services Inc. is the highest-scoring respondent.
•A budget of$60,000 was provided to Supply& Services for this procurement.
in accordance with Purchasing Policy Item 06.04, the authority for the dollar limit as set out
below excludes HST.
•
ATTACHMENT# —TO REPORT# 1 R'd 3—R6
In accordance with Purchasing Policy, Item 06.11,where the compliant quotation or tender meeting
specifications and offering best value to the City is acceptable or where the highest scoring proposal
is recommended and the estimated total purchase price is: . .
(a) Over$30,000 and up to$75,000, the Manager may approve the award, subject to
consultation with the appropriate Director and confirmation of financing by the Treasurer.
Once this approval is received, an approved "on-line" requisition will be required to
proceed.
Please direct all enquiries to Supply& Services. Respondents will be advised in due •
course.
If you require further information or assistance, do not hesitate to contact me or a member
of Supply &Services. •
•
VAFIgb •
Attachments (3) • • •
•
•
•
•
•
•
•
•
•
•
• Page 2 of 2
ATTACHMENT# 2- TO REPORT#_-EL C3- 1
•
cm, 00
NONCIONIIi2C
Memo
To: Marisa Carpino November 3, 2016
Director, Community Services
From: Vera A. Felgemacher
Manager, Supply& Services
Copy: Manager, Facilities Operations
Supervisor, Facilities Operations
Supervisor, Supply & Services
Subject: Quotation No. Q-26-2016
Fire Hall #2 Outdoor Diesel Generator
File: F-5300-001
Further to memo dated July 19, 2016 and direction given to Supply & Services to contact the
highest scoring respondent- Standby Generator Services Inc. to review the lowest cost quotation
for negotiation, as pricing received was over-budget.
Standby Generator Services Inc. was able to provide revised pricing in the amount of$67,465.00
plus HST.
In accordance with Purchasing Policy Item 06.04, the authority for the dollar limit as set out below
excludes HST.
In accordance with Purchasing Policy, Item 06.11, where the compliant quotation or tender meeting
specifications and offering best value to the City is acceptable or where the highest scoring proposal is
recommended and the estimated total purchase price is:
(a) Over$30,000 and up to$75,000, the Manager may approve the award, subject to consultation
with the appropriate Director and confirmation of financing by the Treasurer.
A budget of$60,000 was provided to Supply & Services for this procurement. The revised price
remains over-budget. In accordance with the Financial Control Policy Item 11.04, Current and
Capital Budget expenditures in excess of the limits established in Item 11.01, 11.02 and 11.04
shall require the approval of the Treasurer, the Chief Administrative Officer and Council.
Once this approval is received, an approved "on-line" requisition will be required to proceed.
Plea-e direct all enquiries to Supply & Services. Respondents will be advised in due course.
'If yo require further information, do not hesitate to contact me or a member of Supply& Services.
VAF
Attachments