Loading...
HomeMy WebLinkAboutENG 19-14 Cat/00 =`_ Report to Revised Executive Committee PICKERING Report Number: ENG 19-14 Date: September 8, 2014 From: Richard Holborn Director, Engineering & Public Works Subject: Stormwater Drainage in the Hamlet of Claremont- - Update on the Claremont Drainage Feature Cleanout - File: A-1440 Recommendation: 1. That Report ENG 19-14 of the Director, Engineering & Public Works concerning Stormwater Drainage in the Hamlet of Claremont be received; 2. That Council change the 2013 Capital Budget approval and corresponding funding for the Claremont Drainage Feature Cleanout (Account 5410.1301) from $550,000 to $41,700 and that the Treasurer be authorized to fund the expenditure from a transfer from the Rate Stabilization Reserve; and 3. That Staff be authorized to finalize the scope, and prepare Terms of Reference of a Claremont Master Drainage Plan in order toinitiate a Request for Proposal for consulting services for the study, with funds being proposed in the 2015 Current Budget. Executive Summary: After a number of complaints from affected residents, Council approved the Claremont Drainage Feature Cleanout in the 2013 Capital Budget. Through the detailed design process for the Claremont Drainage Feature Cleanout project it was determined that the project was not feasible due to the shallow depth of the TransCanada pipeline underneath the ditch. It is recommended that the Claremont Drainage Feature Cleanout project be reduced to the expenditures for the consulting services spent to date,and that funding be provided in the 2015 Current Budget for the completion of a Master Drainage Plan for Claremont. The Master Drainage Plan will analyze the existing drainage patterns and infrastructure in Claremont, identify deficiencies and propose recommended projects to optimize and improve the drainage system. Financial Implications: This project was originally financed through the issuance of ten year external debt. The project's scope and direction has changed significantly and therefore the project is no longer proceeding as originally planned. Recommendation Two reduces the 2013 budget approval to final project costs and provides an alternative 35. • Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 2 financing source - Rate Stabilization Reserve. There are sufficient funds in this Reserve to meet the revised project cost. Discussion: Due to the age of development in the Hamlet of Claremont, the drainage infrastructure in the community was not built to meet formal and current engineering standards. The City periodically receives drainage complaints that are primarily related to nuisance drainage issues caused by blocked driveway culverts, cross road culverts, and roadside ditches requiring maintenance. These nuisance issues are routinely resolved by City forces. Staff are aware of two properties that have experienced repeated basement flooding • from surcharging gravity foundation drains, and one property that has experienced surface flooding from road drainage. These drainage issues are more serious in nature and they have been mitigated through remedial works by the City and the affected - homeowner. It is worth noting that the.Region of Durham completed a study on the Central Street drainage system in 1996 in response to drainage issues associated with the road right-of-way (Stormwater Management Study for Road Improvements for Regional Road No. 5 through the Town of Claremont, Paul Theil Associates, 1996). The recommendations of that report were implemented when the Region reconstructed Central Street in 1996. The information in Tables 1 and 2 provides some context regarding the nature of the drainage issues in Claremont. It can be seen from the information in the tables that the drainage problems are mainly nuisance issues and occur primarily during the spring. Table 1 - Summary of Flooding Complaints in Claremont since 2009 Type of Drainage Number of Complaints Action Complaint over the last 5 Years Basement Flooding 2 Resolved by private contractors Surface Flooding 1 City retained contractor to raise the road curb Wet yards due to the 4 No action at this time Claremont Drainage Feature Nuisance Drainage (Wet 7 Resolved by City forces or yards, driveway culvert currently being reviewed. replacements, re-ditching) 36 CORP0227-07/01 revised Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 3 Table 2 - Drainage Complaints by Season Season Complaint was Received Number of Complaints Spring • 9 Summer 2 Fall 2 Winter 1 An analysis of the rainfall data from 2009 to 2013 indicates that there have been some significant rainfall events in Claremont during this period. A storm that occurred on July 25, 2009 is characteristic of the intense summer storms which frequently cause drainage issues in urban areas. The storm was approximately equivalent to the City of Pickering's 2 hour, 50 year return period storm. Notwithstanding, the City's Customer Care Centre did not receive any drainage complaints following this storm. The only customer care complaint that was received following any of the large rainfall events that occurred from 2009 to 2013 was after the April 3, 2009 event, and was a request for an update on work the City was completing on the Canso Drive ditch. Claremont Drainage Feature The 2013 Stormwater Capital Budget allocated funds for the Claremont Drainage Feature Cleanout project. The Claremont Drainage Feature, hereinafter referred to as the ditch, originates at a storm sewer outfall on Central Street west of Franklin Street and flows south through private property, through Claremont Park, through more private property and west under Old Brock Road south of Bovingdon Place (refer to Figure 1). With respect to ownership, where the ditch is on private property the City has an 8 m wide easement with the exception of the section through 4933 Brock Road. CORP0227-07/01 revised 3 7 Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 4 • ' ,giiiP 3.x~R 1 ,y. - •-5\ � •.~+¢li .I '" 7e------ F:`• .it __ __ ! 1 1--•t_. ' ' \ LL �H I 11 s \- y - _.,-•�i PLC �•—''.�`•y_.` 1 v __"r"' S`.•- ,,.1 ,,,. .:.. ...--- . ,2'.„:-.....\ --.._..-.:.':,.. Ink\l.......\-- ...... --$.,, v .„ ... -. .. , , ... ...- "5\ \:.:... '.. ... "\;, ..."\ - - 4 A ' ‘ .--• ' .. '',.' / S • .1\9 4 ', l _ _. IrL,S,�_ •it `lE.�-6r`: •• /fie.; • } t ' te•, -,�" -. t tt_ `'Ll 1 Kam.• -' 1! .1 + No Easement } ;� t-2-- � ;i� Claremont Drainage ti , t Feature Figure 1 — Claremont Drainage Feature The drainage area of the ditch at the southern limit of the study area is 32 hectares (refer to Figure 2). A significant portion of that drainage area.(9.3 hectares) is from the vacant farm field north of Franklin Street, which is proposed for development by Geranium Homes pending planning approvals from the provincial government, the Region of Durham and the City of Pickering. The remainder of the drainage area is comprised of roads and mainly low-density residential development. • • 38 CORP0227-07/01 revised • • Report ENG 19-14' September 8, 2014 • Subject: Stormwater Drainage in the Hamlet of Claremont • Page 5 \�\. /1 . `\ -_...._.' . LANE STREET.... Y 4-H r 0 0I I O , hii CD. C:i J� O,' • a_ - j 0,02C+4-1. Z: i al A 1 : . n J t iJ JOSEP• -C!4rf.M DRAINAGE] - S . - G+RGr . • ' - ` TFEE, z AREA z I • E . -.,. vn' '• Q CL a' r- CENTRAL ? '�-/ a " c Q F- ; S i R�_.ET . in �n; L. • u'• W LLI`GT�N ST. L SCi`J S j i PUB!. Q a ! Q STUDY AREA FORT 1 ° i!, / �' � .s i � �$.; i DITCH CLEANOUT < .' ,;U 'CLU_. ;7 Z, j �q. X00'OV`/ p4`.__.___-.. I LAN E_.. 14-11 .a.-i:v // J 1 • wEZ —AC - ------..- I /%/l S v • TRANS-CANADA � / , i / PIPELINE '��� �.. y 3OVI,21D O t �� O: :I'LA"r i .........", ' LARE 1 :� /f, C ANT Figure 2 - Claremont Drainage Feature Drainage Area Flow to the ditch is controlled by a weir at a control.manhole on Central Street. The control manhole was installed by the Region in 1996 to reduce the amount of flow being conveyed to.the ditch in response to drainage concerns raised by residents. The configuration of the system consists of the storm sewer from Central Street east of the ditch (which includes drainage from Franklin Street), and the Barclay Street ditch which flows into the control manhole. At the manhole, the outlet flow is split between the ditch flowing south and the storm sewer continuing west along Central Street to its outfall near . the Claremont Public School. Staff retained Cole Engineering in 2013 to complete a design for the ditch cleanout and secure the necessary approvals and permits from the Toronto and Region Conservation Authority (TRCA) and the Ontario Ministry of Natural Resources (MNR). The scope of the cleanout project was from Wellington Street to Bovingdon Place with the respective road culverts representing fixed points that the cleanout project had to tie into. • CORP0227-07/01 revised 39 Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 6 The drainage ditch is being deemed as a watercourse by TRCA, which is subject to their permit process under Ontario Regulation 166/06. Although redside dace are not found in the ditch, the MNR deems it contributing habitat due to the presence of redside dace in the subwatershed. As such, MNR's approval is required and any works must take place during the timing window of July 1 to September 15. Cole Engineering evaluated design slopes on the ditch of 0.5%, 1% and 2%. Regardless of the design slope, the ditch would need to be excavated to provide the necessary grades. It should be noted that the City's engineering standards specify that the minimum acceptable slope on a ditch is 2%. To provide some context, the minimum acceptable slope to allow for proper drainage on roads is 0.5%. The City had the subsurface utilities mapped which determined that the TransCanada pipeline is only 1.3 m below the ditch. Any work within the TransCanada right-of-way requires their approval and the minimum allowable cover on the pipeline is 1.2 m. It should be noted that this is TransCanada's main east-west pipeline and the costs associated with relocating it would be significant. Staff have found that similar pipeline relocation projects in surrounding municipalities cost in the order of millions of dollars. Given the restriction of the shallow pipeline, the maximum possible slope which can be achieved on the ditch is 0.5%. A ditch with a slope of 0.5% translates into 5 centimeters of vertical fall for every 10 linear meters of ditch. It is difficult to construct a ditch with this degree of precision. Furthermore, given the gentle slope of the ditch, vegetation growth may prevent the ditch from functioning properly. As this ditch is regulated by both TRCA and MNR, the City would need a permit to cut vegetation as this would constitute in- water works. While a 0.5% ditch will be an improvement over the existing condition, it is not certain that the cost can be justified given the nature of the drainage complaints received to date. There are 9 properties that would directly benefit from this cleanout and the estimated cost to complete the project is approximately $385,000.00. Based on the above, staff are recommending that the balance of the Claremont Drainage Feature Clean Out project be cancelled and that alternative solutions be reviewed. Given the constraints and the ineffectiveness of the resulting design of the ditch cleanout project, staff are reviewing options and alternative methods of improving the drainage system in Claremont. A cost-sharing arrangement for the proposed options will be explored with the Region of Durham since Central Street is a Regional Road, and its associated drainage infrastructure are an important component of any solution. The options are presented below. Option 1 - Complete a Master Drainage Plan Class Environmental Assessment for Claremont The purpose of completing a Master Drainage Plan is to comprehensively analyze the existing drainage system throughout Claremont, identify deficiencies and recommend 40: CORP0227-07/01 revised Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 7 projects to improve the drainage system. This Master Drainage Plan would be very similar to the Whitevale Master Drainage Plan that was completed in 2013. Furthermore, given that Claremont was built prior to modern drainage standards, the Master Drainage Plan will also determine the level of service that can be provided. Setting the level of service is a policy decision made by the municipality that sets the minimum standard for the drainage system. The purpose of setting the level of service for the drainage system is to provide some protection for the City from claims should an 9 Y p p event occur that is larger than the level of service set. Some of the background work for the Master Drainage Plan has already been completed through the Claremont Flood Mitigation Study completed by AECOM in 2012. Staff have reviewed the AECOM study and have determined that the scope was too narrow, the model overestimates flows, and the methodology used to evaluate alternatives is oversimplified. However, the AECOM work is a good starting point and can be built upon. This study could proceed in 2015 subject to budget approval. Option 2 - Modify the Weir in the Control Structure on Central Street This would be a scoped version of the Claremont Master Drainage Plan that would focus on the feasibility of modifying the weir in the control manhole on Central Street to send increased flow west to the outlet on Canso Street and less flow south to the ditch. It is recommended that the analysis completed by AECOM be calibrated and that a field survey determine whether there are any foundation drain connections along Central Street. The hydraulic impacts of modifications to the weir in the control manhole on Central Street can then be analyzed and a modified weir can be designed and constructed. This project could proceed in 2015 subject to budget approval. • Recommendation Staff recommend that the funds allocated for the Claremont Drainage Feature Cleanout in the 2013 Capital Budget be reduced to the expenditures that have been spent on consulting services to date, and that new funds be proposed in the 2015 Current Budget to undertake the Claremont Master Drainage Plan. The Master Drainage Plan will analyze the existing drainage system in Claremont, identify deficiencies and propose recommended projects to optimize and improve the drainage system. By completing a full analysis of the drainage system, the City can ensure that projects are prioritized to maximize the benefit to the community as a whole. Attachments: 1. Not Applicable CORP0227-07/01 revised 41 Report ENG 19-14 September 8, 2014 Subject: Stormwater Drainage in the Hamlet of Claremont Page 8 Prepared By: Approved/Endorsed By: lOr Tom Dole, P.Eng. Ric and Holb!in, P. Eng. Sr. Water Resources Engineer Dir-ctor, Engineering & Public Works Prepared By: Approved/Endorsed By: Marilee Gadzovski, M. Sc. (Eng.), P.Eng. r Stan Karwowski,-CPA, CMA Division Head, Water Resources & f`'Division Head, Finance & Treasurer Development Services TD:Ir Recommended for the consideration of Pickerin ity Council 67])4 ? /1i Tony Prevedel, P.Eng. j Chief Administrative Officer • • 42 coRP0227-07/01 revised