HomeMy WebLinkAboutENG 14-13 City A. Report to Council I SKEWIKX Report Number: ENG 14-13 Date: October 28, 2013 From: Richard W. Holborn Director, Engineering & Public Works Subject: Noise Attenuation Wall — Bayly Street - File: A-1440 • Recommendation: 1. That Report ENG-14-13 from the Director, Engineering & Public Works regarding the construction of a Noise Attenuation Wall on Bayly Street be received; 2. That the Mayor and Clerk be authorized to execute an Encroachment Agreement with the Regional Municipality of Durham to address liability and maintenance responsibilities of the noise attenuation wall located on the Bayly Street road allowance, substantially in the form of Attachment#1, subject to such minor revisions as are satisfactory to the Director, Engineering & Public Works, and the Director, Corporate Services & City Solicitor; 3. That the Mayor and Clerk be authorized to execute an Agreement with the Ministry of Transportation Ontario for the cost-sharing of the construction of the noise attenuation wall, substantially in the form of Attachment#2, subject to such minor revisions as are satisfactory to the Director, Engineering & Public Works and the Director, Corporate Services & City Solicitor; and 4. That the appropriate City of Pickering officials be authorized to take necessary action to give effect thereto. Executive Summary: The residents of Marinet Crescent have been requesting appropriate measures to address noise, which is a result of the widening of Bayly Street by the Region of Durham, widening of Highway 401 by the Province of Ontario, and noise and vibrations associated with the VIA/GO line all running parallel to the rear of their properties. After Council passed Resolution #173/04 in December 2004 requesting a review of this matter, discussions took place between the City, the Region and the Ministry of Transportation. Noise testing was carried out and has confirmed the level of noise is in excess of acceptable standards, however, funding for the project was not available. The Ministry of Transportation Ontario has received funding and is now ready to proceed with the construction of the noise attenuation wall this year. In order for the project to proceed, the City must enter into an encroachment agreement with the Region of Durham to address liability and future maintenance responsibilities and a cost-sharing agreement with the Ministry of Transportation Ontario to address our financial contribution to the project. Report ENG 14-13 October 28, 2013 Subject: Noise Attenuation Wall — Bayly Street Page 2 Financial Implications: In 2011, Council approved $100,000 in the Roads Capital Budget for the City's contribution of the cost sharing for this approximately $1,000,000 project. Future maintenance costs associated with the noise attenuation wall will be addressed in future years' current budgets. The Ministry of Transportation has recently tendered the project and is prepared to award the tender. The City must enter into a cost-sharing agreement with the Ministry of Transportation as a mechanism to flow our agreed upon cost-sharing amount of $100,000 to them. Discussion: As far back as December 2004, when Council passed Resolution #173/04, it has been recognized that the residents of Marinet Crescent have been requesting appropriate measures to address noise which is a result of the widening of Bayly Street by the Region of Durham, widening of Highway 401 by the Province of Ontario, and the noise and vibrations associated with the VIA/GO line all running parallel to the rear of their properties. Noise testing and a technical feasibility study were carried out in 2005 and confirmed the level of noise is in excess of acceptable standards. The Ministry of Transportation Ontario is now ready to proceed with the construction of the noise attenuation wall this year, as funding has been made available. A Public Information Centre for this project was held at the Pickering Civic Complex on Wednesday, June 19, 2013. The preferred alignment of the noise wall along the south side of the sidewalk on Bayly Street was presented to the residents of Marinet Crescent. In 2006 a tri-party agreement was to have taken place between the Region of Durham, the Province of Ontario and the City of Pickering to each pay a portion of the total costs to construct a noise attenuation wall along the rear lots of all homes on Marinet Crescent that abut Bayly Street. The City passed Resolution #21/11 in February 2011 advising the province that Pickering will budget $100,000 towards the project and requesting the Region of Durham to assume responsibility for the maintenance costs associated with the wall. The Region does not currently have a guideline or policy that addresses the installation or long term maintenance of retrofit noise attenuation barriers abutting a Regional Road right-of-way. Since the Region's inception, the Region has not maintained or replaced rear lot fencing along Regional Road corridors. Therefore, the Region has advised that responsibilities associated with the construction, maintenance and liability of the retrofit noise attenuation wall, are with the local municipality. Since the Region of Durham does not assume any responsibility related to the installation and maintenance of the retrofit noise attenuation wall, an encroachment agreement will be required to permit the placement of the noise wall within the Regional right-of-way on Bayly Street. The Region has provided approval for the noise attenuation wall to be constructed, subject to the City entering into an encroachment agreement. The City will be responsible for the maintenance of the wall upon completion of the construction. Report ENG 14-13 October 28, 2013 Subject: Noise Attenuation Wall — Bayly Street Page. 3 The City must also enter into an agreement with Ministry of Transportation Ontario for cost-sharing for detail design, tendering and construction of the noise attenuation wall. The City will have to cost-share on this project in the amount of$100,000 from funds approved in the 2011 Roads Capital budget project 5320.1121. The project will be financed through a five year internal loan. The Engineering & Public Works Department recommends that Council authorize the Mayor and Clerk to enter into an agreement with the Ministry of Transportation Ontario for the cost-sharing for the construction of the noise attenuation wall on Bayly Street. Staff also recommends that Council authorize the Mayor and Clerk to enter into an Encroachment Agreement with the Regional Municipality of Durham for the maintenance of the noise attenuation wall on Bayly Street. Attachments: 1. Encroachment Agreement with the Regional Municipality of Durham 2. Agreement with Her Majesty The Queen in Right of the Province of Ontario, as Represented by the Minister of Transportation for the Province of Ontario 3. City of Pickering Resolution #173/04 4. City of Pickering Resolution # 21/11 Prepared By: Approved/Endorsed By: /Aat / cif "I Darrell Selsky, C , C Ill / Rich-rd Holbor,", P. Eng. Manager, Capital Projects & Infr.structure Dir.etor, Engineering & Public Works Stan Karwowski, MB Division Head, Finance & Treasurer DS:ds Recommended for the consideration . of Pickering City Council a.;teudi 0417 2's zo/3 Tony Prevedel, P.Eng. Chief Administrative Officer ATTACHMENT# I -.. TO REPORT# ENL& 14-13 I of 14 0 September 9,2013 RECEIVED • DURHAM REGION SEP 13 2013 City of Pickering CITY OF PICKER1'+I One The Esplanade tG1ERtNG SERVICES The Regional Pickering,ON Municipality L1V 6K7 of Durham Works Department Attention:. Darrell Selsky 605 ROSSLAND RD.E. • Re: Encroachment Agreement City Pickering P.O.BOX 623 greement between the Ci of Pickerin WHITBY ON L1N 6A3 And the Regional Municipality of Durham CANADA Noise Attenuation Barrier—Bayly (RR#22),Pickering 905-668-7711 ti Bi y y Stree t,(RR#22,Pickerin 1-800-372-1102 Our File: ENC22-11 Fax:905-668-2051 Email:works@durham.ca Enclosed please find four(4)copies of the above noted Encroachment www.durham.ca Agreement to be signed by the City of Pickering. Please return all four(4) a R.Curtis,P.Eng.,MBA copies to the undersigned. Once signed by the Regional Municipality of Commissioner of Works Durham a fully executed copy will be returned to your office. If you have any questions or concerns,please do not hesitate to call. . Thank you, ../---; --....ai 'Zit-------..... Catherine Stobbart Real Estate Division Encl. • /cs $. x nce for hies" '61W C 100%Post Consumer • ATTACH MENT# 1'. TO REPORT# CNG: -13 a of 14 THIS ENCROACHMENT AGREEMENT made this 30th day of August,2013. BETWEEN: THE CITY OF PICKERING (the"City of Pickering") -and- THE REGIONAL MUNICIPALITY OF DURHAM (the"Region") WHEREAS the Region has jurisdiction of Bayly Street(Regional Road 22)(the "Road Allowance"). AND WHEREAS the City of Pickering intends to construct a noise attenuation barrier which will encroach on the Road Allowance at the location in the manner as shown on the attached Schedule"A"(the"Encroachment"); AND WHEREAS the City of Pickering will be solely responsible for all costs, present and future, associated with the design, construction, repairs and maintenance of the Encroachment on the Road Allowance and the adjoining Boulevard as depicted in Schedule"A"(the"Boulevard"), and the construction and maintenance of the Encroachment and Boulevard shall be without cost to the Region.; AND WHEREAS Regional Council has authorized the execution of an encroachment agreement with the City of Pickering; NOW THEREFORE THIS AGREEMENT WITNESSES the parties agree as follows: 1. The Region grants to the City of Pickering permission to maintain the Encroachment provided the City of Pickering is not in default of any of its obligations under this Agreement. 2. The parties acknowledge and agree that upon the removal or destruction of the Encroachment,the permission hereby granted and this Agreement will automatically terminate and be of no further force or effect. 3. Nothing contained in this Agreement shall be construed as giving the City of Pickering anything more than permission to maintain the Encroachment and the Boulevard. 4. The City of Pickering shall at all times fully indemnify and save harmless the • ATTACHMENT# TO REPORT# ENG Iq-13 3 o 14 -2- Region against all actions,suits, claims and demands whatsoever that may be brought against or made upon the Region and from and against all loss,costs, damages,charges and expenses whatsoever that may be incurred, sustained or paid by the Region for or by reason of or on account of the permission hereby granted to the City of Pickering or the maintenance of the Encroachment. The City of Pickering shall maintain the Encroachment(noise wall)and also be responsible for the maintenance of the Boulevard between the back of curb and the residential property line for the entire length of the Encroachment(noise wall), including maintenance of the ditch and ditch inlet catchbasins.The City of Pickering shall deal with and defend, at its own expense, all actions, suits, claims and demands which may give rise to any loss indemnified hereby by any person claiming to be entitled to any monies from the Region,and the Region agrees that it shall not unilaterally settle any such actions,suits, claims or demands without the consent of the City of Pickering. The Region shall give the City of Pickering,notice of any action,suit, claim or demand which comes to its attention and shall cooperate with the City of Pickering in any matters that are reasonably necessary to the proper dealing with or defence of any such action, suit,claim or demand. 5. The City of Pickering agrees to take out and keep in force during the term of this Agreement a policy of Comprehensive General Liability insurance acceptable to • the Region providing coverage in respect of any one incident pertaining to the Encroachment to the limit of at least Five Million Dollars($5,000,000.00) exclusive of interest and costs,against personal injury or loss or damage to property and that such policy will name the Region as additional named insured thereunder and will protect the Region against all claims or damage or injury, including death to any person or persons, or damages to any property of the Region or any other public or private property resulting from or arising out of any act or omission on the part of the City of Pickering,their servants or agents and persons permitted thereon by the Owner and to forward evidence of such coverage to the Region upon request. Such insurance policy shall contain provisions for cross liability and severability of interest and further that the policy will not be changed or amended in any way or cancelled until 45 days after written notice of such change or cancellation shall have been given to the Region. 6. The City of Pickering shall pay to the Region any costs associated with maintaining, repairing, relocating or reconstructing the Road Allowance that are attributable, in the sole opinion of the Region,to the existence of the • ATTACHMENT#_LL_a TO REPORT# CNC„ 103 -3- Encroachment. The City of Pickering shall not maintain any action or assert any claim against the Region for any damage to any part of the Encroachment that may result from the maintenance, repair, relocation or reconstruction of the Road Allowance. 7. Where, in the opinion of the Commissioner of Works of the Region, it is necessary to remove or alter the Encroachment or any part thereof,the City of Pickering shall, at its own expense,and to the satisfaction of the Commissioner of Works, alter or remove the Encroachment or any part thereof from the Road Allowance, and restore the affected area upon receiving notice in writing from the Commissioner of Works to do so,without being entitled to any compensation whatsoever for such alteration or removal and restoration. If the City of Pickering • neglects, refuses or fails to do so within 30 days of receiving the aforesaid notice to alter or remove,then the Region may remove or alter the Encroachment or parts thereof specified in the notice from the Road Allowance and restore same to a safe and proper condition as determined by the Commissioner of Works at the expense of the City of Pickering and the Region may recover such costs from the City of Pickering in a like manner as taxes. 8. The City of Pickering agrees that for the purpose of this agreement, notice may be given to the City of Pickering by mailing the same, by prepaid registered mail, addressed to the City of Pickering at its address as last known and to the Commissioner of Works. Such notice shall be deemed to have been received by the Owner five(5)days following the date when it was mailed. • 9.. Upon removal of the Encroachment,the City of Pickering shall be entitled to a • full release from the Region of all obligations under this Agreement. 10. The burden of this Agreement and of all the covenants herein contained shall be binding upon and enure to the benefit of the parties hereto and their respective heirs,executors,administrators,successors and assigns. 11. The City of Pickering acknowledges and agrees to bear full legal and registration costs associated with the registration of this Agreement against title to the Property if required. 12. This Agreement shall read with all changes in number and 9 ender as may be appropriate or required by the context. . . ........ . ATTACHMENT# / TO REPORT# ( I4-13 of -4- 13. Any reference in this Agreement to the Region and/or the City of Pickering includes the employees and/or duly authorized representatives and agents of the respective parties to this Agreement. 14. It is agreed that this Agreement, including attached schedules, and recitals are legally binding upon the parties to the Agreement and embodies the entire agreement of the parties with regard to the matters dealt with in it, and that no understandings or agreements,verbal or otherwise,exist between the parties except as expressly set out herein. IN WITNESS WHEREOF the parties have affixed their corporate seals,attested by the hand of its duly authorized officers. ' THE CITY OF PICKERING Dave Ryan, Mayor (c/s) Debbie Shields, Clerk THE REGIONAL MUNICIPALITY OF DURHAM Roger Anderson, Regional Chair&CEO (c/s) • D. Bowen, Regional Clerk • • CONTRACT •DRAWINGS CONTRACT NO. 2013-2028 n BOOK 1 OF 1 • m' z 3 -0 Cl)c • CENTRAL REGION cH C ., [r_e- o O rri W • rte' V in istry of Transportations Ontario • INDEX • W.P. No. 2326-10-00 Contract No. 2013-2028 • • Sheet Sheet No. ' Description No. Description COVER SHEET TITLE SHEET/KEY PLAN INDEX CONTRACT DRAWINGS 01 REMOVALS 02-04 NEW CONSTRUCTION m 05-00 MISCELLANEOUS DETAILS Z —4 0 QUANTITY SHEETS �+ 01 EARTH EXCAVATION(GRADING) Q 02-03 MISCELLANEOUS I • . 0 • 1 1 REGIONAL MUNICIPALITY OF DURHAM CITY OF PICKERING I Y e ` / �� W No 2326-10-00 Contrast No 2013-2028 � ! ///� Work of NOISE WALL BARRIER i \-1\ '�./� {4iNwy No NIA+ District No CEPfIRAL /� O, lnca0on BAriY STREET, PICKERING C>'10,,,..6.s., g0 SOUTH OF 401, EAST OF WHITES ROAD C-: i/ Station 10+000.000 to 10+382.000 m �yN PP-�O J "//• Length 0.4 km. /�O \ `� 1 �Q. Reference Plans B-PIan:6-2-401-36206 �✓• it 4AP9 Ge O/a 7 x —corn �s o O 1 PR IP % O0. 71C P.Ens. It�' P� � Date� Manager,Engineering .... y,z7-' A s KEY MAP l', N.T.S. P.Eng. , �/v Date Regional Director . N / Ministry of Transportation �r� • 11 Ontario • • • METRIC COT O N • �} WP _ !l� - REMOVALS SHEET LIMIT OF REMOVAL STA 10.00D TO STA 10.382 1 STA. 10+029 ,,,M, ... 01 o + o o + E)OSING REMOVED 01 RAMPML (A + - y-.z.�...-..s....._...-.,s�.._z._.....TO•sxE�vi� _:.aan, xm-a:;. "_ .. ..�z,¢-.nama i-.v-aea... '-_s_z.s.v.E...:..�r.-.,.".=ate=-na_z-ssao ". �� ° BAYLY STREET V �Tr-____._ _ "°`' .>.-............� -�-yam --.w.._�: __ _ -___- —_ --- bu -- — _ ` -'� -sF— r ass _ ss sr sr ph sr v L F S F .__ —_-C L F _- cleel Fen... E i ._ ._._ ."___ __ _ 4, •__---SF NP W Tt]O tp ASP4LLT To or a —1 D • y S-- 3 m Z Q ti LEGEND —1 8 N ,f• 1 tom'PEDESTRIAN HANDRAIL REMOVAL _.___ _ _ __—___ -®_.... A.md_.� __ �J_�g�.Y_4REET _ ® ASPT PA VEM0NT TO RE SF`__I^-._- _--••�°`°° ,.•'..- -: .-_._ -SP- - RMflIFA ., -__ 9E _ ....--_ -___ _._._._ _-_-. '- OPSO 219 110 ;-- SILT FENCE P 0 "-I LIMIT OF REMOVAL ^�( rrt ISTA. 10+371 V ko _ ---_-__1___ .L+are ii i Cp .,�.ae_-_._—_9AriY_ SR-EELS_.p,.o,�_,��, __._.�______ O_---� sr L6 p 1 — SOUP z S6 • • • • METRIC PLATE No CONT @ ' LIMIT OF CONTRACT WP STA. 9+500 • • : J40TE:. NEW CONSTRUCTION SHEET BREAKPOINTS ON THE CENTERUNE ALIGNMENT OF NOISE STA 10+000 TO STA 10+160 02 BARRIER ARE APPROXIMATE LIMIT OF CONSTRUCTION STA. 10+000 . I ,.,,,n tosE 131446g 5.0m REENTER NOISE BARRIER 1 (EXISTING RETAINING WM.E SECTION) .I 5.0m RETAINED NOISE BARRIER (ASPHALT BACKSLOPE TO BE REMOVED-SECTION) 5.0m NOISE BARRIER 5.0m RETAINED NOISE BARRIER 1 • :f. -0.6m OFFSET FROM BACK -c-B3 • POST 4. 8 o BACK OF SIDEWAUT APPROX.CENTERLINE OF 8 e OF SIDEWALK TO FACE OF ... g . NOISE BARRIER A it; o% • + ,r,-21.r.,,..m.-...; --1 L 4 07100 . > ----- . n °TM°F WCH REFER TO SHEET 5 AND 6 FOR DEEMS . Is., ■• REGARDING MEG AR BETWEEN SIDEWALK tr"."1 M :Om DOUBLE SWING CHNN-LINK GATE ANT4N01.1E ti:'136:11NO. ....., /t 0150 972.102 . 1/ 0 . • . kr ..„ 5.0m-MANED NOISEILARRIER --1- 5.0,9 NOI-S4ARRIER -1— ' j.061 REJOINED IISE BAfjRIER ' - --T —510rn RETUNED NOISE 4. - 1.0m NOISE BARR ER I _(EIGMIG"-MINING WALL.SS1029, _ LIALT LOPUTO ario,SIMON) I 102— ----1 1 - 1 1 T STEP DOWN I ---1- . 1___ 1 ____—____--1 I — --------I_ L_____I______ ---t- --1----1 _is.'" ' — i I -1-- 1 I 1 1 j 1 1 TOP OF 5m NOISE : •RIER I I I I -..4,.......M 100-----1- -- --- — — — _ I--- . [ - -- --- 100 -7-- 7 I I . 1 i 1 ___i_ I meolummo_ 1 _ , . J______. 1 I 1 1 __ .. it 4.5m 98, _ • -— 1 —.11-- -- . ' 1 i 1 --.---— 1 . - L I 5.0m . :,_, t —— I._ t i I , J _ 96 __. •-•• 1 — i- 1-- •RIGINAL CROON@ Ali E _ AT FACE OF NOME BARMER I it* ____ • ... .. _ ___ .______ ......: 1 t —._ t t -- I ----t- I I ----I.—I I -- .-___r_________,_ _ 5 I I I 3 i _ __ { 1 I _ _i_l - 1 _11 .__ _._ ____ ---,In 016. 1 I 10+000 11015BMBIKBSVALLPRGMLE 10+100 10+160 Vottiool 1 1 2esofY Holizontal - " . _ • • METRIC - HATE tfo • • CONT (:-. ) • . WP NOTE; BREAKPOINTS ON TOE CENTERIJNE ALIGNMENT OF NOISE NEW CONSTRUCTION SHEET BARRIER ARE APPROXIMATE. STA 10+160 TO SIR 101-300 03 SI.I■W 11.7.1 . i . . . . . . • ... 1 5.0m RETAINUI • • I NOISE BARRIER . • 5.0m NOISE BMRIER • 1 -0.6m OFFSET FROM BACK .f. 8 • . APPROX.CINTERLINE OF .t. OF SIDEWAIX TO FACE OF POST 6,+ BAO1 OF.DEWALH NOISE BARRIER o g • + + gl ''-'1 • . n ____ 7 T• . ----7-2-: .--1:1-----"---:- -----O'_'-.1T--'7 ''-'-----------'-''----• M , 7 --- m -- _ BOTTOM OF DITCH REFER TO SHEET 5 MID 6 FOR DETNLS ' • --...- 0 REGARDING AREA BETWEEN IOEWNX MOO NOISE BARRIER. `1. q, r - -__ -,____ Z U —I • fm . • (7) . , I I I • _ .._.+ --1 1— --I- I ________ 100 •••••• 0: . k I . I I I 1 1 . TOP IF 5m OISE,•RIER t j _ _ I . I I • -13 _ ______I XI■ - • -1. It I I 1 I I 1 08 1 __,__i 1.- 1.. ,1_1_ —1 98 I 121 i I —I —...---- ---r--- I - _ , I 1 . I - I- — 1 1 ---1 1---1 • , . , t . 94 — —--•••-- — • 1________ -- '..r.. l g 1 i r 1 1 1----L 1 -: • .•FATE-trtir - :.. OF 1DEVI _ —I --— 8ART j__ MEW -.....)3 • 1 1 I I ___ I h 1 . . • I 1. __ . 1 I t____I ._ 1----r 1, — - __ ____ • -----F ou.....1 . 10+300 001101 10+200 . 10+16D • • 1 NOISE BARRIER WAI I PROPIE . 2atri.s.? . • , . i 1 . • . • . Hokonlol - . . • • • METRIC NATE No CONT (: )1 • LIMIT OF CONTRACT : . WP STA. 10+882 NEW CONSTRUCTION SHEET I • LIMIT OF CONSTUCTION STA 10+300 TO STA 10+362 S.ng7 Rah. 04 STA. 10+382 50rn RETAINED NOISE BARRIER .'ER I 5.0m NOISE BARRIER .- 5 OISE .0ro N .. . <4 cl Mg..82.8r BACK OF SIDEWALK -0.6m OFFSET FROM BACK OF SIDEVANK TO FACE OF POST -... APPROX.CENTERUNE OF + r'T NOISE BARRIER --- ---- --- BREAKPOINTS ON THE CENTERLINE AUGNMENT OF NOISE >. --1.-- 7. 7'' ---. — -------- ----- - BARRIER ARE APPROXIMATE. ..".1 )1'.'">i _.------ .se 0 tl,'i n --- OPSO CIUM.41 BT.% 6 801TOM OF DITCH 1: •EFER TO SHEET 5 AND 6 FORD/pp REGARDING AREA BETWEEN$ID A.14,-; AND NOISE BARRIER. rn Z 0 . —4 It n ,----1 c..7., . -.._ . - - 0 $01-...... , 1T-T-T-1---1 __E._ 111 1 1 —1--T 11 1.-T 11_ . ......, __1 ....._. 0 . i 5.0m 10ISE WITMER I 7 510n1 RET4INED NCISE RAROER 1 5.4m NOISE -11 . • 'Lr...,1 72 I I —11-- BARRIER. __L__L_______z,-1 ToP CIF 5rn; T OISE BARRIER1 I 96 ---;---t__ ; i I I I I BAY 0.5m It ' _ 1 — i --, ........_ . ...... _____iL 96 I 1 I • ,r. I -- L_ __L.. .._ _ __ 1 . t — 1)m--- - - ---—54 F. ..C. 4 4.5rn ' — 1-- --- ------_ — _----1 1. , ' ••••••■ # 1 1 ORIG NAL GEtOUND AT_TCE OF NOISE BARRIER K OF sibtivAuc )‘./ i 82— 00 I -1 --------------.-__ • I - ; . i I 8 I I--- ---I-1— I 1_4_ — I I 90 • -- 0.5 0 I 10+300 10+385 ;Mica laseoll ' NOISE BARRIFR WAIL PRO F • Horizontal . : . r • • METRIC PUTS O CONT WP = E E E MISC. DETAILS SHEET BAT,STREET SIDE RESIDENTIAL SIDE • STA TO STA 05 E 1=_____—__=—__h STA �R. IIPNOPOGEDN06E BARRIER WALL PANES 7====_I ∎r_ PROPOSED NOISE BARRIER SDm HEIOM ------_-- -- WALL PANELS _"—_—_� _ �-- 6Am HEIGHT 1 181 PANEI.IS CONCRETE FOR 7,—r.,--- _Ii ) MAWTEHANCE PROTECTION 'I --__—_ ___ SODANO •TOPSOIL(EDNO Sgtl(OFSIOEWMIL Iiy ■ - II • ] _ =% OWGINAL GROUND D4Pn MS . IUEWAIA \ i BOTTOM OF DITCH -— • CROSS SECTION NOISE BARRIER PROFILE SECTION E E E > TYPICAL SECTION DETAIL KW,STREET MOE RESIDENTIAL SIDE ' STA 10.00-STA IDHpB '! PAIRNLSFD NOISE BAtW1ER 'Iy-----� ---- 2 STA 10.095-STA161S1 =�= �'—_�_—_ _�� STA10N6-STA WM. WALL PANELS rI — — — — --_. PROPOSED NOISE BAIWER L=—■■_—_■ --- WNLPANRS SD,D SEMITE I_t"1 —"_—t --. .• Z Ma I SOD II: 1ST PANEL O CONCRETE FOR YI.---_—_—-----_— QDII NEIOM TOPSOIL(SOm) MNNTENANOE PROTECTION I --------- �}y E E BACK OFBWEWNI( 'fl — --------�I `Fi . E S_ ORIGINAL GROUND '''fYt.T'i-:..�ti�%:;'y.;'.ti: DANK STREET ODE RESIDENTIAL SIDE _ PROPOSED NgSE BARRIER V-- ------=-pl EXISTING SIDEWALK.] BOTTOM OF ORCN 1' ___ __- 1........ WALL PANEL''I� —_---__===— ___...••• 'il_ --- --- '.� •—_— --- �.I FJOSTMO PEE �' II Q..-1"2"LT. OUTLET PROPOSED NOISE PANELS BA'''" S.0m HEIGHT ---�--- ' S.Om NE1BM �h 0 181 PANPLISCONCRETE FOR `( � �"— ����� I•' CROSS SECTION I SODAND �1NNTENANCEPROTECTION "I----_--------_—'. on I . N --�— ---- J I D 1 'TORSOS PDmm) II ----_�. PIPE CROSSING DETAIL BACK OFSIOEWAUI -,•'•( STA 10.215 PROFILE SECTION I�TZ. a.., ... 74 — Y ORIGINAL GROUND L' a+ "����F-r.;=~�x+;'.R . 1r � BOTTOM OF DITCH II • _ _�• _ -;I E%16TWOb1DEWNRJ I _ Ii- '�-:- _ _— E E E O. II GAYLY STREET SIDE RESIDENTIAL SIDE y5 RETNNINO WALL PANELS I• \ I ----_---_---_-1I. \l _ PROPOSED HDIBE BARRIER �I -- .JII 77 In IT W.LLIPANEl6 II_R..: --_-- YL. ILJII]_II RETNNINO WALLPANELB L i VC PROPOS®N06E BPRNER �I=— =-—. _. WALL PANELS SOn HEIGIO �_-- -----I 6An 11F1GIIT I t$f PANEL IS OONCPETE FOR -� — —����—� _I. • CROSS SECTION RETAINED NOISE BARRIER PROFILE SECTION TOP''OL SOO AND(Soon) I MAMIENANCE PROTECTION I --- ==-----�I TYPICAL SECTION DETAIL BAGC S 6NEWAN{ � `-c =I' STA.16161.STA.10.16 Ski !' OW HEAL GRO AN STA 16]6-''10.10.]11 EXSTING SIDEW.W(f —E� `_� BOTTOM OF DITCH III•$�, EXISTING PIPE INLET I' ^ — L O — 1 RUNNING WALL PANELS 'II Balm PIPE INLET TO 11' Il tl BE CORED CV ,r_. RETAINING WALL PA(IEIB I O • CROSS SECTION PIPE CROSSING WITHIN PROFILE SECTION • • g RETAINING WALL PANEL DETAIL' 510161ST g 8TA 10NS5 G . • • METRIC COT O • CON WP _ • MISC. DETAILS SHEET STA TO STA 08 s..a f f BAYI.Y STREET BIDE RESIDENTIAL SIDE • ! PROP0.4EO NOIRE BARRIER __�_ ___ III-- -------?TNT E R I W"LL PANELS _ —___- E{e PROPOSED NOISE AL PANES •I _ �—_��` �. WALL AIM •; C��= ���� BOO AIM SOB HEIGHT I -.7.-72 6AB HEIGHT TOPSOIL(R]nm) 1ST PANEL IS CONCRETE FOR 11r—_--L--=---- -- — i I I[ GRANULAR ANbR+) I I MIBt/IENANCEPROTI'LTON `I 7r — ____ —_—__ EXISTING SIOEWNX f \J V ORIGINAL GROUND BACK OF MENINX • 1 T� ASPHALT BACKSLOPE It BOTTOM OF ORCH '�- ' —. TO BE REMOVED II \� ---- RETAINING WALL PANELS �pIN —BOTTOM OF DITCH - RETAINING WALL PANELSi ` ii II a• f PROFILE SECTION m CROSS SECTION REMOVED ASPHALT BACKSLOPE DETAIL �L.{. . L STA-IOMEB•STA-10809 H....... O 1 ..._ f f • BAYLY STREET ROE RESIDENTIAL BIDE 1 WALL PANEIb I���� —I m PROPOSED NOISE BARRIER II_ ==7=-7====_ WALL PANELS ' __ __I I. SOD t 6Am HEIGHT III � �� � • 050 NEIGIfT 0■ TOPSOIL AND 1ST PANEL IS CONCRETE FOR :--r...—::—=•7=T-:=-1-------7..1—�--- 1 V MAWTENANCEPROTEClION � � ���� GRANULAR hI ���.. ..'I EXISTING SIDEWALK _ fR� = rl ORIGINAL GROOM BACK OF SIDEWALK ro S EXISTING RETAINING WAIL E. I j—--— BOTTOMOFORCN ,. _ ••I. RETAINNSWALL PAWLS III N...m.r.OP DITCH y RETAINING WALL PANElBi j s In II Ii II ' PROFILE SECTION CROSS SECTION - EXISTING RETAINING WALL DETAIL STA 10.015-STA 10.06E 5 1 . B _______________ •ATTACHMENT# TOREPORT#, ENG 14-13 of. �v Memorandum �`�=-� Ontario To: Darrell Selsky Date: August 12,2013 Manager,Capital Projects&Infrastructure Engineering&Public Works Department One The Esplanade, Pickering,ON L1V 6K7 RECEIVED From: Heather Nottbeck AUG � 2V3 Planning&Design,Toronto/Durham O • 1201 Transportatio CITY 4th tFl n Bldg D ,,�y�RING SEt ICES Downsview,ON M3M 1J8 Tel(416)235-4900 Fax(416)235-3576 Re: Bayly Street Noise Barrier Wall:MTO-Pickering Legal Agreement Darrell, Enclosed is the Legal Agreement between the City of Pickering and the Ministry of Transportation for the Bayly Street Noise Barrier Wall Project. As requested, changes have been made to the document to assign any warranties to the City and to add the City and the Region as parties to be indemnified. Please return the signed Agreement to me as soon as time allows. Thanks, 114144 . Heather Nottbeck, P.Eng Planning&Design,Toronto/Durham Ministry of Transportation 1201 Wilson Ave,4th Fl.,Bldg D Downsview,ON M3M 1J8 (416)235-4900 ATTACHMENT# — TO REPORT# E.1 -I) Z of.� THIS AGREEMENT is made day of ,2013. BETWEEN: • HER MAJESTY THE QUEEN IN RIGHT OF THE PROVINCE OF ONTARIO,AS REPRESENTED BY THE MINISTER OF TRANSPORTATION FOR THE PROVINCE OF ONTARIO (hereinafter referred to as the"Ministry") OF THE FIRST PART -and- THE CORPORATON OF THE CITY OF PICKERING (hereinafter referred to as the"City") OF THE SECOND PART WHEREAS (1) The City has requested the Ministry to design and construct a noise attenuation barrier along a portion of Durham Regional Road 22(as known as Bayly Street) in an effort to reduce the noise resulting from traffic on the King's Highway 401 as more particularly shown on Schedule "A" attached to this Agreement ("the Bayly Street Noise Wall Barrier"). (2) The City has advised that the Regional Municipality of Durham ("Region"),having the jurisdiction over Durham Regional Road 22, has agreed to grant the City an encroachment in order to allow the construction of the Bayly Street Noise Wall Barrier upon terms and conditions set out in the Region encroachment permit. (3) The City has agreed to be fully responsible for and to maintain the Bayly Street Noise Wall Barrier upon its construction completion. (4) The City has agreed to contribute to the costs of the design and construction of the Bayly Street Noise Wall Barrier. (5) The Ministry recognizes the benefits of constructing the Bayly Street Noise Wall Barrier on the Regional right-of-way on Bayly Street and desires to assist the City in this regard upon the terms and conditions agreed upon in this Agreement. ATTACHMENT# ° TOREPORT# ENC )t -/3 3 of (P Page 2 NOW THEREFORE THIS AGREEMENT WITNESSES that in consideration of the premises and other good valuable consideration,the receipt and sufficiency of which are hereby acknowledged,the parties agree as follows: 1. The Ministry or its consultants,contractors or agents will undertake the work necessary to design and construct the Bayly Street Noise Wall Barrier. 2. More particularly, the Ministry agrees to undertake all surveying, engineering investigations, environmental studies, engineering design and other duties that are normally associated with the design of a project of this type. 3. The City agrees to facilitate and obtain all permits required by the Region to perform the work necessary to design and construct the Bayly Street Noise Wall Barrier. 4. While the Ministry is responsible for providing overall directions for the work to design and construct the Bayly Street Noise Wall Barrier, it is understood by the parties and agreed that the City will also be involved in some aspects of work for the Bayly Street Noise Wall Barrier, although the amount of involvement from the Ci ty may vary depending upon the circumstances and the Ministry's discretion. Toward that end, the City and the Ministry agree to meet on an as required basis to discuss the work to design and construct the Bayly Street Noise Wall Barrier. 5. The Ministry will be responsible for all costs to undertake the work necessary to design and construct the Bayly Street Noise Wall Barrier,subject to such contributions from the City as described in this Agreement. 6. The City agrees to contribute $100,000.00 toward the overall cost of the Bayly Street Noise Wall Barrier. The City will pay this amount to the Ministry once the Bayly Street Noise Wall Barrier construction is complete and upon being invoiced by the Ministry for the said monies. Payment shall be made to the Ministry within 30 days of the receipt of the invoice by the City. 7. The Ministry will be responsible for the construction administration associated with the construction contract and other duties associated with the supervision and administration of a construction project of this type. At the discretion of the Ministry,the Ministry may retain the services of a consultant to perform such duties. 8. The Ministry advises and the City accepts that the Ministry's construction contract will include provisions that the contractor retained by the Ministry will be fully responsible for traffic control and safety during the construction of the Bayly Street Noise Wall Barrier. 2 ATTACHMENT# _ TO REPORT# EN(, of 4 Page 3 9. The Ministry advises and the City accepts that the Ministry's construction contract will include provisions for resolving any and all construction liens filed with respect to the Bayly Street Noise Wall Barrier. 10. The Ministry advises and the City accepts that the Ministry's construction contract will provide that the Ministry's contractor shall be required to indemnify and save harmless the Ministry,the City and the Region from and against any claim,action,cause of action or liability from loss, damage, accident or injury in any manner arising due to, out of, from or in connection with the work to construct the Bayly Street Noise Wall Barrier undertaken and performed by the contractor under this Agreement, except for work negligently performed by the Ministry. 11. The Ministry advises and the City accepts that the Ministry's construction contract will • require that the Ministry's contractor will be required to maintain comprehensive commercial general liability insurance, protecting indemnifying the Ministry, the City and the Region from and against all claims for damage or injury to persons, including • loss of life to persons,occurring during the work to design and construct the Bayly Street Noise Wall Barrier. 12. The Ministry advises and the City accepts that the Ministry's construction contract will require the contractor to provide a warranty of all construction works for a period of one year following the date of acceptance of contract completion and subject to sign off by the Ministry and City. The Ministry agrees to provide and the City agrees to accept that the Ministry may assign to the City, in the Ministry's construction contract with the contractor, the one year warranty for the construction of the Bayly Street Noise Wall Barrier works provided by the Contractor along with any contractual rights to enforce this warranty. 13. When the Ministry is satisfied that the Bayly Street Noise Wall Barrier has been completed in accordance with this Agreement,the Ministry shall notify the City and the Region shall have the Bayly Street Noise Wall Barrier inspected. If the City finds that the Bayly Street Noise Wall Barrier has been completed to its satisfaction and this Agreement,the City shall give the Ministry a written notice that the Bayly Street Noise Wall Barrier has been completed. 14. While the Ministry will take normal precautions and construct according to the normal practice of the Ministry of Transportation,no warranties are expressed or implied by this Agreement as to the Bayly Street Noise Wall Barrier, except those warranties provided by the Contractor as mentioned herein. 15. It is understood and agreed by the parties that upon completion of the construction of the Bayly Street Noise Wall Barrier,the Region will maintain ownership of Bayly Street and 3 ATTACHMENT# TOREPORT# EN& X1-13 5 of 4 Page 4 the City will have responsibility for the maintenance of the Bayly Street Noise Wall Barrier. 16. Upon completion of the Bayly Street Noise Wall Barrier and subsequent notice of its completion; the City acknowledges that pursuant to section 33(1) of the Public Transportation and Highway Improvement Act,the Bayly Street Noise Wall Barrier is a municipal undertaking and the Ministry is not liable for any repair and maintenance of the Bayly Street Noise Wall Barrier. 17. Any changes, alterations or amendments hereto, other than as herein specifically authorized shall be made in writing signed by the City's authorized signing officers and by the Ministry's Regional Director,Central Region or his nominee. 18. The City warrants that they have taken all necessary steps,done all acts,passed all by- laws and obtained all approvals within their powers required to give them the authority to enter into this agreement. 19. This Agreement shall be governed by the laws of the Province of Ontario and the laws of Canada applicable thereto. IN WITNESS WHEREOF the Minister, on behalf of the Party of the First Part,has hereunto set his hand,and the Party of the Second Part has hereunto affixed its Corporate Seal under the hands of its proper officers duly authorized in that behalf. SIGNED AND SEALED this day of ,2013. MINISTER OF TRANSPORTATION FOR THE PROVINCE OF ONTARIO SIGNED AND SEALED this day of ,2013. THE CORPORATION OF THE CITY OF PICKERING • 4 ATTACHMENT#1_ IOREPORT# ENG !4'13 L of SCHEDULE`A' to an Agreement between the Ministry of Transportation and The Corporation of the City of Pickering N �'`�� -mil_ -; < +" J-:7--/--'-"-----' -----1"------....„-- ___.A. ,__- •7 ,-Z.7 - ''7.,bf".6>" 61-7 . \.-\\\-(1- - ,40:1-7 0- 4, . - /� / NOISE BARRIER''••., .%/.." / -WALL LIMITS '`, • / 380m J r Bayly Street Noise Barrier Wail South of Highway 401 East of Whites Road 5 ATTACHMENT# 3_ MREPORT# EN6 )14-13 ) of Z C-ifq oo Council Meeting Minutes NCI+/O N X01 Monday, December 20, 2004 7:30 PM Resolution #173/04 Moved by Councillor Brenner Seconded by Councillor Ashe WHEREAS the residents on Marinet Crescent and Eyer Drive, backing onto Bayly Street, between Whites Road and West Shore Boulevard, have expressed concern respecting the impact of noise from Highway #401, the CNR line, and VIA train activity, and Bayly Street, on their living environment; and WHEREAS the homes in this area of the City were constructed in the 1960's and 1970's, prior to the construction of Bayly Street between Whites Road and West Shore Boulevard; and WHEREAS residents have continually expressed concern over the increase in noise levels that have occurred over the years as each of the noise sources was established and/or increased in intensity; and WHEREAS at a meeting held on December 6, 2004, the Region of Durham and the • Ministry of Transportation staff advised that it is reasonable to consider this area of the City for retrofit measures to address noise concerns through attenuation fencing, based on the principle of cost sharing by all parties; and WHEREAS the City of Pickering acknowledges the significance of area resident concerns respecting noise levels in this area of the City and the impact of noise on the residential living environment; and WHEREAS Bayly,Street is under the jurisdiction of the Region of Durham which has expertise and experience in addressing retrofit solutions to noise attenuation matters; NOW THEREFORE BE IT RESOLVED THAT the City of Pickering requests the Regional Municipality of Durham to coordinate a review of potential noise attenuation measures and implementation strategies to address resident concerns in the area of Bayly Street between West Shore Boulevard and Whites. Road, and that such investigation include staff from the Ministry of Transportation, the CNR, GO Transit, Region of Durham, City of Pickering and area residents; and • FURTHER THAT the Region of Durham advise the City of Pickering of the work program that it intends to undertake to address this matter; and FURTHER THAT a copy of this resolution be forwarded to: - 8 - ATTACHMENT#__,3 sO REPORT# C1\1G+ 4-i3 of .2, C-ifq o. Council Meeting Minutes 'Lit�ft.�,� i'wi'. ■ Monday, December 20, 2004 7:30 PM o Minister of Transportation, the Honourable Harinder S. Takhar o Development Review Coordinator, CN Railway Properties, Mr. G. Woods o Managing Director&CEO, GO Transit; Mr. G. McNeal o Region of Durham Commissioner of Works, Mr. C. Curtis P.Eng., MBA o Regional Council o Mark Holland, MP, Ajax-Pickering o Hon. Dan McTeague, P.C., MP Pickering-Scarborough East CARRIED Resolution #174/04 Moved by Councillor Brenner Seconded by Councillor McLean That Pickering Council directs the Director, Planning & Development to consider, as part of the zoning strategy for Central Pickering, the use of holding provisions in zoning by-laws for lands where studies are required related to the protection of First Nations' site features and resources. • CARRIED (V) BY-LAWS That Councillor Dickerson, seconded by Councillor Brenner, took leave to introduce by- laws of the City of Pickering: By-law Number 6413/04 Being a by-law to amend Restricted Area Zoning By-law 3037, to implement the Official Plan of the City of Pickering, Region of Durham, north Part of Lot 14, Concession 9, City of Pickering. (A 03/04) By-law Number 6414/04 Being a by-law to authorize the release and removal of the Subdivision Agreement and related amending agreement respecting Plan 40M-1602, Pickering, from title. - 9- ATTACHMENT#_ _ TO REPORT# ENG "+-13 _Lot Czry a0 Council Meeting Minutes Tuesday, February 22, 2011 NON-Ciatil t 7:30 PM Council Chambers Special In Camera Council Minutes, January 31, 2011 Special Council Minutes, January 31, 2011 Special In Camera Council Minutes, February 7, 2011 Special Council Minutes, February 7, 2011 Planning & Development Committee Minutes, February 7, 2011 Executive Committee Minutes, February 14, 2011 • Carried Resolution#20/11 Moved by Councillor O'Connell Seconded by Councillor Dickerson • That the rules of procedure be suspended in order to change the order of business to allow the introduction of the Notice of Motion with respect to noise concerns on Marinet Crescent to be dealt with before the delegations. • Carried on a • 2/3 Majority Vote Noise Concerns on Marinet Crescent Councillor O'Connell provided the Chair with an amended notice of motion to introduce to Council. Councillor O'Connell noted that the changes had been suggested by staff in order to follow the proper processes for the 2011 Budget. A question and answer period ensued. Resolution #21/11 Moved by Councillor O'Connell Seconded by Councillor McLean WHEREAS the residents of Marinet Crescent have been requesting appropriate measures to address noise which is a result of the widening of Bayly Street by Durham Region, widening of Highway 401 by the Province of Ontario and vibrations associated with the Via/GO line all running parallel to the rear of their properties; and WHEREAS testing has been carried out and has confirmed the level of noise is in excess of acceptable standards; and WHEREAS in 2006 a tri-party agreement was to have taken place between Durham Region, Province of Ontario and the City of Pickering to each pay a portion of the total 2 • ATTACH MENT4_11 TO REPORT#tN G la-I 3 2. or 2i Cali 00 _ Council.Meeting Minutes Tuesday, February 22, 2011 Council Chambers costs to construct.a noise attenuation wall along the rear lots of all homes on Marinet that abut Bayly; and • WHEREAS to date no action has been taken to commence the construction of the ' Marinet noise attenuation wall; NOW THEREFORE BE IT RESOLVED the City of Pickering advise the Province of • Ontario of our intention to include the City's share of funding ($100,000) for the construction of this project in our 2011 Budget; AND FURTHER the City of Pickering request the Region of Durham to assume 14 responsibility for the maintenance costs for this noise attenuation wall; • AND THAT staff report back to Council no later than the April meeting of Council with the timelines for commencing and completion of this project. Carried Unanimously On a Recorded Vote (IV) Delegations • Resolution #22/11 • Moved by Councillor O'Connell • Seconded by Councillor McLean That the rules of procedure be suspended in order to allow for the additional • delegations of Don Harvey, Michael Fearon, Steve Murray and Bruce Smith. Motion Lost on a Recorded • Vote as Follows: Yes No Councillor McLean Councillor Ashe Councillor O'Connell Councillor Dickerson • Councillor Rodrigues Councillor Pickles Mayor Ryan 1. Durham Regional Police Update on Community Safety Deputy Chief Sherry Whiteway appeared before Council relaying Chief Eweles regrets as he was unable to attend. She provided an overview of their.completed 2011-2013 • 3• • eSCRIBE eSCRIBE ■Workflow.Status: eSCRIBE Approval Workflow .YE ETIa G3,EVOt VtD Workflow Information Initiator: Stoddart,Katherine Document: ENG 14-13 Noise Attenuation Wall-Bayly Street Started: 10/22/2013 11:50 AM Status: Approved Last run: 10/22/2013 12:01 PM Tasks ......:.... .......... The following tasks have been assigned to the participants in this workflow.Click a task to edit it.You can also view these tasks in the list Tasks. r Assigned To Title Due Date Status Related Content Outcome Shields,Debbie ENG 14-13 Noise Attenuation Wall-Bayly Street.docx Review tin,, 10/22/2013 Completed ENG 14-13 Noise Attenuation Wall-Bayly Street Approved Workflow History ,.._........... .,__ The following events have occurred in this workflow. RI Date Occurred Event Type _User ID Description Outcome 10/22/2013 11:50 AM Workflow Initiated Stoddart,Katherine eScribe Approval Started 10/22/2013 11:50 AM Task Created - Shields,Debbie Approval Task Assigned 10/22/2013 12:01 PM Task Completed Shields,Debbie Document Approved 10/22/2013 12:01 PM Workflow Completed System Account Document was Approved