HomeMy WebLinkAboutENG 13-13 City 4 A Report to Executive Committee PICK V Report Number: ENG 13-13 Date: October 7, 2013 From: Richard W. Holborn Director, Engineering & Public Works Subject: Tender for Removal and Replacement of a Pedestrian Bridge in Kinsmen Park - Tender No. T-22-2013 - File: A-1440 Recommendation: 1. That Report ENG 13-13 of the Director, Engineering & Public Works regarding Tender No. T-22-2013 for the Removal and Replacement of a Pedestrian Bridge in Kinsmen Park be received; 2. That Tender No. T-22-2013 as submitted by McPherson-Andrews Contracting Limited in the total tendered amount of $65,490.28 (HST included) be accepted; 3. That the total gross project cost of$76,246.00 (HST included), including the tender amount and other associated costs and the total net project cost of $68,662.00 (net of HST rebate) be approved; 4. That Council authorize the Division Head, Finance & Treasurer to fund the project as follows: a. The sum of $46,000.00 as approved in the 2013 Parks Capital Budget from property taxes; b. The additional sum of $22,662.00 from property taxes through savings in the Beechlawn Park Walkway and Lighting project; and 5. That the appropriate City of Pickering officials be authorized to take necessary action to give effect thereto. Executive Summary: As part of the 2013 Parks Capital Budget, the replacement of the pedestrian bridge in Kinsmen Park was approved as a construction project. Tender No. T-22-2013 was issued on August 2, 2013 and closed on Monday, August 19, 2013 with five bidders responding. The low bid submitted by McPherson-Andrews Contracting Limited is recommended for approval. The total gross project cost is estimated at $76,246.00 (HST included) and the total net project cost is estimated at $68,662.00 (net of HST rebate). 120 Report ENG 13-13 October 7, 2013 Subject: Tender for Removal and Replacement of a Pedestrian Bridge in Kinsmen Park Tender No. T-22-2013 Page 2 Financial Implications: 1. Tender Amount Tender No. T-22-2013 $57,956.00 HST (13%) 7,534.28 Total Gross Tender Cost _ $65,490.28 2. Estimated Project Costing Summary Tender No. T-22-2013 for Removal and Replacement of a $57,956.00 Pedestrian Bridge in Kinsmen Park Associated Costs TRCA permit fee 2,500.00 Construction Contingency 6,000.00 Other Associated costs 1,018.00 Total $67,474.00 HST (13%) 8,772.00 Total Gross Project Cost $76,246.00 HST Rebate (11.24%) (7,584.00) Total Net Project Cost $68,662.00 3. Approved Source of Funds 2013 Parks Ca•ital Bud•et 5780.1331.6181 Funding Source Available Budget Required Property Tax $46,000.00 $68,662.00 Total Funds $46,000.00 $68,662.00 Net Project Costs under (over) Approved Funds" ($22,662.00) A number of the other 2013 Parks Capital projects including Beechlawn Park Walkway and Lighting were completed significantly under budget. As such, staff recommends that the additional $22,662.00 required for the Removal and Replacement of a Pedestrian Bridge in Kinsmen Park be funded from these savings. In accordance with Section 11 of the City's Financial Control Policy, the Chief Administrative Officer, Department Head and Treasurer may jointly approve changes to authorized expenditure amounts provided that the total amount of the over expenditure does not exceed the lesser of 10% of the approved capital expenditure or $100,000. Council approval is required for the Removal and Replacement of a Pedestrian Bridge in Kinsmen Park as the over expenditure exceeds 10%. 121 Report ENG 13-13 October 7, 2013 Subject: Tender for Removal and Replacement of a Pedestrian Bridge in Kinsmen Park Tender No. T-22-2013 Page 3 Discussion: As part of the 2013 Parks Capital Budget, the replacement of the pedestrian bridge in Kinsmen Park was approved as a construction project. The project includes the removal of the existing bridge, installation of helical pier and concrete grade beam foundations and the installation of a new pre-engineered steel bridge. The south bank of the stream is vertical and has been eroding over time. As part of this project, armourstone will be installed along the stream bank to stabilize the bank and protect the foundations on the south side of the bridge. This work was not anticipated in the original budget estimates and has resulted in a higher project cost. Tender No. T-22-2013 was issued on August 2, 2013, advertised on the City's website and closed on August 19, 2013 with five bids received. The low bid submitted by McPherson- Andrews Contracting Limited of$57,956 plus HST is recommended for approval. References for McPherson-Andrews Contracting Limited have been reviewed and deemed acceptable by Senior Coordinator, Landscape & Parks Development. The Health & Safety Policy, WSIB Injury Summary Report, and WSIB Clearance Certificate as submitted by McPherson-Andrews Contracting Limited have been reviewed by the Coordinator, Health & Safety and are deemed acceptable. The Certificate of Insurance has been reviewed by the (Acting) Manager, Budgets & Internal Audit and is deemed acceptable. In conjuction with staffs review, the tender is deemed acceptable. The additional funds required for this project will be offset by savings that were realized from the Beechlawn Park Walkway and Lighting project. Approximately $59,000 of the budgeted $95,000 has been committed for this project, leaving a balance of approximately $36,000. This project was funded from property taxes. Upon careful examination of all the tenders and relevant documents received, the Engineering & Public Works Department recommends the acceptance of the low bid submitted by McPherson-Andrews Contracting Limited for Tender No. T-22-2013 in the amount of$65,490.28 (HST included) and that the total net project cost of$68,662.00 (net of HST rebate) be approved. Attachments: 1. Memorandum from Supply & Services dated August 19, 2013 2. Location Map 122 Report ENG 13-13 October 7, 2013 Subject: Tender for Removal and Replacement of a Pedestrian Bridge in Kinsmen Park Tender No. T-22-2013 Page 4 Prepared By: Approved/Endorsed By: )4 • -.? , _, A, )(mold Mostert, GALA Rich:rd HoI./.rn, P. Eng. Senior Coordinator Dire tor, Engineering & Public Works Landscape & Parks Development (---1 - /\,/.7/,/if' . ()—b-/4,' -;%> ------ ------,... .. Darrell Selsky, C`ET, CMM III! / Stan KanNowski, CMA,TNIBA Manager Division Head Capit.I Projects & Infrastructure Finance & Treasurer 6 Vera A. Felgemacher CSCMP, CPPO, CPPB, CPM, CMM III Manager, Supply & Services AM:am Recommended for the consideration of Pickering Ci Council 4 / J .' & 2313 Tony Prevedel, P.Eng. Chief Administrative Officer 123 -OREPORT# ENG, City 4 .f. 1 3 _ City of Pickering Engineering&Publ is Works _�� trail. AUG 20 2013 PICKERI � , Memo Received To: Richard Holborn August 19, 2013 Director, Engineering & Public Works From: Vera A. Felgemacher Manager, Supply & Services Copy: Manager, Capital Works & Infrastructure Subject: Tender No. T-22-2013 Tender for Removal and Replacement of a Pedestrian Bridge in Kinsmen Park - File: F-5400-001 Tenders have been received for the above project. An advertisement was placed in the Daily Commercial News and on the City's website inviting companies to download the tendering documents and drawings for the above mentioned tender. One addendum was issued. Five bidders submitted a tender for this project. A copy of the Record of Tenders Opened and Checked used at the public tender opening is attached. Tenders shall be irrevocable for 60 days after the official closing date and time. Purchasing Procedure No. PUR 010-001, Item 13.03 (r) provides checking tendered unit prices and extensions unit prices shall govern and extensions will be corrected accordingly, which has been done. All deposits other than the low three bidders may be returned to the applicable bidders as provided for by Purchasing Procedure No. PUR 010-001, Item 13.03(w). Three (3) bids have been retained for review at this time. • Copies of the tenders are attached for your review along with the summary of costs. SUMMARY Harmonized Sales Tax Included Bidder Total Tendered Price After Calculation Check McPherson-Andrews Contracting Ltd. $65,490.28 $65,490.28 Montgomery MacEwen Contracting $102,515.13 $102,515.13 Limited Dig-Con International Limited $121,972.20 $121,972.20 Bob Hendricksen Construction Limited $189,747.34 $189,747.34 - Automatic rejection— Bid deposit not provided and Addendum No. 1 not acknowledged. Reference: Serve Construction Ltd. Purchasing Policy No. PUR 010, Procedure No. 23.02, Item 10(c) and Item 11, IB Item 9, 11, 13, 23, 25, 26, 27, 39, 40 and 41; TS Item 1, 2, and 3, and Addendum No. 1. 124 ATTACH NEN"trr�_.1.... 1' NtPORT',+ NG, i�1� 2 -or 3 Pursuant to Information to Bidders Item 28, the following will be requested of the low bidder for your review during the evaluation stage of this tender call. Please advise when you wish us to proceed with this task. (a) A copy of the Health and Safety Policy to be used on this project; (b) A copy of the current Workplace Injury Summary Report issued by Workplace Safety & Insurance Board (in lieu of the Workplace Injury Summary Report document, a copy of the current CAD 7, NEER, or MAP reports may be submitted); (c) A copy of the current Clearance Certificate issued by Workplace Safety & Insurance Board; (d) The City's certificate of insurance or approved alternative form shall be completed by the bidder's agent, broker or insurer; (e) The City's Accessibility Regulations for Contracted Services form currently dated and signed; (f) list of Sub-Contractors in accordance with General Conditions Item 35; and (g) Waste Management Plan to be used on this project in accordance with Tendering Specifications Item 18. In accordance with Purchasing Policy Item 06.12 where the compliant quotation or tender meeting specifications and offering best value to the City is acceptable and the total purchase price is over $30,000 and up to $75,000, the Manager may approve the award, subject to consultation with the appropriate Director and confirmation of finance by the Treasurer. An approved "on-line" requisition will be required to proceed. Please do not disclose any information to enquiries except you can direct them to the City's website for the unofficial bid results as read out at the public tender opening. Bidders will be advised of the outcome in due course. If y u require further information, please feel free to contact me or a member of Supply & Se ices. VAF/jg Attachments August 19, 2013 Tender No. T-22-2013 Page 2 1 242emoval and Replacement of a Pedestrian Bridge in Kinsmen Park 9ZI. z w O U 0 C 1 0 • U ti C U a) ca C Q aci 1n in m C tn N a O ca o :o -a C d C3 C _ d O 0 Q U O> Ui a N m E a) m -a m ~ .v N7 v3 Ep o L l • �t) U 4) a a 1 co t U d -Op ``'- 1 \ 4.::?. CD o N C N ` c jj ,.O F-Q Ti, a U H CO m m I- Q D Q L. 'B a) c O -0 O -0 ° ) x•cl ,if, \� � q Q' m a) a ■ v\ CI L c " q O p \ , CO ~ N a E C N E I_ ci. c o .\1 a> U 7 -6 , CD c n J RO ((f y J �11 Z O c p N N O 1173 E 7-5 a cy CO 0 16 Y a) Q� , m m �� c C rn w a 1 a 0 c o _ • D a -_U c V U c a'o ( 'E a a c a) . b, U [i J Q U (A 0 7 r City odl ^°, i. „�f.S' :,^ic' 0 c+'.,...2 fo REFORM YY EN(n r3-'12, "af. � I l f _ 1 fig 1 P I- till Engineering & Public Works Department Attachment for Tender T-22-2013 Removal and Replacement of a Pedestrian Bridge in Kinsmen Park A ILL•WSIDE COLMAR CO RT O i Q z i 0 O Z Z ,` o PARKHAM Q O . i i ft 1 CRESCENT 7_': FELDSPAR PARKETTE , O . COURT m aLaERwooa O• O /// O U • O �Q O AIL A ALEX Q w 1r _ m ROBERTSON % SUBJECT PARK PARK } 0 z Q 0 MONTGOMERY PARK - ROAD Location Map — Kinsmen Park Proposed Construction Includes: The proposed works are to include the removal of the existing bridge, installation of helical pier and concrete grade beam foundations, installation of a pre-engineered steel bridge and stream bank stabilization, 127