HomeMy WebLinkAboutENG 05-13From: Richard W. Holborn
Director, Engineering & Public Works
Subject: Tender for Asphalt and Concrete Repairs
- Tender No. T -9 -2013
- File: A -1440
Recommendation:
Report to
Council
Report Number: ENG 05 -13
Date: April 22, 2013
That Report ENG 05 -13 of the Director, Engineering & Public Works regarding
Tender T -9 -2013 for Asphalt and Concrete Repairs be received;
2. That Tender No. T -9 -2013 as submitted by Ore Construction Ltd. for Asphalt and
Concrete Repairs in the total tendered amount of $337,475.17 (HST included) be
accepted;
3. That the total gross project cost of $371,456.00 (HST included), including the
tender amount and other associated costs and the total net project cost of
$334,508.00 be approved;
4. That Council authorize the (Acting) Division Head, Finance & Treasurer to finance
the project as follows:
a) that the sum of $50,800.00, as provided for in the 2013 approved Current and
Capital Budgets, be funded from property taxes;
b) that the sum of $124,149.00, as provided for in the 2013 approved Current
Budget for Sidewalks — Sidewalk Rehabilitation Program, be funded from
Federal- Gas Tax grant;
c) that the sum of $64,987.00, as provided for in the 2013 approved Capital
Budget for Parks, be funded by a transfer from the Rate Stabilization Reserve;
d) that the sum of $10,569.00, as provided for in the Current Budget for
Development Control - Road Maintenance Asphalt & Concrete Works, be
funded from other revenues collected from fees and charges required and
related to building permits and cash -in -lieu;
e) that the sum of $84,003.00 for the Transit Bus Pads be funded by a recovery
from Durham Region Transit; and
Report ENG 05 -13 April 22, 2013
Subject: Tender for Asphalt and Concrete Repairs
Tender No T -9 -2013 Page 2
5. That the appropriate City of Pickering officials be authorized to take necessary
action to give effect hereto.
Executive Summary: As part of the 2013 Current Budget and Capital Budget,
various municipal maintenance and construction projects were approved that require
the supply and installation of concrete and asphalt products. Tender No. T -9 -2013 was
issued on Thursday, March 14, 2013 and closed on Wednesday, April 3, 2013 with
seven bidders responding. The low bid submitted by Ore Construction Ltd. is
recommended for approval. The total gross project cost is estimated to be $371,456.00
and an estimated net cost of $334,508.00 (net of HST -rebate).
Financial Implications:
1.Tender Amount
T -9 -2013 $298,650.59
HST (13 %) 38,824.58
Total $337,475.17
2. Estimated Project Costing Summary
T -9 -2013 — Tender for Asphalt & Concrete Repairs
City of Pickering Portion
$216,101
Durham Region Transit Portion — Bus Pads
82,550
298,651
Associated Costs
Materials Testing
8,000
Miscellaneous Costs
1,500
Construction Contingency
20,571
Total
$328,722
HST (13 %)
42,734
Total Gross Project Cost
$371,456
HST Rebate (11.24 %)
(36,948)
Total Net Project Cost
Report ENG 05 -13
Subject: Tender for Asphalt and Concrete Repairs
Tender No T -9 -2013
3. Source of Funds
Capital and Current Budqets
April 22, 2013
Page 3
Description
Project Code
Funding Source
Available
Required
Budget
Budget
Operations - Roads
Asphalt and Concrete
2320.2408.0002
Property Taxes
$40,000
$33,312
Repair Program
Operations - Roads
Storm Sewer Repairs
2320.2408.0002
Property Taxes
10,000
6,157
(Partial)
Operations - Sidewalks
Sidewalk Rehabilitation
2323.5981.0000
Federal Gas Tax
200,000
124,149
Program
Grant
Subtotal
$250,000
$163,618
Operations - Parks
Rouge Valley Park
5780.1313.0000
Rate Stabilization
$90,000
$64,987
Pathway
Reserve
Operations - Parks
Beechlawn Park
5780.1329.0000
Property Taxes
15,000
11,331
Walkway (partial)
Subtotal
$105,000
$76,300
Planning & Development
Development Control
Road Maintenance
2613.2407.0000
Other Revenue
$25,000
$10,569
(fees & charges)
Subtotal
$25,000
$10,569
Third Party Recoverable
Durham Transit
Transit Bus Pads
3290.0001
Region of
$84,003
$84,003
Durham
Subtotal
$84,003
$84,003
TOTAL
$464,003
$334,508
Net Project Costs (over) under Approved Funds $129,495
The total tender amount includes a provisional rate of $100 per square metre for any
unanticipated asphalt grind and overlay work that may arise during the contract. Any
extra work deemed necessary may be accommodated within the total approved budget
amount available.
Report ENG 05 -13 April 22 -, 2013
Subject: Tender for Asphalt and Concrete Repairs
Tender No T -9 -2013 Page 4
Discussion: Annual maintenance programs requiring the supply of materials and
labour for the repair of roads, curbs and sidewalks are included in the tender for asphalt
and concrete repairs. Similar to last year's program, various concrete and asphalt
projects were combined into one tender in an effort to achieve cost efficiencies.
Projects included in this tender are walkways for Rouge Valley Park and Beechlawn
Park.
This tender also includes a third party component for the construction of concrete transit
bus pads on municipal boulevards, which is fully recoverable from Durham Region
Transit.
Tender No. T -9 -2013 was issued on Thursday, March 14, 2013 and closed on
Wednesday, April 3, 2013 with seven bidders submitting a bid. The low bid was
submitted by Ore Construction Ltd. Ore Construction Ltd. has previously worked for the
City on Tender T -24 -2012 Asphalt and Concrete Repairs and are deemed acceptable
by the Manager, Capital Projects & Infrastructure. The Health & Safety Policy, current
WSIB, Council Amendment to Draft #7 (CAD -7), Certificate of Clearance issued by
Workplace Safety & Insurance Board, proof of compliance with Confined Space Entry
Regulations, copies of certified training and procedures, list of employees trained in
confined space entry procedures as submitted by Ore Construction Ltd., have been
reviewed by the Coordinator, Health & Safety and are deemed acceptable. The
Certificate of Insurance has been reviewed by the (Acting) Division Head, Finance &
Treasurer and is deemed acceptable. In conjunction with staffs review of the
contractor's previous work experience and the bonding available on this project, the
tender is deemed acceptable.
Upon careful examination of all tenders and relevant documents received, the
Engineering & Public Works Department, and Durham Region Transit recommends the
acceptance of the low bid submitted by Ore Construction Ltd. for Tender No. T -9 -2013
in the amount of $337,475.17 (HST included) and that the total net project cost of
$334,508.00 be approved.
Attachments:
1. Supply & Services Memorandum dated Wednesday, April 3, 2013
2. Email dated August 28, 2012 from Durham Region
3. Location Maps
Report ENG 05 -13
Subject: Tender for Asphalt and Concrete Repairs
Tender No T -9 -2013
Prepared By:
Approved /Endorsed By:
VDrell S CET, C III Ric�rd W
Manager, Capital Projects & Inf structure Di r/ tor, E
Vera A. F�Igemacher
CSCMP, CPPO, CPPB, C.P.M., CMM 111
Manager, Supply & Services
Caryn Kong, CGA
Senior Financial Analyst
Capital & Debt Management
DS:ds
April 22, 2013
Page 5
61born, P. Eng.
neering & Public Works
Stan Karwowski
(Acting Division Head, Finance & Treasurer
Recommended for the consideration
of Pickering City Council
� V, S Aa J17,' 20!
Tony Prevedel, P.Eng.
Chief Administrative Officer
TOREPORT #�
ATiACi -i MEiVT;# � � tu
� f_a
City 00 APR 4
ICI
I I C6"f'Y OF PICKFR10S
PICKERINENGINEERING
To: 'Richard Holborn
Director, Engineering & Public Works
From: Vera A. Felgemacher
Manager, Supply & Services
Copy: Manager, Capital Works & Infrastructure
Subject: Tender No. T -9 -2013 ,
Tender for Asphalt and Concrete Repairs
- RIP- F- 5400 -001
Memo
April 3, 2013
Tenders have been received for the above project. An advertisement was placed in the Daily
Commercial News and on the City's website inviting companies to download the tendering
documents and drawings for the above mentioned tender. Seven (7) bidders submitted a .
tender for this project.
A copy of the Record of Tenders Opened and Checked used at the public tender opening is
attached. Tenders shall be irrevocable for 60 days after'the official closing date and time.
Purchasing Procedure No. PUR 010 -001, Item 13.03 (r) provides checking tendered unit
prices and extensions unit prices shall govern and extensions will be corrected accordingly,
which has been done.
All deposits other than the low three bidders may be returned to the applicable bidders as
provided for by Purchasing Procedure No. PUR 010 -001, Item 13.03(w). Three (3) bids have
been retained for review at this time.
Copies of the tenders are attached for your review along with the summary of costs.
SUMMARY
Harmonized Sales Tax Included
Bidder
Total, Tendered Amount :
After Calculation Check.
Ore Construction Ltd.
$337,475.16
$337,475.17
Serve Construction Ltd.
$391,299.46
$391,299.45
Ashland Paving Ltd.
$395,362.46
$395,362.46
Aloia Bros. Concrete Contractors Ltd.
$421,846.85
$478,516.69
2274084 Ontario Ltd. o/a GMP
Contracting
$424,519.53
$424,519.53
Trisan Construction
$536,732.49
$536,732.49
Royalcrest Paving
$647,210.89
$647,210.89
ATTACHMENT# ��� TOREPORT #LN G o5—_1_3
Pursuant to Information to Bidders Item 31, the fel nY, 41 e requested of the low bidder for
your review during the evaluation stage of this tender call. Please advise when you wish us to
proceed with this task.
(a) A copy of the currently dated and signed Health and Safety Policy to be used
on this project;
(b) A copy of the current Workplace Injury Summary Report issued by Workplace
Safety & Insurance Board (in lieu of the Workplace Injury Summary Report
document, a copy of the current CAD 7, NEER, or MAP reports may be
submitted);
(c) A copy of the current Clearance Certificate issued by Workplace Safety &
Insurance Board;
(d) Proof of compliance with amended Confined Space Entry Regulations
(September 30, 2006). Copies of certified Training and Procedures to be used
on this project;
(e) A list of employees trained in the confined space entry procedure who will be
working on this project,
(f) The City's certificate of insurance or approved alternative form shall be
completed by the bidder's agent, broker or insurer;
(g) The City's Accessibility Regulations for Contracted Services form currently
dated and signed;
(h) list of Sub - Contractors in accordance with General Conditions Item 37; and
(i) Waste Management Plan to be used on this project in accordance with
Tendering Specifications Item 18.
Please include the following items in your Report to Council:
(a) if items (a) through (e) noted above, are acceptable to the Co- ordinator, Health &
Safety;
(b) if item (f) — Insurance — is acceptable to the (Acting) Manager, Budgets & Internal
Audit,
(c) any past work experience with the low bidder Ore Construction Ltd. including work
location;
(d) without past work experience, if reference information is acceptable;
(e) the appropriate account number(s) to which this work is to be charged;
(f) the budget amount(s) assigned thereto;
(g) Treasurer's confirmation of funding;
(h) related departmental approvals; and
(i) related comments specific to the project.
Please do not disclose any information to enquiries except you can direct them to the City's
website for the unofficial bid results as read out at the public tender opening. Bidders will. be
advsised of the outcome in due course.
If ybu require further information, please feel free to contact me or a member of Supply &
Se ices.
i
�i
VAF /jg
Attachments
April 3, 2013
Tender No. T -9 -2013
Tender for Asphalt and Concrete Repairs
Page 2
ATTACHMENT# TO REPORT# j_NG, OS 13
of_ RECEIVED
C &f o� -
-
APR 4 203
a CITY OF picERIN�
PICKERING sN °JEERING
To: `Richard Holborn
Director, Engineering & Public Works
From: Vera A. Felgemacher
Manager, Supply & Services
Copy: Manager, Capital Works & Infrastructure
Subject: Tender No. T -9 -2013
Tender for Asphalt and Concrete Repairs
- File: F- 5400 -001
Memo
April 3, 2013
Tenders have been received for the above project. An advertisement was placed in the Daily
Commercial News and on the City's website inviting companies to download the tendering
documents and drawings for the above mentioned tender. Seven (7) bidders submitted a
tender for this project.
A copy of the Record of Tenders Opened and Checked used at the public tender opening is
attached. Tenders shall be irrevocable for 60 days after the official closing date and time.
Purchasing Procedure No. PUR 010 -001, Item 13.03 (r) provides checking tendered unit
prices and extensions unit prices shall govern and extensions will be corrected accordingly,
which has been done.
All deposits other than the low three bidders may be returned to the applicable bidders as
provided for by Purchasing Procedure No. PUR 010 -001, Item 13.03(w). Three (3) bids have
been retained for review at this time.
Copies of the tenders are attached for your review along with the summary of costs..
SUMMARY
Harmonized Sales Tax Included
Bidder Total Tendered Amount After Calculation Check
Ore Construction Ltd. $337,475.16 $337,475.17
Serve Construction Ltd. $391,299.46 $391,299.45
Ashland Paving.Ltd. $395,362.46 $395,362.46
Aloia Bros. Concrete Contractors Ltd. $421,846.85 $478,516.69
2274084 Ontario Ltd. o/a GMP
Contracting $424,519.53 $424,519.53
Trisan Construction $536,732.49 $536,732.49
Royalcrest Paving $647,210.89 $647,210.89
ACHMENT# I - TO REPORT# 1� N U 0S -13
. of 2
Pursuant to Information to Bidders Item 31, the following will be requested of the low bidder for
your review during the evaluation stage of this tender call. Please advise when you wish us to
proceed with this task.
(a) A copy of the currently dated and signed Health and Safety Policy to be used
on this project;
(b) A copy of the current Workplace Injury Summary Report issued by Workplace
Safety & Insurance Board (in lieu of the Workplace Injury Summary Report
document, a copy of the current CAD 7, NEER, or MAP reports may be
submitted);
(c) A copy of the current Clearance Certificate issued by Workplace Safety &
Insurance Board;
(d) Proof of compliance with amended Confined Space Entry Regulations
(September 30, 2006). Copies of certified Training and Procedures to be used
on this project;
(e) A list of employees trained in the confined space entry procedure who will be
working on this project;
(f) The City's certificate of insurance or approved alternative form shall be
completed by the bidder's agent, broker or insurer;
(g) The City's Accessibility Regulations for Contracted Services form currently
dated and signed,
(h) list of Sub - Contractors in accordance with General Conditions Item 37; and
(i) Waste Management Plan to be used on this project in accordance with
Tendering Specifications Item 18.
Please include the following items in your Report to Council:
(a) if items (a) through (e) noted above, are acceptable to the Co- ordinator, Health &
Safety;
(b) if item ,(f) - Insurance - is acceptable to the (Acting) Manager, Budgets & Internal
Audit;
(c) any past work experience with the low bidder Ore Construction Ltd. including work
location;
(d) without past work experience, if reference information is acceptable;
(e) the appropriate account number(s) to which this work is to be charged;
(f) the budget amount(s) assigned thereto;
(g) Treasurer's confirmation of funding;
(h) related departmental approvals; and
(i) related comments specific to the project.
Please do not disclose any information to enquiries except you can direct them to the City's
website for the unofficial bid results as read out at the public tender opening. Bidders will. be
advised of the outcome in due course.
If y u require further information, please feel free to contact me or a member of Supply &
Se ices.
{
VAF /io
Attachments
April 3, 2013
Tender No. T -9 -2013 Page 2
Tender for Asphalt and Concrete Repairs
ATTACHMENT # �! TO REPORT #ryG 05'1.3
_._1_ of .�
Pelzowski, Mike
From: Tony Francis [Tony. Francis @ Durham. ca]
Sent: April -17 -13 12:27 PM
To: Pelzowski, Mike
Cc: Selsky, Darrell; Woolley, Don; Smith, Grant; Felgemacher, Vera; David Gooding
Subject: RE: T -9 -2013
Mike,
This email is confirmation that Durham Region Transit will participate in T -9 -2013 being awarded to Ore Construction
Ltd. for the construction of concreted standing areas and walkways at bus pads.
We understand that the results are based on the original quantity of 95 stops and that actual costs will reflect actual
quantites.
I look forward to working with you again.
Tony
Tony Francis
Supervisor, Scheduling
44 William Street, Oshawa, ON
(Office) 905 - 571 -5019 Ext. 225
(Fax) 905 - 571 -7390
tony.francis @durham.ca
From: Mike Pelzowski [ma i Ito: mpelzowski(apickering.ca]
Sent: April -16 -13 12:26 PM
To: Tony Francis
Cc: Darrell Selsky; Don Woolley; Grant Smith; Vera Felgemacher
Subject: T -9 -2013
Mr. T. Francis
Supervisor Scheduling
Durham Transit
Tony,
Attached are the bidder results of the Concrete and Asphalt Tender T -9 -2013 for your information
and file.
Could you please reply noting confirmation and acceptance of the results and participation in the
program.
Of note, the results are based on the original transit pad quantity of 95 which was recently revised via
your memo of March 15, 2013 to 100 pads. Consequently, actual costs will reflect actual quantities.
ATTACHMENT# __;� _ FOREPORT# � D�S-12a
'�'_ of �_
Thanks.
Mike Pelzowski CET
Coordinator, Roads & Infrastructure Maintenance Contracts Engineering & Public Works
Department
905.420.4660 ext. 5227 1 1.866.683.2760 1 TTY 905.420.1739 Cell 905.767.6154
mpelzowski()pickering.ca
Your City, Right Now. pickering.ca
CiityApp a eNews 0 twitter 91 facebook
This message is for the use of the intended recipient(s) only and may contain information that is
privileged, proprietary, confidential, and /or exempt from disclosure under any relevant privacy
legislation. If you are not the intended recipient or authorized agent thereof, you are hereby notified
that any review, retransmission, dissemination, distribution, copying, conversion to hard copy, taking
of action in reliance on or other use of this communication is strictly prohibited. If you are not the
intended recipient and have received this message in error, please notify the sender by return e-mail
and delete or destroy all copies of this message.
�x.
Report No. ENG 05 -13
Attachment # 3
1 of 2
Engineering & Public Works Department
Attachment for TenderT -9 -2013
Beechlawn Park Walkway
Location Map — Beechlawn Park
Proposed Construction Includes:
Beechlawn Park Walkway and Lighting Installation - The proposed works to include
installation of a new asphalt walkway.
W W
°
W
>
W
° >
z
m � °
°
°
z
m
0
Q
Q
CE)
�-
r
Q
m
O
DRIVE
J W
W
D
o
ry
BANBURY
U
� W
=
COURT
Q_.....__
-- ......__.
DRIVE
z
SUBJECT
AREA W
°
W
O
W =
:�i I U
o >
�
z
YD W
°
Z
Y
m 0
0
O
-j
o
N
-
C2
PICKERING
PARKWAY
Location Map — Beechlawn Park
Proposed Construction Includes:
Beechlawn Park Walkway and Lighting Installation - The proposed works to include
installation of a new asphalt walkway.
/ll
Report No. ENG 05 -13
Attachment # 3
2 of 2
Engineering & Public Works Department
Attachment for Tender T -9 -2013
Rouge Valley Park Pathway
TWYN
COURT
RIVERS DRIVE
LAWSON STREET
C.N.R.
TWYN RIVERS DRIVE
O
BRIMWOOD O� j
HOWELL j Q
�
3a
COURT Q O D
a Q
O RICHARDSON O
CTS
STREET
CRESCENT STREET
00�
LITTLEFORD
/� OOOV\�W
�2 N1
ff
I'F
Iji
O STOVER
A
O CRESCENT
G
O DRIVE
m
SUBJECT
PETUNIA 2%
PARK
PLACE
Q
Z
GWENDOLYN O
9<
STREET
DRIVE Q
Location Map — Rouge Valley Park Pathway
Proposed Construction Includes:
Rouge Valley Park Pathway Resurfacing - The proposed works to include removal and
replacement of the existing pathway.