HomeMy WebLinkAboutCR 07-13 ��t� �� Report to
'�' Executive Committee
� �
PICKERING RePo� Number: cR o�-�s
Date: April 15, 2013
From: Stephen Reynolds
Director, Culture & Recreation
Subject: Tender for West Shore Community Centre Entrance & Washroom
Renovation Project
- Tender No. T-8-2013
- File: A-1440
Recommendation:
1. That Report CR 07-13 of the Director, Culture & Recreation regarding the West
Shore Community Centre Entrance &Washroom Renovation Project be
received; �
2. That Tender No. T-8-2013 submitted by Direct Construction Co. Ltd. in the
amount of$162,720.00 (HST included) be accepted;
3. That the total gross project cost of$236,566.00 (HST included), including the
tender amount and other associated costs, and the total net project cost of
$213,035.00 (net of HST rebate), be approved;
4. That Council authorize the (Acting) Division Head, Finance & Treasurer to fund
the project as follows:
a) the sum of$70,940.00 as provided for in the 2013 Community Centres
Capital Budget to be funded from the Community Infrastructure Improvement
Fund (CIIF) Federal Grant;
b) the sum of$142,000.00 as provided for in the 2013 Community Centres
Capital Budget to be funded from a five-year internal loan at a rate to be
determined; and
c) the balance of$95.00 to be funded from property taxes; and I
5. That the appropriate City of Pickering officials be authorized to take necessary
action to give effect thereto.
Executive Summary: The City of Pickering has been approved for funding under
the Community Infrastructure Improvement Fund for the West Shore Community Centre
Entrance and Washrooms. This project was approved in the 2013 Capital Budget in the
amount of$314,344.
Report CR 07-13 April 15, 2013
Subject: Tender for West Shore Community Centre Entrance .
& Washroom Renovation Project � � Page 2
The West Shore Community Centre Entrance and Washroom Renovation project will
include installing an accessible entrance to the community centre which includes a ramp
and railing, redesigning and installing an upgraded interior entrance space, replace
lighting with new energy efficient lighting controls and fixtures, upgrading existing
washroom facilities and constructing an accessible washroom.
The low bid submitted by Direct Construction Co. Ltd. in the amount of$162,720.00
(HST included) is recommended for approval. The total gross project cost is estimated
at $236,566.00 and the total net project cost is estimated at $213,035.00 (net of HST
rebate).
Financial Implications:
1. Tender No. T-8-2013
Accessibility Upgrades/Alternations to West Shore $144,000.00
HST (13%) 18,720.00
Total Gross Tender Cost �162,720.00
2. Estimated Pro"ect Costin Summa
Tender No. T-8-2013 for Accessibility Upgrades/Alternations
to West Shore $144,000.00
Miscellaneous Costs 2,000.00
Communication Costs (project signage, public . 5,000.00
announcement)
Consulting Costs 28,350.00
Construction Contingency 30,000.00
Total Project Costs $209,350.00
HST (13%) 27,216.00
Total Gross Project Cost $236,566.00
HST Rebate (11.24%) �23,531.00)
Total Net Project Cost $213,035.00
CORP0227-07/01 revised
Report CR 07-13 April 15, 2013 '
Subject: Tender for West Shore Community Centre Entrance I
&Washroom Renovation Project Page 3 �I
I
3. A roved Source of Funds
pp
� Communit Centres Bud et
Account Code Source of Funds Budget Required
5719.1303.1610 Federal Grants $104,677.00 $70,940.00
5719.1303.1711 Internal Loan (5 year) 209,000.00 142,000.00
5719.1303.2823 Property Tax 667.00 95.00
$314,344.00 �213a035.00
Project Cost under (over) approved funds by , $101,309.00
The City of Pickering was successful in receiving a Federal Grant with the Community
Infrastructure Improvement Fund for the West Shore Community Centre Entrance and
Washroom Renovation project that covers up to a third of the total project cost. The
estimated project cost submitted for the grant application was $314,344, out of which
$104,677.00 (1/3) was approved to be funded by the CIIF grant. The amount
reimbursable by this grant is limited to 33.3% of the total cost of the project. The City
bears the remaining share of the 66.7%. As the tender came in under than the j
estimated cost submitted for the grant application, the amounts to be funded from the
CIIF grant and City's share have been adjusted accordingly. Table 3 provides the
amount to be funded from each party according to the approved funding ratio.
As per the contribution agreement for the CIIF grant, this project must be completed by
March 31, 2014 and as such immediate project mobilization is critical to this project.
Discussion: The West Shore Community Centre Entrance and
Washroom Renovation Project was approved by Council in the 2013 Capital Budget in
the amount of$314,344.00.
As part of the City of Pickering Five Year Accessibility Plan (2011-2016), renovations at
the West Shore Community Centre (WSCC) was identified as a 2013 capital project.
A number of improvements to the WSCC entrance and washroom facilities are required
in order to provide barrier free access to facility users.
The West Shore Community Centre Entrance and Washroom Renovation project will
include the installation of an accessible entrance with ramp and automatic doors;
redesigned interior entrance space with new recycled flooring and energy efficient
windows; upgraded washroom facilities with energy efficient fixtures and the installation
of a new universal washroom; and, energy efficient lighting replacement to the entrance
CORP0227-07/01 revised
Report CR 07-13 April 15, 2013
Subject: Tender for West Shore Community Centre Entrance
&Washroom Renovation Project Page 4
area and washroom facilities. West Shore Community Centre is a well used facility for
programs and events. These upgrades will provide accessible access to all facility
users regardless of their abilities.
Bids have been received to the tendering call, which closed on Tuesday, March 26th,
2013. A mandatory site visit was held on Thursday March 14, 2013 for the eight ;
prequalified contractors selected to submit a tender for this project. The low bid was
submitted by Direct Construction Co. Ltd. !
Jurecka + Associates, consultant on the renovation project, recommends Direct
Construction Co. Ltd. as the lowest acceptable qualified bidder. The Health and Safety
Policy, a current WSIB Workplace Injury Summary Report, Clearance Certificate issued
by Workplace Safety and Insurance Board (WSIB) as submitted by Direct Construction
Co. Ltd. have been reviewed by the Coordinator, Health & Safety and deemed
acceptable. Certificate of Insurance is deemed acceptable to (Acting) Manager,
Budgets & Internal Audit. In conjunction with staff's review of the contractor's previous
work experience, check of references and bonding available on this project, the tender
is deemed acceptable.
Upon careful examination of all tenders and relevant documents received, the Culture &
Recreation Department recommends the acceptance of the low bid submitted by Direct
Construction Co. Ltd. for Tender No. T-8-2013 in the amount of$162,720.00 (HST
included) and that the total net project cost of$213,035.00 be approved. '
Attachments: �
1. Location Map
2. Supply & Services Memorandum dated March 26, 2013
3. Letter from Paul Jurecka, Jurecka + Associates Architects Inc. dated March 27,
2013.
Prepared By: Approved/Endorsed By:
�
Marisa Carpino ` Stephen Rey old�
Manager, Culture & ecreation Director, Culture & Recreation
CORP0227-07/01 revised
Report CR 07-13 April 15, 2013
Subject: Tender for West Shore Community Centre Entrance - .
& Washroom Renovation Project Page 5
Vera A. Felge acher Stan Karwowski
C.P.P., CPPO, CPPB, C.P.M., CMM III (Acting) Division Head, Finance & �
Manager, Supply & Services Treasurer
.,
��+�-- � � .
Caryn Kong, CGA Paul Bigio
Senior Financial Analyst-Capital & Director, C r.por te rvices & City Solicitor
Debt Management Treasurer
SR:mc ,
_ I
Recommended for the consideration �
of Pickering Cit Council .
,4 ' 2, zo�3
Tony Prevedel, P.Eng.
Chief Administrative Officer
CORP0227-07/01 revised
�`('TACHMENT# � TC3 REPORT#C� �� "— � �
-�°":.
.,...
�..
. 'f�..�
D��� _�....-� � ..�..
H�N P� . "� ..�.
��" ..--�--`�`�� .w---.....,�..
`` .�..
,� r�.. .�- 2 2 ,
_ �...
....-S�R��� �__�
.��--- � .
..�-
.�..
�- �,� _
BP� _
�........
.�-w--=
�, __.........---- S U BJ ECT �
SITE
WEST S RE
CO N TY
CENTR
�l�El�l C H M/-� l�l 'S
B,q Y
[� � �° aQ �
a ___ _�_� ______�_ � _�_ ._�`` . =�
__��._________ DRIVE ,
VISTULA ___ _____�� .
_-__ ._ , �
_--__
____ ,
�_ - �
_ ❑ � '
�
ENG�tvEERIi�G&PUBL�C ATTACHMENT FOR COMMUNITY
woxics DEPARTMENT SERVICES REPORT CR 07-13 � �� , ;
CAPITAL PROJECTS&
INFRASTRUCTURE RENOVATION PROJECT T-8-2013 � �
S�^�E °"TE WEST SHORE COMMUNITY CENTRE
N.T.S March 25/2013
��T�CHNi�NT# 2 TU�CEPORT# � ��— ��
�L� O�
���
� �
� PICKERING � M (�1'Y1 O �
To: Stephen Reynolds March 26, 2013
- Director, Culture &_Recreation
From: Vera A. Felgemacher
Manager, Supply & Services
Copy: Manager, Culture & Recreation
Supervisor, Facilities Operations -
Subject: Tender No. T-8-2013
Tender for West Shore Community Centre Entrance &Washroom Renovation Project
- File: F-5400-001 �
Tenders have been received for the above project. An advertisement was placed in the Daily
Commercial News and on the City's website inviting prequalified companies to download the
tendering documents for the above mentioned #ender. One (1) addendum was issued on this
project. A mandatory site visit was held on Thursday, March 14, 2013. Ten (10) companies
attended the site visit of which six (6) bidders submitted a t�nder and one (1) bidder responded as
unable to bid. .
A copy of the Record of Tenders Opened and Checked used at the public tender opening is
attached. Tenders shall be irrevocable for 60 days after the official closing date and time. ,
Purchasing Procedure No. PUR 010-001, Item 13.03 (r) provides checking.tendered unit prices .
and extensions unit prices shall govern and extensions will be corrected accordingly, which has
been done.
All deposits other than the low three bidders may be returned to the applicable bidders as provided
for by Purchasing Procedure No. PUR 010-001, Item 13.03(w). Three (3) bids have been retained II
for review at this time. �
Copies of the tenders are attached for your review along with the summary of costs.
SUMMARY
Harmonized Sales Tax Included �
Bidder Total Tendered Amount After Calculation Check
Direct Construction Co. Ltd. $162,720.00 � $162,720.00 � _
M/2 Group Inc. $224,618.01 $224,618.01
DASD Contracting Inc. $225,830.50 $225,830.50
� Gerr Construction Ltd. $231,650.00 . $231,650.00
� Rutherford Contracting Ltd. $319,790.00 $319,790.00
BECC Construction Ltd. $395,500.00 $395,500.00
HN Construction Ltd. Unable to Bid
. � -
References have already been checked-and deemed acceptable during the prequalification
process of Request for Proposal No. RFP-9-2012 -
Pursuant to Information to Bidders Item 32, the following will be requested of the low bidder,
Direct Construction Co. Ltd. for your review during the evaluation stage of this tender call.
Advise when you wish us to proceed with this task.
(a) the City's certificate of insurance shall be completed by the bidder's agent,
broker or insurer (received with tendering document); ,
(b) the City's Accessibility Regulations for Contracted Services form currently dated
� and signed (received with tendering document);
(c) list of Sub-Contractors in accordance with General Conditions Item 30 (received
with tendering document); and �
(d) Waste Management Plan to be used on this project in accordance with
Tendering Specifications Item 18. , .
. Please include the following items in your Report to Council:
(a) if item (a) — Insurance — is acceptable to the (Acting) Manager, Budgets & Internal
Audit; .
(b) the appropriate account number(s) to which this work is to be charged;
(c) the budget amount(s) assigned thereto;
(d) Treasurer's confirmation of funding;
(�e) related departmental approvals; and .
(fl related comments specific to the project.
P�lease do not disclose any iriformation to enquiries except you can direct them to the City's
website for the unofficial bid results as read out at the public tender opening. Bidders will be
advised of the outcome in due course. '
If y u require further information, please feei free to contact me or a member of Supply &
Se ices. .
. ,.�. . '
VAF/jg
Attachments � �
March 26, 2013
Tender No. T-8-2013 Page 2 I,
West Shore Community Centre Entrance &
Washroom Renovation Project
� , .
� '
�
_ ,r G� C� :CJ � C7 G� 00� � C� 0 ;`- _:;"''` .
' z Q. (D ? rtpD am N Q �' ;, :c�. ,,
n ' -, ,-„ � ' Cn � C� m
\ -� (p r ,n�, W `}
� � OC�'i �, 0 'an G� � Q :;
• � rt ~. o � ~. � c o ''� • �
� � � n. �- ->m
m C � rt rt � � : :i�[;y-;.,
? . ��-, n r v � � � '. �%'Z.'.:.;'.; .
cD O = R t� C c� C c.>.�^v'.?,
7 O • '_" h C�
rt . :���' �,:'.
o ' r' � cQ ° ° �?` '>
� a � ? ' -� �
v ;::: ::. :•.;:
�
, f-;;;, ..;:.. a
m
:.:W.,:;: .-i ''
::Q;:,::r � p.
y i`:Q::-'..�:: Q •,� ' •
= • �'' N p
"..-t.; '`�. � -�
. �: �,, . � :�.:��. Z .�
�— �a�';:�°;: o , o
.'�:i';=. �
� � - 'r�. :."'; --1 ., _
� , '.'�:. ' N cD
O �
�� • � cn:�a�i,�.',Di -' �
� -< -< • -< � -< -< -G m:�:�`:�; c'' �
ai v�i v�i ai v�i ai c�ir G:a';�� o ;p
' a �,.Q �
m N'_o::�:-co- m
� • � n
. Q . . �:rt�:�.: ,.e0:` .
;,.:�.:; .ti y � .
� D ', rt � I
�:.:. D �
c �'.:';.. � �' p
�::;• °:Q�.
� o -�
�� ( e:..Z::�: m �
� ' \ ( . � o:.= -�
� \ �.::i._ �� n m c�
� � i�D:.';,�.Q:? -1 0 Z
� ( , a'.::.:°c;: � � o �
m ' - \ �- '`3J c. 3 m O
� .O n.:;:,..._,_, � � � -n
\ � � � � � . . _ �
v -� 0 o p o � o ;>d,>:.`..:s � '� � c�
_ � o�. o`� � :,:�.., -�
�' m � o� o�. \ .�,:.00�: w n m �
o � � � -;o'_Q-.' � � z m
+�, , � OO � � Q '.' y'' -.`.. �' ,.y, ffl .Zl
::'+.'':- �, t�1 � p Z
o a � D �
rn
o ; �:,.;y; i � �
f..:-°:.:ia;=
� � 00`�.�::�;- ta su n
w � \ � � � o::-�tm-. � _
� �:;:o•, .. � m
m c �. .:�; �D �
o a�i � , `�., �
�_ - ' a- , � � 0
_ �� �. . �s �i tva . f» ss y� -1;.'. ..:`.:"� �' �..
�n 0 fD,.:..,:. ; (p �
p 7'-;!.' :.,_. p
n Q r� � � 1N � � fl..• .. � O
O � � � �V � �p�_.��:.:�W: D ,
� � \O � � � /V �•..�:.�. .� �
'fD.:. ':N: . -O
� _ _ _ _ - _ Q:t;,,�.a..;fD:: -s �7
� ' � � � � � �( -�''�`:� X 7 .
� . �' � Q � �p p ;3r."�':;•:Q:` N .c
,o;:..;.:.-
Q �a g � �o �� ��, ;�: -::.:;� �; �
y b rt::,. :� .a 3
m- � 'o
� �
o , `��{..;�.; �
-� ,.0;':•..
y • }_ ��-,,,
. . m.,,_,.;
z:`='.,.
, ;::�>:-;:.
� _ ;`.,;�..;;.,
� � . �
, .
, -
A�`�"ACF�M�NT#t�T�REFORT# C�, O� ^ L �J
� �urecka � Associates Architects Enc
� 150 Glendale Ave,
� • �01'4f1tQ, ��R��2
� March 27, 2013 tel 41fi-�72-9385
fx 866-475-7256
www.jurecka . ca
Division of Culture & Recreation
City of Pickering
One, The Esplinade
Pickering, Ontario
L1 V 6K7
Attn: Marisa Carpino, Division Head
Re: Review of Tender T-8-2013:
West Shore Community Centre Entrance and Washroom Renovation Project
Dear Ms. Carpino:
The lowest tender for the West Shore Community Centre was submitted by Direct
Construction Company Ltd.. The City has already prequalified this contractor as part of
their recent process, so I have not sought to further review their experience at this stage..
Although we have no direct experience with them, we trust th�at Direct Construction
Company Ltd, the lowest acceptable qualified bidder for your tender no. T-15-2012 has
satisfied the tender requirements and is qualified to undertake this project as the General
Contractor. Since your purchasing policy requires that you take the lowest bid, we accept
that you award the contract to Direct Construction Company Ltd,. on the basis of their
bid submitted March 26, 2013. The base bid (including HST) should result in a contract
amount of$162,720.00. We further advise that you carry a contingency of at least 10%
for unforeseen conditions or associated project expenses.
Sincerely,
Paul Jurecka OAA
Jurecka + Associates Architects Inc.