Loading...
HomeMy WebLinkAboutOES 42-09 Cary REPORT TO EXECUTIVE COMMITTEE PICKERING Report Number: OES 42-09 299 Date: July 6, 2009 From: Everett Buntsma Director, Operations & Emergency Services Subject: Roof Replacement - Pickering Public Library and Fire Hall #2 - Tender No. T-12-2009 - File: A-1440-001-09 Recommendation: 1. That Report OES 42-09 of the Director, Operations & Emergency Services regarding Roof Replacement at Pickering' Public Library and Fire Hall #2 be received; 2. That Tender T-12-2009 submitted by Crawford Roofing Corporation at a cost of $214,200 (GST included) be accepted; 3. That staff be authorized to negotiate with the low bidder to undertake the additional roofing work at Petticoat Creek and Whitevale Library, at a cost not to exceed the project costing as outlined in the report; 4. That the total gross project cost of $259,350 (GST included) and a net project cost of $247,000 including the tender amount and other associated costs be approved; 5. That Council authorize the Director, Corporate Services & Treasurer to finance the project as follows: a) the sum of $65,000, as provided for in the 2009 approved Capital Budget for Fire Services, to be financed through property taxes b) the sum of $74,000 as provided for; in the 2009 approved Capital Budget for Libraries-Central & Whitevale and Petticoat Creek Library and Community Centre, to be financed through Provincial Grants-Investing in Ontario c) the amount of $100,000, as provided for in the 2009 approved Capital Budget for Library-Central, to be financed through Federal Gas Tax funding d) the additional amount of $8,000 for'iPetticoat Creek Library and Community Centre Roof Rehabilitation to be funded from Federal Gas Tax i Report OES 42-09 July 6, 2009 Subject: Roof Replacement - Pickering Public Library and Fire Hall #2 Tender No. T-12-2009 Page 2 300 e) the Director, Corporate Services & Treasurer be authorized to take any actions necessary in order to affect the foregoing; and 6. That the appropriate City of Pickering offigials be authorized to take necessary action to give effect thereto. Executive Summary: The roof replacement at Pickering Public Library and Firehall #2 was approved by Council in the 2009 Capital Budget for the total amount of $265,000. An allowance of $5,000 was approved in the 2009 Capital Budget for a roof rehabilitation design at Petticoat Creek Community Centre and Library. The existing roof structures have reached the end of their useful life cycles and currently are experiencing failure. in several key areas. Replacement of the roof structures will resolve the leakage issues, resulting in the reduction of maintenance costs as well as improving the insulation factors. Since the time of budget approval, staff have been made aware of additional roof leaking issues at the Whitevale Library, as well as confirmation of a budget cost for the roof replacement at Petticoat Creek Community Centre & Library. The marginal additional costs to undertake these two (2) additional roof repairs have been estimated at $21,000 and can be accommodated from savings from this low tender result. The four (4) roof replacement projects combined are $23,000 less than the approved budget, in accordance with the low tender. Financial Implications: 1. TENDER AMOUNT T-12-2009 $204,000 GST 10,200 Sub-Total 214,200 GST Rebate (10,200) Total 204,000 CORP0227-07/01 revised Report OES 42-09 July 6, 2009 Subject: Roof Replacement - Pickering Public Library and .Fire Hall #2 301 Tender No. T-12-2009 Page 3 2. APPROVED SOURCE OF FUNDS Central Library Capital Budget Operations & Emergency Services Department,Capital Budget Location Project Code Source of Funds Budget Required T-12-2009 Roofing 5800.0913.6181 Federal Gas Tax $100,000 $100,000 Repair - Central Provincial Grants- 100,000 61,000 Library Investing in Ontario Whitevale 5800.0913.6181 Provincial Grants- 0 5,000 Library Investing in Ontario Roof for 5340.0925.6181 Property Taxes 65,000 65,000 Firehall #2 Roof 5719.0910.6181 Provincial Grants- Rehabilitation Investing it Ontario 5,000 8,000 (PCCC) Federal Gas Tax 0 81000 FUNDS AVAILABLE $270,000 $247,000 3. ESTIMATED PROJECT COSTING SUMMARY T-12-2009 $204,000 Tender & Miscellaneous Costs 2,000 Construction Contingency 20,000 Allowance for Petticoat Creek and Whitevale Library Roof 21,000 Repairs Total Project Costs 247,000 GST 12,350 Total Gross Project Cost 259,350 GST Rebate 1( 2,350) Total Net Project Cost $247,000 Project Cost under (over) approved funds by $23,000 CORP0227-07/01 revised Report OES 42-09 July 6, 2009 Subject: Roof Replacement - Pickering Public Library and Fire Hall #2 Tender No. T-12-2009 Page 4 302 Sustainability Implications: The existing roof structures have reached the end of their useful life cycle, and are currently experiencing failure in several key areas. Replacement of the four roof structures will resolve the leakage issues, resulting in the reduction of maintenance costs as well as improving the insulation factors. Background: Bids have been received to the tendering call, which closed on Wednesday, June 17, 2009 for the replacement of the roof structure for the Pickering Public Library and Firehall #2. Eleven (11) companies were invited to participate. An advertisement was placed in the Daily Commercial News and on the City's website. A mandatory site visit was held on Tuesday, June 11, 2009 and eleven (11) companies attended of which seven (7) bidders responded and submitted a bid for this project. The low bid was submitted by Crawford Roofing (Corporation. This company's references have been checked and are deemed acceptable by the Division Head, Facilities Operations. The Health and Safety Policy, Clearance Certificate issued by Workplace Safety and Insurance Board (WSIB), the WSIB Cost and Frequency Record and Certificate of Insurance as submitted by Crawford Roofing Corporation have been reviewed by the Coordinator, Health & Safety and are deemed acceptable. In conjunction with staffs review of the contactor's previous work experienge and bonding available on this project, the tender is deemed acceptable. Upon careful examination of all tenders and relevant documents received, the Facilities Operations Division recommends the acceptance of the low bid submitted by Crawford Roofing Corporation for Tender No. T-12-2009 in; the amount of $214,200 (GST included) and that the total net project cost of $247,000 be approved. In addition to the two roof replacements allowed for in the recent tender call, staff have recently been made aware of additional roof leaking issues at the Whitevale Library, as well as confirmation of a budget cost for the roof replacement at Petticoat Creek Library and Community Centre. The additional funds required under the Roof Reh, abilitation (Petticoat Creek Library and Community Centre (PCCC) will be funded by both Provincial Grant Investing in Ontario ($8,000) and Federal Gas Tax ($8,000). The original budget ($5,000) for this project was to be funded from Provincial Grant only, but with the additional cost requirement and to be consistent with the funding treatment of the Roofing Repair - Central Library, it is deemed appropriate to draw additional funds,,from Federal Gas Tax and that the total cost for this project be shared 50/50 between the Provincial Grant and the Federal Gas Tax. CORP0227-07101 revised Report OES 42-09 July 6, 2009 Subject: Roof Replacement - Pickering Public Library and Fire Hall #2 303 Tender No. T-12-2009 Page 5 Due.to the fact that the City has received a very favourable tender result for the current tender, staff recommend including the work required for the two additional roofs (Petticoat Creek and Whitevale) at an estimated cost of $21,000 into the tender as a negotiated extra. This report has been prepared in conjunction with the CEO, Public Library, the Fire Chief and the Manager, Supply & Services who concurs with the foregoing. Attachments: 1. Supply & Services Memorandum dated June 17, 2009 2. Record of Tenders opened and checked Prepared By: approved orsed By: . Tony Prevedel Everett Bunts Division Head, Facilities Operations Director, Operations & Emergency Services Gillis Paterson Director, Corporate Serv' es & Treasurer Douglas Fire Chief CORP0227-07/01 revised Report OES 42-09 July 6, 2009 Subject: Roof Replacement - Pickering Public Library and Fire Hall #2 Tender No. T-12-2009 Page 6 304 Cathy Grant CEO, Pickering Public Libraries Vera A. Felgemacher C.P.P., CPPO, CPPB, C.P.M., CMM III Manager, Supply & Services TP:mld Copy: Chief Administrative Officer Recommended for nsideration ZofPickering C C ncil A x'23 d T o s J. Qui DMR, CMM II Chief Administrative Officer I CORP0227-07/01 revised ATTACHMENT#TO REPORT# 0~'*a-09 305 Of • MACK4ER MEMO To: Tony Prevedel June 17, 2009 Division Head, Facilities Operations From: Vera A. Felgemacher Manager, Supply & Services Copy: Supervisor, Facilities Operations Subject: Tender No. T-12-2009 Tender for Pickering Public Library & Pickering Fire Hall # 2 Roof Replacement Closing: June 17, 2009 Tenders have been received for the above project. An advertisement was placed in the Daily Commercial News and on the City's Website. Eleven (11) companies were invited to participate. A mandatory site visit was held on Thursday, June 11, 2009, eleven (11) bidders attended of which of which seven (7) bidders responded A copy of the Record of Tenders Opened and Chocked used at the public tender opening is attached. Tenders shall be irrevocable for 60 days after the official closing date and time. Purchasing Procedure No. PUR 010-001, Item 10.03 (r) provides checking tendered unit prices and extensions; unit prices shall govem and extensions will be corrected accordingly, which has been done. All deposits other than the low three bidders may be returned to the applicable bidders as provided for by Purchasing Procedure No. PUR 010-001, Item 10.03(w). Three (3) bids have been retained for review at this time. SUMMARY PST & GST i' eluded Bidder Total Tendered Total Tendered After After Amount Option 1 Amount Option 2 Calculation Calculation' (Base Bid) (Alternate Bid) Check $ Check $ Crawford Roofing Corp. $214,200.00 No Bid $214,200.00 No Bid Trio Roofing Systems $233,100.00 No Bid $233,100.00 No Bid Inc. T. Hamilton & Son $236,388.60 No Bid $236,388.60 No Bid Roofing Inc. Aseal Roofing & Sheet $258,825.00 ;'No Bid $258,825.00 No Bid i ATTACHMENT# f TOREPORT# 0L'S4 OCJ o2_ of .1 306 Metal Ltd. Nortex Roofing Ltd. $266,070.00 No Bid $266,070.00 No Bid Sproule-Specialty Unable to bid Roofing Ltd. Flynn Canada Unable to bid Pursuant to Information to Bidders Item 21, the following will be requested of the low bidder for your review during the evaluation stage of this tender call. Please advise when you wish us to proceed with this task. (a) a copy of the Health and Safety Policy to be used on this project, currently dated and signed; (b) a copy of the current Cost and Frequency Report issued by Workplace Safety & Insurance Board (in lieu of the Cost and Frequency document, a copy of the current CAD 7, NEER, or MAP reports may be submitted); (c) a copy of the current Clearance Certificate issued by Workplace Safety & Insurance Board (received with submission) (d) the City's certificate of insurance completed by the bidder's agent, broker or insurer Q; (e) list of sub-contractors.in accordance with GC Item 32, Include the following items in your Report to Council: . (a) if items (a) through (d) noted above, are acceptable to the Co-ordinator, Health & Safety; (b) any past work experience Crawford Roofing Corp. including work location; (c) without past work experience, if reference information is acceptable; (d) the appropriate account number(s) to which this work is to be charged; , (e) the budget amount(s) assigned thereto; (f) Treasurer's confirmation of funding; (g) related departmental approvals; (h) any reason(s) why the low bid of Crawford Roofing Corp. is not acceptable; and (i) related comments specific to the project. Please do not disclose any information to enquiriias except you can direct them to the City's. website for the unofficial bid results as read out at the Public tender opening. Bidders will be advised of the outcome in due course. If you require further information, please feel free to contact me or a member of Supply & S rvices. C` VF/jg Attachments June 17, 2009 Tender No. T-12-2009 Page 2 Tender for Pickering Public Library & Pickering Fire Hall #2 Roof Replacement ATTACHMENT #sA._'TOREPORT# 1 of- 307 D 0 z -n cn a~ = M. o 0 o X = c - n m cn g °o d '0 p7 C/3 ~ 0 a go 5 0 1 d m W T m a m ~ z X ;o 3 0) 3 g cn co m Z ~ ~ a D n ~ -G m CD o H vCD~, y ~ H y mm a CD CD o s z <D 12 o. 71 1 O o O a y ° m tO C7 m O• CL O D 0 Za CD m n aQ°c W m aN3 7W 0 cr O 0 a IN, O ~ o o. Sr o a r On ti !v Q c- m' m C 0 -0 W 20 m 0 Z a3 1 a > ° 0 m m g p N o rn v W (1) Q 0 0 C7 ao W R° T = a a o o a~ m mKc N 0 m O R a 0 !V C) m n z o cn 'o 3 z z ci 0 3 m z cn