REPORT TO COUNCIL
FROM:
Everett Buntsma
Director, Operations & Emergency Services
DATE: July 30,2001
REPORT NUMBER: OES 021-01
SUBJECT: Tender for the Construction of the
Petticoat Creek Pedestrian Bridge
Tender No. T-6-2001
RECOMMENDATION:
It is recommended that Report OES 021-01 from the Director, Operations & Emergency Services
be received and that:
1. Tender No. T-6-2001 submitted by King City Group Ltd. to complete the construction of the
Petticoat Creek Pedestrian Bridge in the mount of $823,889.30 including 7% G.S.T. be
accepted;
2. The total project cost of $1,006,298.67 including the tender amount and other associated
costs be approved;
-
3. The funding in the amount of $1,007,000.00 including transfers from Development Charges
(#4227) and Parkland (#4230) Reserve Funds and other sources as identified in prior years
Capital Budgets be approved;
4. a) Debt financing in the amount of$231,000 to be financed internally, for a period not
exceeding 10 years, at a rate of 7 percent per annum, be approved;
b) Financing and repayment charges in the amount of approximately $33,000 be included in
the annual Current Budget for the City of Pickering commencing in 2002 and continuing
thereafter until the loan is repaid; .
c) The Director of Corporate Smrices and Treasurer certifies that this loan and the repayment
thereof falls within the City's Debt and Obligations approval Annual Repayment Limit for
debt and other financial obligations for 2001 as established by the Province for
municipalities in Ontario;
d) The Treasurer be authorized to take any actions necessary in order to effect the foregoing;
and,
5. The appropriate officials of the City of Pickering be given authority to give effect hereto.
ORlGlN:
2000 Capital Budget
-
AUTHORITY:
Municipal Act R.S.O. 1990, as amended
Conservation Authorities Act, R.S.O. 1990, as amended
Report to Council OES 021-01
Date: July 30, 2001
Subject: Tender T-6-2001 Petticoat Creek Pedestrian Bridge
Page 2
-
FINANCIAL IMPLICATIONS:
l.
Tendered Amount:
Construction $ 769,990.00
G.S.T. (7%) 53,899.30
Sub-Total $ 823,889.30
G.S.T. rebate (4%) (30,799.60)
Total $ 793,089.70
2.
Approved Source of Funds:
Prior Years: Budget $ 776,000.00
Debt Financing 488,000.00
Future Years: Budget unknown
Total Approved $1,264,000.00
3.
Estimated Project Costing Summary:
Construction $ 769,990.00
Consulting Fees (various) 76,999.00
Construction Supervision 40,000.00
Site PreparationlRestoration
,- by TRCA 30,000.00
Site Surveying by TRCA 10,000.00
Project Contingency 50.000.00
. Sub Total $ 976,989.00
G.S.T. 68,389.23
G.S.T. rebate (39,079.56)
Total Project Cost $1,006,298.67
4.
Project Costs (over) under Approved Funds $ 257,701.33
EXECUTIVE SUMMARY:
This project involves the construction of a fully accessible, six (6) span pedestrian bridge and
asphalt pathway across the mouth of the Petticoat Creek to unify Pickering's portion of the
Waterfront Trail. Due to the sensitive nature of the site, preliminary site preparation work and
final restoration planting will be carried out by the T.R.C.A. Construction of the bridge
substructure and superstructure and asphalt pathway works are to be completed under contract
T -6-2001.
-
The bridge and trail works are located on lands within the Petticoat Creek Conservation Area
which is owned and operated by the T.R.C.A. To facilitate construction of these works, a permit
was required under Regulation 158. Approval to construct was granted by the T.R.C.A.
Executive Committee at their meeting on July 27,2001.
The Region of Durham maintains an Easement Agreement on a portion of the lands located
within the project site. Permission was granted by the Region to allow construction access to the
Report to Council OES 021-01
Date: July 30, 2001
Subject: Tender T -6-2001 Petticoat Creek Pedestrian Bridge
Page 3
-
project site via the easement as required. A work permit from the Region is not required for this
project.
BACKGROUND:
The Petticoat Creek Pedestrian Bridge project has been identified as a critical link along
Pickering's Waterfront. The project is intended to provide recreation opportunities for Pickering
residents while creating a vital link along the Waterfront Trail between Pickering and Toronto.
The project is to be a landmark attraction that will serve to improve Pickering's recreational,
cultural, and tourism potential in an environmentally sensitive way.
A concept plan for the project was prepared by Victor Ford & Associates, with the detailed
design for the bridge structures prepared by Johnson Sustronk Weinstein + Associates (JSW+)
and J.T. Gregg Associates Ltd. The design development for this project was carried out in
consultation with the Waterfront Coordinating Committee, City of Pickering Peer Reviewer Mr.
Tom Clancy, and the T .R.C.A.
The T.R.C.A. and the City of Pickering are partners in the development of this project. The
T.R.C.A. is in the process of finalizing a Management Agreement with the City for the
maintenance and operation of the bridge and Waterfront Trail located on Conservation Authority
Lands (Council Resolution #139/99).
The project was open for tender on June 20, 2001, with a closing date of July 18, 2001. A
recommended pre-bid site meeting was held on July 9,2001, which was attended by fifteen (15)
potential bidders. The City received a total of eight (8) bids at the time of closing.
~-
Tender documents were review by the consulting team, which included Victor Ford &
Associates, JSW+, and J.T. GreggAssociates. Therecommendation from the consulting team is
to award the contract to the lowest bidder, King City Group Ltd., who has experience with the
construction of pedestrian bridges and boardwalks located in environmentally sensitive areas.
Treasurer's Comments:
Funds for this project have been accumulated from a number of Council approvals over a number
of years.
The 2000 Capital Budget contained a provision of $700,000 in funding for this project which
included the need for $488,000 of long. term financing, whether through the issuance of debt or
internal loans, to be repaid over 10 years, after the expenditures take place. The
Recommendations adopted by Council in connection with the 1999 Current and Capital Budgets
included the following:
"3a) internal debt financing be approved for the projects identified in the 2000 Capital
Budget in the amount of $175,000 for a period not to exceed 5 years; and
$3,005,188 for a period not exceeding 10 years;
b) projects identified in the (2000) Capital Budget as being financed through the
issuance of debt be subject to additional, specific approval by Council of the
expenditure and the financing before proceeding. "
-
While there remains $1,264,000 of unexpended expenditure approvals for the undertaking, the
Tender and other costs included in the report require only $1,006,298 of remaining financing
approvals. This is $257,701 less than that originally provided for, therefore the requirement for
debt financing has been reduced accordingly from $488,000 to $231,000.
Report to COllllCil OES 021~01
Date: July J~ 2001
Subject: Tender T -6-2001 Petticoat Creek Pedestrian Bridge
Page 4
,-
ATTACHMENTS:
1. Letter of Recommendation from Johnson Sustronk Weintstein & Associates (JSW+)
2. Location Map
Prepared By:
Approved / Endorsed By:
Approved / Endorsed By:
~~~~~
Gillis Paterson
Director, Corporate Services & Treasurer
JB:m1d
Attachments
Copy: Chief Administrative Officer
Director, Operations & Emergency Services
Director, Corporate Services & Treasurer
Division Head, Municipal Property & Engineering
-
Recommended for the consideration of Pickering
City Council
Thomas 1. Quinn, Chief Administrative Officer
-~
ATTACHMENT#L. TO REPORT # 0,;;./-0 I
Operations & EmergencY Services I
RECEIVED: JUI 2 7 1nm I
FILE NO.:
ABEY. TO: l,
FWD/COPY TO:
MAYOR COUIlKlt.L.... -
C.A.O. CLERK
CUL. 8. REC. FINANCE
MUN. PROP.&ENG. HUMAN RES-
FIRE SERVICES LEGAL
TRANSIT PLANNING
INFO. SYSTEMS CUST. CARE
LIBRARY ECON. DEV.
.18111+
.~
Johnson Sustronk Weinstein
+ Associates
Engineers
Landscape Architects
Planners
July 24, 2001
City of Pickering
Operations and Emergency Services Departments
Pickering Civic Complex
One The Esplanade
Pickering, Ontario
LIV 6K7
Attil: Mr. Everett Buntsma, Director
Re: Petticoat Creek Pedestrian Bridge
City Contract No. T-612001
Tender Review and Recommendation
Dear Sit:
Further to the receipt of eight tender submissions for the above noted project, we have carried
out a brief analysis of the low three tenders. They are as follows:
I. King City Group
2. Aecon Constnictionand Materials Ltd.
3. North American Construction Services
$ 823,889.00
$ 1,048,745.81
$ 1,068,181.00
We understand from our discussions with .your Department, that the City Solicitor has reviewed
the legalities of the Form of Tender submissions. Our review of the Schedule of Items and
Prices and the individual contractor references have discovered no inconsistencies or
irregularities in the bids as submitted.
-
JSW+ has worked with King City Group in the past on the installation of the Duffins Creek
Pedestrian Bridge. This project was carried out for the TRCA in conjunction with the City of
Pickering and the Town of Ajax. Based on that experience and our discussion with others
relative to King City Group's capabilities and their ability to carry out this type of project, we
recommend that the contract be offered to King City Group at the tender price noted above.
On this particular project we would further recommend that significant on-site inspection be
carried out to ensure that the City's environmental concerns and priorities are adequlltely
accommodated. Should you have any further questions please do not hesitate to contact me
directly.
Yours very truly,
GLH/slv
20 Mural Street. Unit 10 c.c.
Richmond Hili. Ontario
l4B 1 K3
Victor Ford (Victor Ford Associates)
Terry Gregg (J.T. Gregg Associates)
Jill Hone (City of Pickering . Purchasing)
Larry Field (fRCA)
Tom Clancy
Tel: (905) 889 - 8100
Fax: (905) 889 - 6616
-
ATTACHMENT # L TO REPORT # 0;2.1'" 0 (
-
I SANOK GR
VICKI
lJ][][]D
>- U
'"
::>
m
Ul
'"
~
<t
::;
-
l-
t/)
W
~
o
~ TULLO
'"
COWAN
ROAD
LAKE
ONTARIO
-
t
OPERA nONS AND EMERGENCY
SERVICES DEPAR1MENT
MUNICIPAL PROPERTY AND
ENGINEERING DIVISION
ATTACHMENT FOR OPERATIONS
& EMERGENCY SERVICES REPORT
LOCATION OF PETTICOAT CREEK PEDESTRIAN BRIDGE
~
SCAlf: 0iA.Tt:
1:10 000 JULY 3012001
L:\I.IP.t"E\TNCU4T1C UAPPJNC\~\SrREEr a..SE\OC4S DIRECTOR\ATTACHJJENT FOR REPDRT\