REPORT TO COUNCIL
FROM:
Gillis A. Paterson
Director of Finance & Treasurer
DATE: September 20, 1999
REPORT NUMBER: FIN24-99
SUBJECT:
Report on the Y2K preparedness of the Town of Pickering.
RECOMMENDA TION:
That Report FIN24/99 of the Director of Finance and Treasurer be received and that Council
approve the Y2K Contingency Plan as attached.
ORIGIN:
,A/IfOIo.
The Chief Administrative Officer appointed a Y2K Committee with the Manager of Information
Systems as the Chair. The Committee was charged with the responsibility of identifying all
Town computer and computerized systems, labeling the systems as being Y2K or non- Y2K
compliant, and upgrading the systems to Y2K compliancy if necessary. Funds were provided in
the 1999 Capital I3udgel for this purpose. In addition to equipment verification, the Y2K
Committee was also charged with the responsibility of ensuring departments reviewed and
vcrilicd thcir Y2K I3usincss Contingency Plans.
AUTHORITY:
Thomas J. Quinn, Chief Administrative Officer.
FINANCIAL IMPLICATIONS:
Council approved a budget of $179,000 (FIN02-99) to upgrade those computer and computerized
systems within the Town and Library that were identified as being not Y2K compliant. To date,
$127,095 has been expended on Y2K upgrades. Still to be charged is $41,980 for the Energy
Management System, and $6,046 to upgrade the Phoenix Gas Dispensing System at the Works
Centre. The total estimated Y2K costs will be $175,121, an estimated under expenditure of
$3,879. ^ portion ($1,900) of the under expenditure will be used to fund a linalmuiling to Town
residents in late October, outlining both the Town's and Region's Y2K status.
, "
"
.-
It should be noted the Vehicle Maintenance system in use at the Works Centre will not be
upgraded to Y2K compliancy, as the vendor has decided not to upgrade their sofiware, but to
replace it in its entirety. The cost of the replacement soHware is $12,500 (US). Until it has been
determined whether the Town financial systems will be replaced, and if so, if the replacement
systcm will contain a Vchiclc Maintenance modulc, the Works Centre will revert baek to using a
manual system. The Director of Parks and Facilities and staff of the Works Centre supports the
strategy. If a new linancial package did include a Vehicle Maintenance module, this would
ensure complete integration with the Inventory, Purchasing, and General Ledger systems.
Finally, the cost to upgrade the Civic Complex's Lighting system was not included in the Y2K
project. Any costs associated with upgrading the Lighting system will be identified within the
?OOO h",ln,,' or P".-I..., ",,,I r.",,;I;j;,,~
Reportlo Council flN24.99 Date: September 20, 1999
Subject: Report on the Y2K preparedness of the Town of Pickering. Page 2
-
EXECUTIVE SUMMARY:
The Y2K project within the Town has been a success, although the final analysis will not be
completc until January 2000. All identified systems Ilave been updated with the exception of
two. The update to the Energy Management System is complete but is still waiting for the final
sign-off, which will occur when the heating system is activated presumably later this year and a
full-load test can take place. The Phoenix Gas Dispensing system (for vehicles) upgrade is still
waiting for the release of the Y2K-compliant module. The latest release date estimate is the
month of October.
The only departments to identify critical supplies, other than computers and the like, were Parks
and Facilities, and Transit. Both identified fuel as being the only critical supply to their function.
To ensure fuel problems do not occur during the Millennium changeover, a memo was recently
sent to the following departments: Parks and Facilities, Transit, Public Works, fire, and Clerks.
The memo directed these departments to have all vehicle and power-generator fuel tanks filled
on December 31, and all fuel storage tanks filled the week of December 27. This action will
ensure vehicles will have fuel should there be a power outage and fuel is unable to be pumped
from fuel storage tanks.
The Region of Durham has assured the Town that they are reasonably confident that no major
services such as water, sewage, and traffic control will be interrupted. All major outside service
providers, such as Ontario Hydro, Pickering Hydro, and Bell Canada, have also provided the
same assurance.
,-1
It was the intent of the Town to contact all buildings with elevators and fire-detection systems, to
remind them to verify that their systems are Y2K compliant. This task was assigned to Fire
Inspection. The Fire Chief has assured the Y2K Chair that this is being undertaken.
Pickering residents have been notified of the Town's Y2K progress through the News Advertiser,
the Town's website, and an insert in the Town's final billing. A final notification by means of a
brochure will occur in late Octobcr. Thc brochure will include the Y2K status for both the Town
and the Region.
BACKGROUND:
Under the direction of the Chief Administrative Officer, the Town of Pickering created a Y2K
Committee during the latter part of 1998. The task of the Committee was to identify all
computer and computerized systems within the Town that would be afTected by the Y2K
changeover, and eithcr upgrade or replace the systems by June 1999. Departments were asked to
review their operations and report to the Committee by Decembcr 15, 1998, with any systems
that were not Y2K compliant.
I;,
The first report to Council (FIN02-99) was dated February 2, 1999. Attached to FIN02-99 was a
report entitled "Y2K Compliance Status." The submission identified which departments were
Y2K compliant, and which had systems that were not. The cost to replace the systems was
identified at $179,000. This amount was included and approved by Council in the 1999 Capital
Budget.
,-
The process of replacing the non-compliant systems began on February 22, 1999. The
Committee consisted of four staff members, which was later expanded to six by the Chief
Administrative Officer. Project schedules were developed with Committee mcmbers being
assigned responsibility for different systems. All systems that were feasible were completed on
timc. Somc systems were delayed due to outside suppliers or external factors, but all identiIied
systems are still planned to be upgraded before December 31, 1999.
Those departments that had originally identified non-compliant systems and devices were asked
to re-visit their operations to ensure that all such systems had been identified. To date, no new
systcms have been reported to the CommitLee. At the same time, those departments who utilize
Report to Council FIN24-99
Date: September 20, 1999
-
Subject: Report on the Y2K preparedness of the Town of Pickering.
Page 3
just before December 31, 1999. While problems are not expected, the Town is doing everything
possible to identify potential problems and take preventative action.
During the course of the project, the task of thc CommiUec cvolvcd to includc dcveloping
strategies to keep Town residents informed of Y2K developmcnts that might artcct thcm, along
with identifying all critical supplies and suppliers used by and within the Town, to ensure
continuance of business operations should Town suppliers suffer Y2K related difficulties.
Communication with Town residents has been very important to the success of the project. To
keep Town residents updated on Y2K-related events, the Town has used a variety of means,
including the electronic message display board, News Advertiser, website, and a brochure
included within the June tax billing. A final communique will be sent out in late October to all
residents of Pickering by means of Canada Post. During this time period, all other municipalities
will also be contacting their residents. Pickering will be participating in a regional blitz to ensure
all residents of the Region are notified as a whole. The communique will include both Regional
and Pickering related information. This is expected to be the last direct Y2K-releated
communication event, other than through the website.
Finally, the Committee requested all departments to identify those supplies ami suppliers that
were critical to their operations. On December 31, departments were asked to have a one-month
supply on-hand of those supplies that were deemed to be critical. The only critical supply
identified by some of the departments was fuel.
,...
A IT ACHMENTS:
Y2K Contingency Plan
Prepared By:
Approved / Endorsed By:
Gillis A. Paterson
, ~ .;-~._._. - --- --.--
~~~C~
Director of Finance and Treasurer
JGS:vw
Attachments
copy: Chief Administrative Officer
Department Heads
Y2K Committee
Recommended for the consideration of
Pickering Town Council
Thomas J. Ouinn, Chief Administrative Officer
."....
ATTACHMENT#-L. TO REPORT#[iN"c:.11"1Q
-
~1'1 OF PIC
';;OS\
X ~~~ z
~ ~
..
The Corporation of the Town of Pickering
Y2K Contingency Plan
IIFor Internal Staff Use"
September 9, 1999
-
-
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
1. PURPOSE:
The purpose of the plan is to assist Town staff in dealing with the Y2K millennium
changeover and outlines the two levels of Town response strategies. These levels are:
1. Part I - Normal Y2K Response
2. Part II - Full Scale Emergency Y2K Response
Based on current knowledge, we are not anticipating any significant inconveniences and
will therefore be implementing the "Normal Y2K Response." However, in the unlikely
event that an emergency should occur, the "Full Scale Emergency Y2K Response" will
be implemented.
It should be noted that it is not possible to be certain that all aspects of the Year 2000
issues affecting the Town, including those aspects relating to the efforts of third parties,
have been identified and fully resolved.
2. RESPONSIBILITIES:
~
Department heads and alternates will be available to assist the Town within their own
areas of expertise. The fan-out of the Municipal Control Group (MCG), if required for
full-scale emergency response, would be activated through Fire Dispatch according to
the Priority Notification Lists (fan-out) contained in the Town of Pickering Nuclear
Emergency Plans.
3. IMPLEMENTATION:
Notification I Activation:
Relevant Town staff and MCG members, if required, will be available to co-ordinate
duties within their areas of responsibility during the millennium changeover as follows:
Part I - Normal Y2K Response: Certain Town staff will be on duty on December 31,
1999, and January 1, 2000, as outlined on Page 2. The MCG will also be "On Call"
during the millennium changeover.
Part II - Full Scale Emerqencv Response: The MCG members will be contacted as
outlined on Page 4. The emergency response plan will be activated through Fire
Dispatch according to the Priority Notification Lists (fan-out) contained in the Town of
Pickering Nuclear Emergency Plan.
A telephone contact list has been prepared for internal use only. Please refer to page 6.
-
Page 1 of 6
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
PART 1- NORMAL Y2K RESPONSE
A) Expectations:
Minor inconvenience to the Town, Town residents, businesses, and institutions.
B) Response Level:
The Town will maintain a "Normal" response level with a few additional staff available to
assist if required.
C) Functions:
The Town will conduct business as usual with Customer Care and support staff
available during the millennium changeover to address public questions and concerns.
Those staff are:
I. Customer Care and Information / Customer Relations Clerk support staff will be
on duty in the Civic Complex:
-
a) from 6:00 p.m. December 31, 1999, to 1 :00 a.m. on January 1, 2000. The Civic
Complex will not be open for walk-in traffic.
b) from 8:30 a.m. to 4:30 p.m. on January 1, 2000, to take calls from the
general public. The Civic Complex will not be open for walk-in traffic.
Staffing requirements and/or the extension of these operating times could be
changed at the discretion of the CAO or the Manager of Customer Care. (The
option of staffing the Civic Compiex was chosen as being the most practical of all
options considered.)
II. Parks and Roads staff will be liOn Call" for their normal storm duty.
III. Information Systems staff will be on duty after 10:00 a.m. on January 1, 2000, as
long as necessary, to ensure computer changes and upgrades were successful.
IV. Transportation: The Manager of Transportation will respond with staff and vehicles
if an emergency response is required.
-
Page 2 of 6
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
V. Fire Department staff will monitor the Y2K changeover as it happens from 6:00 p.m.
December 31. 1999, to 1:00 a.m. on January 1, 2000. Fire Dispatch will provide a
Y2K status update to Customer Care (420-4666) staff each hour during that period.
The Fire Dispatcher will immediately notify the Fire Chief (who would evaluate the
situation) regarding any serious concerns that may affect the Town.
VI. All Municipal Control Group (MCG) staff will be "On Call" for immediate response
in the event the full-scale emergency plan is activated. MCG staff will provide Fire
Dispatch with phone numbers where they can be reached during the period from
6:00 p.m. December 31, 1999, to 1:00 a.m. on January 1, 2000. These response
times may be extended at the discretion of the CAO or designate.
VII. All Fire Department staff will exercise their normal duty shifts with capabilities of
providing additional immediate emergency response if required. The extension of
their response level is at the discretion of the Fire Chief and using normal
emergency response procedures.
,,,....
VIII. Parks and Facilities staff will perform security inspection checks at all urban Town
facilities, including libraries, between the hours of 10:00 p.m. on December 31,
1999, and 1 :00 a.m. January 1, 2000. Facilities located in the northern rural areas
will not be checked due to the diminished probability of vandalism. Doors will be
checked for proper closure and locking, and a visual inspection will be undertaken
for unwanted or suspicious activities. At least one complete inspection be
performed after midnight and all inspections will be logged. The police will be
advised of the Town inspection program.
,...
Page 3 of 6
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
PART II - FULL SCALE EMERGENCY Y2K RESPONSE
A) Expectations:
That a major or significant emergency will affect the Town, Town residents, businesses,
and institutions. This event will not likely be the result of disruption to local services but
rather as a result of the loss of essential services provided by others. If this happens,
the Town would provide support to the Region of Durham and others through the
activation of the MOC (Municipal Operations Centre), located in Claremont Community
Centre.
Essential services include water, power, telecommunications, and sewage treatment. A
loss or disruption to one or more of these services would likely trigger a Full Scale
Emergency Y2K Response.
B) Response Level:
A partial or full activation of the Town's MOC will be undertaken at the discretion of the
CAO in consultation with the Fire Chief and Mayor.
C) Activation Procedures:
-
The Municipal Control Group (MCG) will be "On Call" during the millennium changeover
ready to fully activate the Municipal Operations Centre if necessary. This plan will be
activated through the Priority Notification Lists (fan-out) contained in the Town of
Pickering Nuclear Emergency Plans.
D) Functions:
All MCG staff listed in the Glossary of Terms will be contacted through the normal fan-
out. If required, they will be notified by Fire Dispatch to report to and open the MOC and
activate the Town of Pickering Emergency Measures Plan or Nuclear Emergency Plan.
Emergency response will include:
. Providing support to Durham Emergency Measures Office (DEMO) or the
Region.
. Responding appropriately to the level of the emergency that exists at any time.
. Attending a debriefing session to be held as soon as reasonably possible upon
the deactivation of any emergency response.
.",...
Page 4 of 6
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
Glossary of Terms:
1. The Municipal Control Group (MCG):
Municipal Control Group (MCG) is made up of senior Town staff that includes the
Mayor, CAO (Operations Officer), Fire Chief (Emergency Co-ordinator) and certain
designated department heads.
External MCG members include Pickering Hydro, Police, and Ambulance. They
would be notified under the Priority Notification Lists (fan-out).
2. The Municipal Operations Centre (MOC):
The Municipal Operations Centre (MOC) is located in the Claremont Community
Centre to co-ordinate emergency response activities in the Town through the MCG.
3. Levels of Full Scale Emergency Response: (Provincial standards)
-
3.1 Routine Monitoring (On Call): When MCG Staff are "On Call", their
whereabouts is required in the event of an emergency during the critical period.
MCG staff will provide dispatch with a phone number where they can be reached.
Further notification of MCG staff will be made through the Fire Dispatcher in the
event the emergency is upgraded.
3.2 Enhanced Monitoring: The Emergency Co-ordinator, CAO, and Mayor will
monitor the situation from the Municipal Operations Centre. Alternates will be
called to relieve for additional shifts if required.
3.3 Partial Activation: All emergency MCG personnel placed "On Standby" will
report to the Municipal Operations Centre to monitor / assess the situation and
await further direction from the CAO.
3.4 Full Activation: Emergency plans are fully activated with the MaC operating and
fully staffed by the MCG 24 hours per day.
.,...
Page 5 of 6
The Corporation of the Town of Pickering
Y2K Contingency Plan
-
Y2K INFORMATION CONTACT LIST
,..
COMPANY/ORGANIZATION TELEPHONE NUMBER
BELL CANADA - Y2K HELP DESK 1-877 -678-1265
CONSUMERS/ENBRIDGE GAS 1-800-265-6164
DURHAM EMERGENCY MEASURES OFFICE (DEMO) 905-431-6000 u(24 hour)
DEMO (DUTY OFFICER) 905-430-1638
DURHAM REGION HEAL TH UNIT 1-905-723-8521
DURHAM REGION POLICE SERVICES 905-683-9100
EMERGENCY MEASURES ONTARIO (EMO) 416-314-0451 (D. Banke)
GO TRANSIT 416-869-3200
ONTARIO HYDRO - Y2K HOTLINE 1-800-400-1921 or
839-11 51 Ext. 4409
PICKERING HYDRO 905-427 -0791
PICKERING WORKS EMERGENCY - 24 HRS. 905-683-4319
REGION OF DURHAM - Y2K INFORMATION 905-666-8913
1-877-641-9813
REGION WORKS EMERGENCY (AFTER HRS.) 905-576-9991
REGION WORKS EMERGENCY 905-683-1471
AJAX DEPOT (7:30 A.M. - 3:30 P.M. )
TOWN OF PICKERING WEB SITE www.town.oickering.on.ca
NOTES
1. The Town is working closely with the Region of Durham, other municipalities, and
agencies to ensure there is little or no interruption to essential services.
2. Information on the Town's Y2K progress was included with the June interim tax bills
sent to all residents/taxpayers.
3. Residents requesting information concerning banking, use of Automatic Teller
Machines (A TM), automotive fuel, etc. should contact these institutions/companies.
4. Questions regarding resident concerns of additional food supplies, travel etc.
(suggest residents use their own discretion.)
5. Other areas of concern should be directed to Betty O'Brien (Ext. 2173) for response.
-
Page 6 of 6