HomeMy WebLinkAboutOES 34-05PICKERING
REPORT TO
COUNCIL
Report Number: OES 34-05
Date: September 8, 2005
From:
Richard Holborn, P. Eng.
Division Head
Municipal Property & Engineering
Subject:
Tender No. T-12-2005 - Tender for Concrete Sidewalk Installations -
Various Locations
Recommendation:
That Report OES 34-05 regarding Concrete Sidewalk Installations - Various
Locations be received; and that
Tender No. T-12-2005 submitted by Trisan Construction for Concrete Sidewalk
Installations - Various Locations in the amount of $116,740.32 (G.S.T. included)
be accepted; and that
o
The total gross project cost of $139,100 and a net project cost of $130,000,
including the tender amount and other project costs identified in this report be
approved; and that
The amount of $106,196 for Central Street, Valley Farm Road and Westney
Road be funded by a combination of transfer from the Easement Settlement
Reserve and Property Taxes, and the amount of $23,804 for Finch Avenue to be
funded by a transfer from Development Charges Reserve Fund and the City's
Share - DC Reserve as provided for in the 2005 Capital Budget and that the
remaining fund of $39,000 from the Property Taxes be carried over to address
any future needs, be approved; and that
The appropriate City of Pickering officials be authorized to take necessary action
to bring effect thereto.
Executive Summary: As part of the 2005 Sidewalk Capital Budget, concrete
sidewalk installations for Central Street, Valley Farm Road and Westney Road were
identified as construction projects. As part of the External Subdivision Budget a
concrete sidewalk installation was identified for Finch Avenue. Tender T-12-2005 was
issued on August 5, 2005 for all four projects and closed on August 31, 2005 with eight
bidders responding. The total gross project cost is estimated to be $139,100 for an
estimated net cost to the City of $130,000 (net of G.S.T. rebate). Staff have been
directed to report to Council on the results of the tender and financing in order to
proceed with this project in a timely manner.
Report OES 34-05
Subject: Tender T-12-2005
Tender for Concrete Sidewalk Installations
Date:
September 8, 2005
Page 2
Financial Implications:
1.
TENDERED AMOUNT
T- 12-2005
G.S.T.
Sub-Total
G.S.T. Rebate
Total
$109,103.10
7,637.22
116,740.32
(7,637.22)
$109,103.10
APPROVED SOURCE OF FUNDS
2005 Sidewalk Capital Budget 2323-6108
6005
& 2005
External Subdivision Budget 2321-
Location
Central Street/
Valley Farm
Road/
Westney Road
Finch Avenue
Project Code
05-2323-001-02
05-2321-002-22
Source of Funds
Easement Settlement
Reserve
Property Taxes
Development Charges
Reserve Fund
City Share - DC Reserve
Available Required
75,000
100,000
175,000
11,700
35,100
46,800
106,196
23,804
FUNDS AVAILABLE 221,800 $130,000
Report OES 34-05
Subject: Tender T-12-2005
Tender for Concrete Sidewalk Installations
Date:
September 8, 2005
Page 3
ESTIMATED PROJECT COSTING SUMMARY
T-12-2005 -Concrete Sidewalk Installations for
Central Street
Valley Farm Road
Westney Road
Finch Avenue
Sub-Total
Associated Costs
Materials Testing
Utility Relocations
Miscellaneous Costs
Project Contingency
Total
G.S.T.
Total Gross Project Cost
G.S.T. Rebate
Total Net Project Cost
$36,533
28,614
23,913
20,044
$109,103
2,500
5,000
2,397
11,000
130,000
9,100
139,100
(9,100)
$130,000
Project Cost under (over) Approved Funds $91,800
The Director, Corporate Services & Treasurer has reviewed the budgetary implications
and the financing of the expenditures contained in this report and concurs. The Director
also states that as these projects are now estimated to cost less, the draws from the
Reserve and Reserve Funds will not be as much as estimated in the 2005 Capital
Budget. Therefore, the funds will not be drawn and will remain in the Reserve Fund.
However, in anticipation of future sidewalk capital requirements, it is recommended that
the excess funding to come from Property Tax Levy in the amount of $39,000 be held for
this purpose. The $39,000 represents the percentage of funds required against funds
available, which is sixty-one percent. The remaining $29,250 from the Easement
Settlement Reserve will be returned to that account.
Report OES 34-05
Subject: Tender %12-2005
Tender for Concrete Sidewalk Installations
Date:
September 8, 2005
Page 4
Background:
Bids for Tender No T-12-2005 were received on Wednesday, August 31,2005. Eight (8)
companies submitted a bid at the time of closing. The references for the Iow bidder,
Trisan Construction, have been checked, and are deemed acceptable by the
Supervisor, Engineering & Capital Works. The Health & Safety Policy and the Cost &
Frequency Report issued by Workplace Safety & Insurance Board, as submitted by
Trisan Construction, have been reviewed by the Safety & Training Coordinator and are
deemed acceptable. Credit information as provided by D & B for Trisan Construction is
not available and therefore a credit risk analysis can not be undertaken by staff. In
conjunction with staff's review of reference information and the bonding available on this
project, is deemed acceptable.
Upon careful examination of all tenders, and relevant documents received, the
Operations & Emergency Services Department, Municipal Property & Engineering
Division recommends the acceptance of the Iow bid submitted by Trisan Construction
for Tender No. T-12-2005 in the amount of $116,740.32 (G.S.T. included) and that the
total net project cost of $130,000 be approved.
The approved 2005 Sidewalk Capital Budget is $175,000, however this tender
represents expenditures of only $106,196 from this account for three sidewalk projects.
Due to the time of year, staff recommend that the balance of funds, estimated at
$39,000 be carried over to address future sidewalk construction needs.
This report has been prepared in conjunction with the Manager of Supply & Services
who concurs with the foregoing.
Attachments:
Location Map
Record of Tenders Opened and Checked
Supply & Services Memorandum
Report OES 34-05
Subject: Tender T-12-2005
Tender for Concrete Sidewalk Installations
Date:
September 8, 2005
Page 5
Prepared By:
Da~B~ Sel~'ky ~/
Supervisor, Engineering & Capital Works
Approved / Endorsed By:
Everett Buntsma
Director, Operations & Emergency Services
Vera A. Felgemacher
Manager, Supply & Services
'---Gilli's A. Paterson
Director, Corporate Services & Treasurer
Ric~:d'W. Hol~(~rn, P. Eng.
D~ision Head, Municipal Property & Engineering
DS:ko
Attachments
Copy: Chief Administrative Officer
Recommended for the consideration of
T,l~r~s O. O~n,~ef ~ ini~rative O~er
~.~', ;M)-~P1ENT~__i~ ..... TOREPORT# 0E ~
MUNICIPAL PROPERTY & ENGINEERING
Attachment For Tender T-12-2005
VALLEY FARM ROAD / WESTNEY ROAD / CENTRAL STREET /
FINCH AVENUE - SIDEWALKS
PARKDALE J L STREET
CRT
VALLEY FARM ROAD
GREENWOOD ~o
SIXTH · CONCESSION
[] UBJECT
ROAD
WESTNEY ROAD
h lAttachments for Tenderst2OO5t T- 12-2005 - Vadous Sidewalks. doc
I ~ ~ ~ ~C ~ ~ ~ ~] ~ ........ TO P, EPOR,T# 0~..~
CLAREMONT
ACORN
JOSEPH
WELUNGTON
CENTRAL STREET
FINCH AVENUE
PROPOSED CONSTRUCTION INCLUDES:
Sidewalk Construction
Valley Farm Road - Construction of a concrete sidewalk (west side)
Westney Road - Construction of a concrete sidewalk (west side)
Central Street - Construction of a concrete sidewalk (north side)
Finch Avenue - Construction of a concrete sidewalk (south side)
I:lAttachments for Tenders~OO5~ T-12-2005 - Vadous Sidewalks. doc
-..,_. ,-,-~ = a"
· '-'" '~
.5'
..~ ~~-,
>
t-
CORPORATE SERVICES DEPARTMENT
MEMORANDUM
August 31,2005
To:
From:
Subject:
Richard Holborn
Division Head
Municipal Property & Engineering
Darrell Selsky
Supervisor, Engineering & Capital Works
Barbara Tran
Buyer
Tender for Concrete Sidewalk Installations - Various locations
Tender No. T-12-2005
Closing: Wednesday, August 31,2005
Tenders have been received for the above project. Ten (10) companies were
invited to participate. An advertisement was placed in the Daily Commercial
News, News Advertiser Community Page and on the City's Website all of which
yielded interest from additional bidders. Ten (10) bidders picked up tendering
documents for a non-refundable fee of $35.00 per set of which eight (8)
responded. A copy of the Record of Tenders Opened and Checked used at the
public tender opening is attached. Tenders shall be irrevocable for 60 days after
the official closing date and time.
Purchasing Procedure No. PUR 010-001, Item 10.03 (r) provides checking
tendered unit prices and extensions; unit prices shall govern and extensions will
be corrected accordingly, which has been done.
All deposits other than the Iow three bidders may be returned to the applicable
bidders as provided for by Purchasing Procedure No. PUR 010-001, Item
10.03(w). Therefore, the tenders of the Iow three (3) bidders are attached for
review.
A Dun & Bradstreet report for Trisan Construction will be requested of the
Purchasing Analyst and a summary will be provided to you during the evaluation
phase of this tender call.
Richard Holborn
Darrell Selsky
August 31, 2005
Page 2
Summary
(PST included, GST included)
Company Total Tendered After Calculation'
Amount $ Check $
Trisan Construction 116,740.32 116,740.32
Royalcrest Paving & Contracting Ltd. 118,463.18 118,345/47
Aloia Bros. Concrete Contractors Ltd. 143,009.78 143,009.78
Slip-Form Construction 144,316.25 143,674.25
Lincoln Paving Contracting Ltd. 147,472.75 147,472.75
Pencon Construction Canada Corp. 158,333.25 158,333.25
Miwel Construction 165,799.11 165,577.90
NuRoad Construction Rejected: Bid bond insufficient.
Reference: lB 18, 19, TS 3.
PUR 010-001, 10.04 Item 9 (d)
D. Crupi & Sons UNABLE TO BID
Pursuant to Information to Bidders Item 2t, the following are being requested of
the Iow bidder for your review during the evaluation stage of this tender call:
(a) a copy of the Health and Safety Policy to be used on this project;
(b) a copy of the current Cost and Frequency Report issued by Workplace
Safety & Insurance Board (in lieu of the Cost and Frequency document, a
copy of the current CAD 7, NEER, or MAP reports may be submitted);
(c) a copy of the current Certificate of Clearance issued by Workplace Safety &
Insurance Board;
(d) the City's certificate of insurance shall be completed by the bidder's agent, broker
or insurer.
Please review the copies of the bids. Include the following items in your Report
to Council:
(a) if items (a) through (c) noted above, are acceptable to the Safety & Training
Co-ordinator;
(b) any past work experience Trisan Construction including work location;
(c) without past work experience, if reference information is acceptable;
(d) the appropriate account number(s) to which this work is to be charged;
(e) the budget amount(s) assigned thereto;
(f) Treasurer's confirmation of funding;
(g) related departmental approvals;
(h) any reason(s) why the Iow bid of Trisan Construction is not acceptable; and
(i) related comments specificto the project.
If you require further information, please feel ,f~me~
Barbara Tran
/bt
Attachments
COpy for: Director, Operations & Emergency Services