Report to
Council
Report Number: ENG 13-26
Date: July 23, 2026
From: Richard Holborn
Director, Engineering Services
Subject:
Engineering Consulting Services for Detailed Design of Michell Bridge Replacement Project
File: A-1440
Recommendation:
1. That Report ENG 13-26 regarding the Detailed Design of Michell Bridge Replacement
Project be received;
2. That the proposal submitted by Keystone Bridge Management Inc. in response to Request
for Proposal No. RFP 2026-7 Consulting Services for Michell Bridge Replacement, in the
amount of $220,615.55 (HST included) or $198,671.14 (net HST) be accepted;
3. That the total gross project cost of $276,578.00 (HST included), including the proposal fee
amount, a contingency, and other associated costs, and the total net project cost of
$249,067.00 (net of HST) be approved;
4. That Council authorize the Director, Finance & Treasurer to finance the net project cost of
$249,067.00 (net HST) by a transfer from the OCIF Fund as approved in the 2025 Capital
Budget;
5. That the Director, Engineering Services be authorized to enter into and execute the Form of
Agreement with the above-mentioned consultant pursuant to Request for Proposal No.
RFP 2026-7; and,
6. That the appropriate officials of the City of Pickering be authorized to take the actions
necessary to implement the recommendations in this report.
1.0 Executive Summary:
The purpose of this report is to obtain Council’s authorization to retain Keystone Bridge
Management Inc. to complete the detailed design and prepare the tender documentation
needed to replace the Michell Bridge (Bridge ID #7001) over Reesor Creek on Seventh
Concession Road.
ENG 13-26 July 23, 2026
Page 2
In 2024, the City of Pickering hired the consulting firm of Keystone Bridge Management Corp.
to conduct the biennial bridge and large culverts inspections including Michell Bridge. The
inspection concluded that the bridge is beyond repair and should be replaced soon.
The City also retained AECOM in 2023 to conduct a detailed structural evaluation and
condition survey of Michell Bridge to explore alternatives for both replacement and
rehabilitation. Based on the structural evaluation, and the guidelines set forth in the MTO
Structural Manual (2021) and Ontario Ministry of Transportation (MTO) Structural
Rehabilitation Manual (2007), AECOM recommended that the bridge be replaced with a new
structure. A load limit of 25 tonne was proposed for the bridge, and a load limit by-law was
passed in 2025.
Request for Proposals No. RFP2026-7 was posted on the City’s bids&tenders portal on May 4,
2026, and closed on June 4, 2026, for a competitive bidding process to select a qualified
consultant to complete the detailed design and prepare the tender documents required to
replace the Michell Bridge. The Evaluation Committee reviewed and evaluated four (4)
proposals received using the criteria outlined in the bid document. The top ranked proposal
submitted by Keystone Bridge Management Inc. in the amount of $220,615.55 (HST included)
or $198,671.14 (net HST) is recommended for approval. It is also recommended that the total
gross project cost of $276,578.00 (HST included) which includes the proposal fee amount, a
contingency and other associated costs, and the total net project cost of $249,067.00 (net
HST) be approved.
2.0 Relationship to the Pickering Strategic Plan:
The recommendations in this report respond to the Pickering Strategic Plan Priorities of
Advance Innovation & Responsible Planning to Support a Connected, Well-Serviced
Community, and Lead & Advocate for Environmental Stewardship, Innovation & Resiliency.
3.0 Financial Implications:
1. RFP Amount
RFP2026-7 $120,040.00
Provisional Item - MCEA Schedule B
HST (13%)
75,195.00
25,380.55
Total Gross RFP Amount $220,615.55
HST Rebate (11.24%) (21,944.41)
Total Net RFP Amount $198,671.14
ENG 13-26 July 23, 2026
Page 3
2. Estimated Project Cost Summary
RFP 2026-7 $120,040.00
Provisional Item MCEA Schedule B Fee 75,195.00
Contingency (10%) 19,524.00
Toronto and Region Conservation Authority Permit Approval and
Review Cost
30,000.00
Sub Total – Costs $244,759.00
HST (13%) 31,818.67
Total Gross Project Cost $276,577.67
HST Rebate (11.24%) (27,510.91)
Total Net Project Cost $249,066.76
3. Approved Source of Funds
Approved Capital
Account
Source of Funds Approved Budget Funds Required
C10570.1804
OCIF Grant $400,000.00 $249,067.00
RF – Roads and
Bridges Debt
Financing – 20 years
$312,374.24
$850,000.00
0.00
0.00
$1,562,374.24 $249,067.00
Net Project Cost Under (Over) Approved Funds $1,313,307.24
Note: The proposal includes a provisional item in the amount of $75,195.00 (HST excluded)
should a Municipal Class Environmental Assessment Schedule B be deemed required to
complete the design of the bridge replacement. The OCIF grant will fund the current
expenditure of $249,066.76.
4.0 Discussion:
The purpose of this report is to obtain Council’s authorization to hire Keystone Bridge
Management Inc. to complete the detailed design and prepare the tender documentation
ENG 13-26 July 23, 2026
Page 4
needed to replace the Michell Bridge (Bridge ID #7001) over Reesor Creek on Seventh
Concession Road.
The City conducts biennial bridge and large culvert inspections to determine the maintenance
and capital needs of the City’s bridge and large culvert assets with a span of 3m or more. This
work generally involves a qualified engineering consulting company providing detailed visual
inspection of each structure and individual inspection reports for each structure. In 2024, the
engineering consulting company Keystone Bridge Management Corp. completed the full bridge
inspection service for 29 bridges and 26 large culverts in the City.
The Municipal Bridge and Culvert Inspection Report completed by Keystone identified Michell
Bridge as a priority bridge in need of immediate replacement. Their report indicates that the
condition of railings, surcharge on the deck, and the exterior condition is driving the need for
the replacement. Michell Bridge is located on Seventh Concession Road crossing over Reesor
Creek and is approximately 70 years old. In October 2025, the bridge was damaged as the
result of a motor vehicle collision and the south railing was detached. A temporary barrier has
been installed for safety reasons.
In 2023, the City retained AECOM to conduct a structural evaluation and detailed condition
survey of the existing Michell Bridge over Reesor Creek to explore alternatives for both
replacement and rehabilitation. Following a comprehensive life cycle cost analysis of all
feasible options, AECOM recommended, based on structural evaluations, and the guidelines
set forth in the MTO Structural Manual (2021) and Ontario Ministry of Transportation (MTO)
Structural Rehabilitation Manual (2007), that the bridge be replaced with a new structure. The
existing bridge has reached the end of its service life, and further rehabilitation to extend its
use is not a financially or structurally viable option in alignment with the Keystone
recommendations. A load limit of 25 tonne was proposed for the bridge, and a load limit by-law
was passed in 2025.
Request for Proposal RFP2026-7 for Consulting Services for the replacement of Michell Bridge
was posted on the City’s bids&tenders portal on May 4, 2026 and closed on June 4, 2026, and
the City received submission from four consulting firms. The proposals were evaluated by the
Evaluation Committee consisting of two staff members from the Traffic and Transportation
section of the Engineering Services Department and one staff member from the City
Infrastructure Department. The proposals were evaluated based on the consultant’s
qualification and experience working on similar projects, their understanding of the objectives
and requirements of the project, proposed workplan to deliver the project in a timely manner,
and proposed price. The top ranked proposal was submitted by Keystone Bridge Management
Inc.
The top ranked proposal submitted by Keystone Bridge Management Inc. in the amount of
$220,615.55 (HST included) or $198,671.14 (net HST) is recommended for approval. It is also
ENG 13-26 July 23, 2026
Page 5
recommended that the total gross project cost of $276,578.00 (HST included) which includes
the proposal fee amount, a contingency and other associated costs, and the total net project
cost of $249,067.00 (net HST) be approved.
Attachment:
1. Location Map
Prepared By: Ridhita Ghose, P.Eng., Transportation Engineer
Nadeem Zahoor, M.Eng. P.Eng., Manager, Transportation and
Traffic
Approved/Endorsed By: Cathy Bazinet, Manager, Procurement and Finance
Stan Karwowski, Director, Finance & Treasurer
Approved/Endorsed By: Richard Holborn, P.Eng., Director, Engineering Services
NZ:nz
Recommended for the consideration of Pickering City Council By:
Marisa Carpino, M.A.
Chief Administrative Officer
Atttachment 1 - Report ENG 13-26