At the January 27th, 2014 Council meeting, staff were requested to review the report
from the Town of Ajax with respect to the Class Environmental Assessment to address
the Outfall Capacity Limitations at the Duffin Creek Water Pollution Control Plant.
1. Corr. 04-14 Council Direction Required
Nicole Wellsbury
Manager of Legislative Services/Deputy Clerk
Town of Ajax
65 Harwood Avenue South
Ajax, ON L1 S 2H9
Correspondence received from Nicole Wellsbury, Manager of Legislative
Services/Deputy Clerk, Town of Ajax with respect to the Duffin Creek Water Pollution
Control Plant Outfall EA.
IV) Confirmation By-law
V) Adjournment
•
Accessible
PI C K E IIN G For information related to accessibility requirements please contact
Linda Roberts
Phone: 905.420.4660 extension 2928
TTY: 905.420.1739
Email: Iroberts(a�citvofpickerina.com
A Town of TOWN OF AJAX
65 Harwood Avenue South
Ajax ON L1 S 2H9
YaX
y the Lake vwvw.ajax.ca
City of Pickering Clerk's Office
ATTN: Debbie Shields, City Clerk
dshields @pickering.ca
February 11, 2014
Re: Town of Ajax Resolution RE: Duffin Creek Water Pollution Control Plant Outfall
Environmental Assessment—Part II Order Request
Please be advised that the following resolution was passed by Ajax Town Council at its Meeting
held Monday February 10, 2014:
1. That the staff report entitled "Duffin Creek Water Pollution Control Plant Outfall
Environmental Assessment-Part II Order Request" dated February 10, 2014, be
endorsed;
2. That Council re-affirm its direction that a Part II Order Request incorporating the results
of technical reviews conducted by the Town's experts be prepared by outside counsel in
conjunction with staff and submitted to the Minister of the Environment, and to the
Councils of Durham Region and York Region, by February 18, 2014;
3. That the Part II Order Request ask the Minister to direct the Regions to reimburse the
Town for the cost of external legal counsel and consulting experts' field work and peer
reviews to date, which demonstrate the fundamental deficiencies in the Outfall EA and
the need for an Individual Environmental Assessment, together with such ongoing
funding as may be necessary to secure the Town's participation in the Individual
Environmental Assessment;
4. That this report and the Part II Order Request and expert reports be made available to
the public by posting on the Town's website,following submission to the Minister; and,
5. That this report be sent to the Ontario Minister of the Environment, the Councils of
Durham Region and York Region, the City of Pickering and other lakefront communities
in Durham Region, the Stakeholder Advisory Committee, Pickering-Ajax Citizens
Together—Protecting Our Water(PACT POW), Ajax Environmental Advisory Committee,
the Environment Commissioner of Ontario, the Great Lakes and St. Lawrence Cities
Initiative, the Regional Works Commissioners of Ontario, the Ontario Water Works
Research Consortium, the Centre of Excellence for Great Lakes and Human Health, the
Executive Committees and Source Protection Committees of the Toronto and Region
Conservation Authority and the Central Lake Ontario Conservation Authority,
Conservation Ontario, the Council of Canadians, EcoJustice, Lake Ontario Waterkeeper,
Environmental Defense, Chris Alexander MP (Ajax-Pickering), Joe Dickson MPP (Ajax-
Pickering), Tracey MacCharles MPP (Pickering-Scarborough East) and other interested
parties.
Ontario's First ISO 9001 Quality Community
•
A copy of the staff report that prompted this action is attached. If you require any additional
information, please do not hesitate to contact the author of the staff report, Barb Hodgins, at
905-619-2529 ext 3247 or barb.hodgins(c�aiax.ca
Sincerely,
. 0,(a(44//.
Nicole Wellsbury
Manager of Legislative Services/Deputy Clerk
Copy: Leona Barrington, Government Relations Advisor,Town of Ajax
Barb Hodgins, Senior Policy Planner, Town of Ajax
•
Town of
TOWN OF AJAX ax
REPORT By the Lake
REPORT TO: Council
SUBMITTED BY: Paul Allore, MCIP, RPP
Director of Planning and Development Services
PREPARED BY: Barbara Hodgins, MCIP, RPP
Senior Policy Planner
SUBJECT: Duffin Creek Water Pollution Control Plant Outfall Environmental
Assessment— Part II Order Request
WARD(S): All
DATE OF MEETING: February 10, 2014
REFERENCE: Staff Reports: General Government Committee - May 5 & November
24, 2011; November 8, 2012; April 4 & May 23, 2013; Community
Affairs & Planning Committee—June 18, 2012; Council—October 22,
2012 &April 8, 2013
Community Action Plan: Leader in Environmental Sustainability
RECOMMENDATIONS:
1. That the staff report entitled "Duffin Creek Water Pollution Control Plant Outfall
Environmental Assessment-Part II Order Request" dated February 10, 2014, be
endorsed;
2. That Council re-affirm its direction that a Part II Order Request incorporating the
results of technical reviews conducted by the Town's experts be prepared by
outside counsel in conjunction with staff and submitted to the Minister of the
Environment, and to the Councils of Durham Region and York Region, by February
18, 2014;
3. That the Part II Order Request ask the Minister to direct the Regions to reimburse
the Town for the cost of external legal counsel and consulting experts' field work
and peer reviews to date, which demonstrate the fundamental deficiencies in the
Outfall EA and the need for an Individual Environmental Assessment, together with
such ongoing funding' as may be necessary to secure the Town's participation in
the Individual Environmental Assessment;
4. That this report and the Part II Order Request and expert reports be made available
to the public by posting on the Town's website, following submission to the
Minister; and,
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 12
Assessment—Part II Order Request
5. That this report be sent to the Ontario Minister of the Environment, the Councils of
Durham Region and York Region, the City of Pickering and other lakefront
communities in Durham Region, the Stakeholder Advisory Committee, Pickering-
Ajax Citizens Together—Protecting Our Water (PACT POW), Ajax Environmental
Advisory Committee, the Environment Commissioner of Ontario, the Great Lakes
and St. Lawrence Cities Initiative, the Regional Works Commissioners of Ontario,
the Ontario Water Works Research Consortium, the Centre of Excellence for Great
Lakes and Human Health, the Executive Committees and Source Protection
Committees of the Toronto and Region Conservation Authority and the Central
Lake Ontario Conservation Authority, Conservation Ontario, the Council of
Canadians, EcoJustice, Lake Ontario Waterkeeper, Environmental Defense, Chris
Alexander MP (Ajax-Pickering), Joe Dickson MPP (Ajax-Pickering), Tracey
MacCharles MPP (Pickering-Scarborough East) and other interested parties.
BACKGROUND:
a) Overview
The Regions of Durham and York(the Regions) have published an Environmental Study Report
(ESR) in relation to the outfall for the Duffin Creek Water Pollution Control Plant (WPCP), which
is available for public comment until February 18, 2014. The ESR documents the findings of the
Regions' Schedule C Municipal Class Environmental Assessment (Class EA) process,' and
presents the Regions' preferred alternative for addressing the limitations of the existing outfall.
The outfall is a 1 km long pipe that extends from the WPCP into the nearshore of Lake Ontario,
discharging sewage effluent into the lake through a series of 38 diffuser ports.2 The Regions
propose to install rubber "duck billed"3 valves on the end of these diffuser ports, which will
discharge effluent with greater velocity, but do nothing to remove phosphorus from the effluent.
This report presents a summary of the key findings of a team of experts hired by the Town to
investigate the causes and impacts of nuisance algae growth in the Ajax nearshore, and to
undertake a peer review of key technical issues raised by the Regions' Outfall EA.
As set out in detail below, these experts have concluded that effluent discharged from the
WPCP creates a plume of phosphorus-enriched water directly over top of prime algae habitat(a
nearshore zone where there is sufficient light, the right water temperature and the right lake-
bottom conditions to grow algae).
In short, phosphorus from the WPCP is over-fertilizing the nearshore water of Lake Ontario,
causing a proliferation of nuisance algae to grow, and resulting in a series of unacceptable
environmental impacts including interference with spawning by native fish species, and the
potential destruction of fish habitat. During the summer, the algae breaks off from the lake
bottom, drifts to shore, and rots. The algae itself washes in to shore in clumps, or gets blended
up into a 'soup', which keeps children from playing and swimming in nearshore water.
'Schedule'C'Municipal Class Environmental Assessment to Address Outfall Capacity Limitations at the Duffin Creek
WPCP(Outfall EA).
2 There are 63 diffuser ports in total on the existing outfall,only 38 of which are presently in use.
3 Or"variable port check valves".
•
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 13
Assessment—Part II Order Request
The severe odour caused by rotting algae interferes with residents' reasonable enjoyment of
their properties, forcing them indoors and behind closed windows during the hottest months of
the summer. The "nauseating", "sewage-like" odour of rotting algae prevents Ajax families from
enjoying the recreational trails, beaches and waterfront lands that Ajax has worked so hard to
assemble and protect for public use.
These nuisance impacts are unacceptable and preventable. Cost-effective technology is
available — and is in use at other similarly-sized sewage treatment plants today — to remove
phosphorus (including up to 99% of the phosphorus that feeds algae growth - soluble reactive
phosphorus or SRP). The Regions' preferred alternative, however, does not result in a
decrease in phosphorus discharges by the WPCP to the Ajax nearshore. On the contrary, when
the WPCP increases the current volume of effluent from 360 million litres per day (360 MLD) to
630 MLD, the Regions preferred alternative would allow phosphorus discharges to nearly triple,
to 113 tonnes/year.
The Regions' Outfall EA is fundamentally deficient because it fails to acknowledge the role of
the WPCP, which supplies approximately 97% of the SRP loading to the Ajax nearshore, in
causing nuisance algae growth. As a result, the ESR fails to examine the environmental
impacts of nuisance algae growth on fish, fish habitat, water quality and on the lives of Ajax
residents. In turn, the ESR fails to identify and assess alternatives based on their ability to
remove phosphorus from WPCP effluent and to mitigate existing adverse environmental effects
caused by the growth of nuisance algae.
The Environmental Assessment(EA) process is intended to identify, mitigate or prevent adverse
environmental impacts, and the Class EA process in particular is to be used for projects with
minor, predictable environmental impacts that can be mitigated.
The Regions' preferred alternative will not result in minor environmental impacts but will
exacerbate the already significant adverse environmental effects caused by SRP in WPCP
effluent. The Regions must be required to implement an alternative that will mitigate or prevent
the adverse environmental impacts presently caused by the SRP in the effluent, rather than an
alternative that will make the impacts worse.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 14
Assessment—Part II Order Request
Based on the Town's experts' findings and conclusions, staff recommend that the Part II Order
Request prepared at Council's direction, incorporating the results of the Town's expert and legal
review, be submitted to the Minister of the Environment and to the Regions by February 18,
2014.
b) Duffin Creek Water Pollution Control Plant
The WPCP is located immediately adjacent to and west of the Town of Ajax, in the City of
Pickering, at the Lake Ontario shore. It has been co-owned and operated by the Regions since
1997.
The WPCP is presently the second largest sewage treatment plant in Ontario. It has been
operating for more than 30 years, and its capacity has been expanded twice, to an approved
maximum of 630 million litres per day (MLD). Effluent flows presently average 360 MLD. The
WPCP releases sewage effluent into the nearshore water of Lake Ontario, just 1 km from the
Ajax waterfront.
Since at least 2005, the Town of Ajax has raised concerns with the Regions and the Ministry of
the Environment (MOE) regarding the adverse environmental impacts of effluent from the
WPCP.
c) Town's First Part II Order(Bump Up) Request
The most recent expansion in capacity from 420 to 630 MLD (Stage 3) was designed to treat
increasing sewage flows from growing communities, primarily located in York Region, and the
expanding York-Durham Sewage System (YDSS or "Big Pipe"). A Class EA process was
undertaken for the Stage 3 expansion in 2004/2005.
Within the context of the Class EA process for the Stage 3 expansion, the Town expressed
concerns to the Regions about nutrients in WPCP effluent exacerbating nuisance algae growth,
and impairing nearshore water quality. The Town did not feel that the impact of the then-current
WPCP effluent discharge, or the proposed increase to 630 MLD, had been adequately studied,
or that appropriate controls were in place to prevent a further deterioration of water quality.
The Town participated in the Class EA process, and communicated its concerns to the Regions
repeatedly, through staff reports, letters and in-person meetings with Region staff and
consultants. Unfortunately, the Town's concerns were not addressed in the Regions' ESR.
Accordingly, in 2006 the Town retained a team of peer review experts and external legal
counsel, David Estrin, Senior Environmental Law Specialist from Gowling Lafleur Henderson
LLP. Mr. Estrin conveyed the results of the Town's peer review to the Regions and to the
Minister of the Environment, and requested that the Class EA be "bumped up" to an Individual
Environmental Assessment, with the goal of avoiding further deterioration of nearshore water
quality4.
In response to the concern expressed by the Town and other stakeholders, the Minister of the
Environment imposed a series of conditions on the Stage 3 expansion.5 The Regions were
required to monitor odour from the WPCP, and prohibited from operating the WPCP at flows
above 520 MLD until a solution for the limitations of the outfall had been identified and
implemented.
4 http://www.ajax.ca/en/doingbusinessinaiax/resources/odeng d revisedoartiiorderreauest.odf
5 http://www.aiax.ca/en/doingbusinessinaiax/resources/DuffinCreekWPCP-MOEDecision-Reaions032107.odf
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 15
Assessment—Part I I Order Request
It is this condition that led the Regions to commence the Outfall EA in December 2010.
d) Independent Peer Review By Dr.Auer
In 2010, just before the Outfall EA commenced, the Regions, the Town and Ontario Power
Generation jointly funded an independent peer review report of available local water quality
studies and data by Dr. Martin Auer of Michigan Technological University.
Dr. Auer's draft peer review report was circulated in the fall,of 2010 and in final form in July
2011. Dr. Auer concluded that the WPCP is overwhelmingly the largest source of SRP and total
phosphorus (TP) to the Ajax nearshore and is therefore the appropriate management focus with
respect to nuisance algae growth. Yet Dr. Auer's findings have not informed the Regions' ESR
or the Outfall EA, which ignores the role of the WPCP in causing nuisance algae growth in the
Ajax nearshore.
DISCUSSION:
a) Outfall EA
The Regions published the Notice of Completion for the Outfall EA on November 19, 2013, and
released the ESR for public comment until February 18, 2014.6 The Town has participated
actively throughout the Outfall EA, as a member of the Stakeholder Advisory Committee (SAC)
and by directly communicating its concerns to the Regions.
To date, neither the Town's concerns, nor Dr. Auer's 2011 findings, have been appropriately
addressed. As a result, for a second time, the Town was required to retain a team of.experts
and external legal counsel to identify fundamental gaps in the Regions' ESR, and to examine
cost-effective and commercially available solutions to remove phosphorus (including SRP) from
WPCP effluent and improve water quality in the Ajax nearshore. As in 2006, the Town retained
David Estrin, Senior Environmental Law Specialist from Gowling Lafleur Henderson LLP.
The Town's team of experts includes:
• Dr. Martin T. Auer, Professor of Civil and Environmental Engineering at Michigan
Technological University, specializing in surface water quality engineering and the study of
algae, with assistance from the Upstate Freshwater Institute in Syracuse, New York;
• Dr. Karl Schiefer, Senior Consultant and Aquatic Toxicologist, specializing in the assessment
of impacts to fish and fish habitat; with assistance from Carri-Lyn Epp, Fisheries Ecologist
with EcoMetrix,
• Dr. Tony van der Vooren, P.Eng., Senior Environmental Consultant with AMEC Americas
Limited, specializing in air quality and odour monitoring and evaluation;
• Dr. Bill Oldham, P.Eng.(BC), President of Oldham Environmental Engineering Ltd., and
Professor Emeritus in the Department of Civil Engineering at the University of British
Columbia, specialist in wastewater management, water treatment and water quality studies;
and
• Al Shpyth, Senior Environmental Specialist with Ecometrix, specializing in environmental
policy and economics.
6 The ESR is available at the Town Hall, Main Public Library and www.durham.ca/outfallea.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 16
Assessment—Part II Order Request
The field studies and peer review conclusions of the Town's experts are summarized below.
b) Summary Of Field Work And Peer Review Team Findings
i) Field Studies of Phosphorus and Cladophora in Lake Ontario along the Ajax,
Ontario Waterfront, and Environmental Study Report Review, by Dr. Martin T. Auer
submitted to the Town of Ajax, January 23, 2014:
Given his extensive knowledge gained through decades of scientific, peer-reviewed research
about attached algae in the Great Lakes, with particular attention to Cladophora, Dr. Auer was
asked to assess whether the phosphorus discharged to the Ajax nearshore from the WPCP is
causing or contributing to the nuisance algae problem occurring along the Ajax waterfront. His
assessment is as follows.
Cladophora requires,four conditions to grow: the right water temperature, sufficient light,
suitable substrate, and a source of food (specifically SRP). In Lake Ontario, optimal water
temperatures generally occur from late-May through mid-June. During the summer of 2013,
field work was completed to examine the availability of light, substrate and phosphorus within
the Ajax nearshore.
•
Sonar surveys of the lake bottom and measurements of the underwater light field, indicate that
wide band stretching along the Ajax nearshore where
there is an approximately 1 kilometre g 9 1
pP Y
sufficient light and substrate exist to support Cladophora growth (the "Cladophora Habitat
Zone"). Underwater video surveys of the Ajax nearshore confirmed the extensive presence of
Cladophora, often covering 100% of the lake bottom, throughout the Cladophora Habitat Zone.
The existence of habitat alone, however, will not create a nuisance algae problem. Algae can
be present without causing nuisance conditions. The difference between areas that merely
have algae present, and areas experiencing nuisance conditions, is how much plant material is
produced during the growing season (or how"productive"the system is).
How much plant material grows in a given area is controlled by how much SRP is made
available to the algae.
To characterize how much SRP is being made available to the algae within the Cladophora
Habitat Zone, the effluent plume from the Outfall was investigated and sampled on two
occasions. The highest SRP concentrations were found immediately adjacent to the Outfall.
Dramatically elevated levels of SRP were observed throughout the Cladophora Habitat Zone,
including levels high enough to achieve maximum Cladophora growth rates.
Currents within the Ajax nearshore have the potential to spread this SRP-enriched plume to the
east and west of the Outfall, across the Cladophora Habitat Zone. Refer to Figure 1.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 17
Assessment—Part II Order Request
v.7.,- �* A ¢ i�
Y � � - S f"Y'' 'GA4-l,, �
1r SRP
• 3 4 ' "a• 1 ." w' 14, ' ' • ' L_1 U
nimpede
d
f r`'' 1 ' �� e r A
' t , " n. ' ' - Stimulated
4a '1 '.
� ' 3� c
• ;; 4- . *
Saturated
1 .
� t„ f r , .. ,.e.-ii;;, - " ,.07.. ■:;;_i- , ..; ,-,, r, .....,.,. ,'4::'46 r 1 T'�i' ' ,fi
,
,
0
k. =.%� I
J Spidat limit of plume survey -, .
20
30
30
• we `` e V
i .` o.F �,' _2't-r:' 0 °''4;)",, 1• w� fib 5 .-...<.r . �at#;`� t jf ft -Y i% o-."l
i ,Wfi'-..s.. ? Y.�Y" E-r �ZkC�1'''..a dam'. -it.. ."..' e.`� 3rPR_4.._.� ��d�E _� � 7
Figure 1: The position of the Duffin Creek WPCP effluent plume (red and pink) on 8/9/2013
overlain on the Cladophora Habitat Zone (green) at Ajax, Ontario. The yellow triangle points to
the location of the Duffin Creek WPCP outfall.
In order to confirm that it is the SRP from the Outfall that is stimulating overproduction of algae
in the Ajax nearshore, samples of algae tissue were taken at various locations across the
nearshore and analyzed for phosphorus content. The highest tissue phosphorus concentrations
were observed in the immediate vicinity of the Outfall, with levels decreasing with distance away
from the Outfall.
In other words, the very highest growth rates of algae were found closest to the Outfall, with
decreasing rates of growth found at increasing distance away from the Outfall.
Based on the results of these field investigations and analysis, Dr. Auer has concluded that
there is no doubt that the SRP in the effluent being discharged to Lake Ontario from the WPCP
is the primary contributor to nuisance conditions of Cladophora growth at Ajax.
The WPCP is slated to substantially increase the amount of phosphorus (including SRP) that it
discharges to Lake Ontario. The impact of this increase, absent a reduction in effluent
phosphorus concentrations and/or relocation of the outfall, will be greater stimulation of
Cladophora growth and exacerbation of the nuisance algae problem (increased amounts of
algae over a larger area).
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 18
Assessment—Part II Order Request
ii) Review—Class Environmental Assessment to Address Outfall Capacity Limitations
at the Duffin Creek Water Pollution Control Plant, by Dr. Martin T. Auer submitted
to the Town of Ajax, January 23, 2014:
In addition to the field investigation of the Ajax nearshore discussed above, Dr. Auer was also
asked to review Chapter 5 of the Regions' ESR which addresses nuisance growth of algae in
the Ajax nearshore. Dr. Auer was specifically asked to determine if the high concentrations of
phosphorus observed along the Ajax waterfront associated with the discharge from the WPCP
were acknowledged in the ESR to be a cause of the nuisance growth of Cladophora and related
water quality degradation and odour impacts being experienced by Ajax residents.
In Dr. Auer's opinion, the ESR fails to acknowledge that the WPCP plays a significant role in
stimulating nuisance growth of Cladophora. Rather, the ESR asserts that the primary drivers of
such nuisance growth are rising water temperatures associated with a global climate change
and the ecosystem engineering activities of invasive mussels.
Having reviewed the reasoning provided for these assertions, Dr. Auer has concluded that:
1) There is no basis in the scientific literature to assert, let alone conclude, that rising lake
temperatures are a primary cause of nuisance Cladophora growth in Lake Ontario; and
2) Based on studies by other scientists as well as Dr. Auer's own studies and field work,
invasive mussels (which transform phosphorus into a form useable by algae) could not cause
the nuisance algae conditions found along the Ajax shoreline in the absence of the very large
quantities of phosphorus being discharged in the WPCP effluent.
Furthermore, Dr. Auer is of the view that the ESR inappropriately focuses on peripheral issues,
to the exclusion of the WPCP, which supplies 97% of the SRP delivered during the months
when Cladophora grows and which delivers that load directly over prime habitat for colonization
by attached algae.
Dr. Auer also found that the ESR leaves the reader with the sense that reducing phosphorous
discharges would require technologies and supporting science beyond that presently available.
Dr. Auer indicates that this is far from the truth, as the required treatment technologies are now
widely applied across Canada and the US.
In addition to these primary deficiencies, Dr. Auer has identified a host of further incorrect or
misleading statements within the ESR relating to the causes of nuisance algae growth in Lake
Ontario and the options that should have been identified as readily available to address this
problem.
iii) Odour and Shoreline Algae Report, prepared by AMEC Americas Limited, January
13, 2014, with an appended August 2013 Odour Study:
In August 2013, given his decades of experience assessing and mitigating odour sources, plus
his ongoing review of the Regions' odour modeling and monitoring work for the expanded
WPCP on the Town's behalf, AMEC was retained to conduct ambient odour sampling at various
locations along the Ajax waterfront in response to numerous complaints received from residents
throughout the Summer of 2013 about offensive, sewage-like odours.
9 9
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 19
Assessment—Part II Order Request
Dr. Tony van der Vooren, P. Eng., Manager, Air Quality analyzed-the results of this sampling,
which indicate that the strong "sewage-like" odours measured along the Ajax shoreline were 30
to 60 odour units (1 odour unit being where 50% of average persons would detect the odour).
In Dr. van der Vooren's opinion, such levels could:
• Lead to odour complaints;
• Prevent the use of Ajax's beaches and shorelines for extended recreational uses;
• Inhibit the use of Ajax's beaches and shorelines for transitory activities such as walking,
rollerblading and cycling; and,
• Impact the enjoyment of nearby residents when using outdoor portions of their property
and cause them to keep windows closed and stay inside.
AMEC's testing further confirmed that these sewage-like odours were emanating from the
lakeshore/lake, and not the WPCP facility. These odours were consistent with the descriptions
provided by Ajax residents logging public complaints.
In addition to the above-noted testing, Dr. van der Vooren also reviewed the ESR and
concluded that:
1. The Regions have not completed any studies in respect of algae-related odour impacts,
despite their acknowledgment that algae is a major contributor to shoreline odour;
2. The ESR fails to assess any causal connection between phosphorus discharges from the
WPCP (including SRP) and the nuisance growth of algae; and,
3. The ESR provides no evaluation of wastewater treatment technologies that could reduce
phosphorus in discharged effluent for the purpose of mitigating algae growth and decay in
the Ajax nearshore and thus reduce the odour impact from decaying algae along the Ajax
shoreline.
iv) Literature Review and Field Investigations of Round Whitefish Habitat Along the
North Shore of Lake Ontario, prepared for the Town of Ajax by EcoMetrix
Incorporated, January 16, 2014:
EcoMetrix Incorporated was retained in 2013 by the Town to assess the potential for
Cladophora to be adversely impacting habitat for Round Whitefish in the vicinity of the WPCP's
existing outfall and the Ajax waterfront. Round Whitefish is an important and useful indicator
species for fish community health in the Ajax nearshore area. EcoMetrix was also asked to
review the ESR for the Outfall EA.
EcoMetrix undertook a literature review, which included reviewing draft and final Outfall EA
reports prepared for the Regions and numerous reports available in relation to the Pickering
Nuclear Generating Station (NGS) and the Darlington NGS. In EAs conducted for the Pickering
and Darlington NGSs (the Pickering NGS study area included the Ajax waterfront), Round
Whitefish was identified as a Valued Ecosystem Component because they are a benthic
(bottom-dwelling) native coldwater species that relies on the nearshore area to feed and spawn.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 110
Assessment—Part II Order Request
Also, EcoMetrix experts conducted fieldwork in Lake Ontario within the WPCP's existing outfall
area and across the Ajax nearshore area, and at a reference area in Georgian Bay.
The results of Ecometrix's literature review, field studies, and ESR review indicate that:
1. Round Whitefish typically spawn over coarse substrates in early December in nearshore
areas along the north shore of western/central Lake Ontario. Rocky substrates of the
nearshore areas along the north central shore of Lake Ontario, including the Ajax nearshore
and the Outfall EA study area, have been documented to be spawning/nursery areas for
Round Whitefish, and as such, the condition of this habitat is likely key to this species;
2. A comparison of substrate information collected in 2013 to historical information for the area
east of the Pickering NGS showed a significant change in substrate type. In 1981, the
substrates east of the Pickering NGS were predominantly comprised of bedrock, with
boulders and some cobble over top. In 2013, little to no visible hard substrate was observed.
Instead, Cladophora algal mats covered essentially all hard substrates west and east of the
existing outfall;
gx.iiiint-7 A,
Figure 2: Round Whitefish Spawning Substrate at 5 metres depth in Lake Huron (Left) and Ajax
nearshore (Right)
3. The potential effects of this heavy Cladophora growth on Round Whitefish spawning habitat
include avoidance of the habitat, increased egg exposure and predation, and increased
mortality of over-wintering eggs. Cladophora-related changes to the nearshore habitat
observed in 2013 indicate that the spawning habitat of Round Whitefish may have already
become permanently altered such that the ability of whitefish to use this area to carry out one
or more of their life processes has been diminished; and,
4. None of the Outfall EA documents or the ESR address the potential for significant adverse
effects on Round Whitefish spawning habitat. In addition, the reports did not contain current
information on Round Whitefish habitat, current use of the habitat by Round Whitefish, or any
data on the reproductive success of Round Whitefish within the study area. As the WPCP is
a contributor of nutrients to the nearshore of Lake Ontario including the Ajax waterfront, and
the effects of excessive nutrients promote excessive algae growth, the effects of Cladophora
on Round Whitefish habitat must be considered as part of the Outfall EA.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 111
Assessment—Part I I Order Request
v) Removal of Soluble Reactive Phosphorus from Sewage Effluent at Duffin Creek
WPCP,prepared by Oldham Environmental Engineering Ltd., January 2014:
Dr. Bill Oldham, P.Eng.(BC) of Oldham Environmental Engineering Ltd. was retained by the
Town in 2013 and was asked to consider:
• What technologies are commercially available to remove phosphorus and, in particular SRP,
from WPCP effluent?
• What concentration of SRP is achievable using these technologies and what would be the
approximate cost of employing these technologies at the WPCP?
• How does this cost compare to the cost of the alternatives evaluated as part of the Outfall EA
and if SRP removal had been considered as one of the criteria for evaluation within the
Outfall EA, how would the existing alternatives rank in relation thereto?
Based on Dr. Oldham's decades of experience, a tour of the WPCP and a review of data
obtained from the WPCP plant staff, Dr. Oldham concluded as follows:
1. The WPCP is a conventional secondary treatment plant that incorporates chemical
phosphorus removal. Based on the first 6 months of 2013, plant effluent contained
approximately 0.3 mg/L of total phosphorus (TP), and about 0.2 mg/L of SRP on average.
These average concentrations equate to estimated loadings of 110 kilograms per day (kg/d)
of TP and 72 kg/d of SRP at the current average effluent flow of 360 MLD;
2. There are multiple commercially proven phosphorus removal technologies that are capable
of achieving dramatically better effluent quality than that which is currently being achieved at
the WPCP. The addition of ballasted flocculation (one form of which is known as "Actiflo") to
the WPCP processes could potentially reduce TP and SRP concentrations in plant effluent to
as low as 0.008 mg/L and 0.003 mg/L, respectively. This would constitute an elimination of
approximately 97% of TP mass and 99% of SRP mass that would otherwise be discharged to
r when the WPCP fully utilizes its 630 MLD capacity;
the Ajax nearshore y
3. Implementing Actiflo at the WPCP is cost effective in comparison to the other solutions
considered by the Regions. The estimated lifecycle cost of using Actiflo at the WPCP is
approximately $118 million. For comparison, the Regions' estimated lifecycle cost of
membrane filtration in the ESR is more than twice as much ($243 million), and the
construction of a new, longer outfall was almost twice as much at$229 million;
4. Assuming that SRP is a more useful effluent parameter than TP in achieving improved Ajax
nearshore water quality, ballasted flocculation should have been considered as a treatment
option in the ESR. As the estimated lifecycle cost of implementing ballasted flocculation is
far less than many of the other alternatives considered in the ESR, it is apparent that the
ESR did not fairly or fully evaluate the potential benefits of this treatment technology; and,
5. The Regions' current preferred ESR alternative, the duck-billed discharge orifices, will not
reduce TP or SRP lake loadings at all. In fact, the net result of the Regions' preferred
alternative will be an increase of TP entering the Ajax nearshore environment of some 30
tonnes per year by the time effluent flows reach 630 MLD.
•
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental P a g e 1 12
Assessment—Part II Order Request
FINANCIAL IMPLICATIONS:
Early in the Outfall EA process, the Town spent approximately $65,000 for preliminary
consulting expertise, particularly reviewing the Regions' lake water modelling.
In April 2013, Council endorsed a phased strategy for the remainder of the Outfall EA, with
supportive funding (which was revised in June and October 2013) to hire external legal counsel
and expert consultants to undertake fieldwork and review the ESR.
Based on invoices received at this time, approximately $594,000 of the $798,000 funding
amount approved by Council for the first and second phase work has been invoiced, leaving
approximately 25% ($204,000) to pay for any outstanding invoices and to complete the
remaining second phase work, which include: the submission of a Part II Order Request; and
follow-up meetings with the Regions and the MOE, if required.
To recover these costs, staff recommend that the Part II Order Request ask the Minister to
direct the Regions to reimburse the Town for the cost of external legal counsel and consulting
experts' field work and peer reviews to date, which demonstrate the fundamental deficiencies in
EA and the need for an Individual Environmental Assessment, to
the Outfall E together with such 9
ongoing funding as may be necessary to secure the Town's participation in the Individual EA.
COMMUNICATION ISSUES:
Under the Ontario Environmental Assessment Act, any persons and parties with unresolved
concerns regarding the preferred solution selected through the Regions' Outfall EA may submit
Part II Order Requests, in writing, directly to the Minister of the Environment
(minister.moe @ontario.ca) until the close of business on February 18`", 2014.
Part II Order Requests or comments should be copied to the Regions, as proponents, at the
Regional Municipality of Durham, 605 Rossland Road East, Whitby ON L1 N 6A3, Regional
Municipality of York, 17250 Yonge Street, Newmarket ON L3Y 6Z1 and may be copied to the
Town of Ajax, 65 Harwood Avenue South,Ajax ON L1 S 2H9.
CONCLUSIONS
Notwithstanding the previous peer review, the concerns that have been raised by stakeholders
and by the Town since at least 2005, and the work done by Dr. Auer for the Regions, the Town
and the TRCA in 2011, the Regions' ESR refuses to acknowledge any causal connection
between phosphorus in the WPCP's effluent (including SRP), and the proliferation of nuisance
algae in the Ajax nearshore. As a result, the ESR fails to study the environmental, social and
economic impacts of nuisance algae, and fails to identify and evaluate alternatives based on
their ability to remove phosphorus, including SRP, from WPCP effluent. On the contrary, the
Regions' preferred alternative will allow phosphorus discharges to nearly triple — to 113 tonnes
per year. This is unacceptable.
The Town's experts carried out an extensive fieldwork program in 2013 and have demonstrated
that phosphorus from the WPCP, and in particular SRP, is causing the proliferation of nuisance
algae in the Ajax nearshore. The Regions must be required to remove phosphorus from WPCP
effluent, in particular SRP, and to mitigate or prevent the adverse impacts caused by nuisance
algae fed by WPCP effluent.
Subject: Completion of the Duffin Creek Water Pollution Control Plant Outfall Environmental Page 1 13
Assessment—Part I I Order Request
The Town's field studies and peer review demonstrate that the Regions' Class EA unreasonably
ignored and refused to scientifically investigate the connection between then nuisance
conditions along the Ajax nearshore and excessive SRP discharges from the WPCP. The
Regions' Class EA is fundamentally deficient and fails to comply with the Environmental
Assessment Act. The Regions must be required to:
• comprehensively examine the environmental, social and economic effects of nuisance
algae caused by phosphorus in WPCP effluent, and in particular SRP, through an
Individual EA;
• undertake a meaningful study of technologies that can remove phosphorus from effluent,
in particular SRP, cost-effectively and within the existing footprint of the WPCP, such as
Actiflo (or"ballasted flocculation"); and,
• the preferred alternative must, at a minimum, mitigate or prevent the adverse impacts
caused by the phosphorus, in particular SRP, presently discharged in WPCP effluent.
Staff recommend that Council re-affirm its direction that a Part II Order Request incorporating
the results of technical reviews conducted by the Town's experts as summarized above be
prepared by outside counsel in conjunction with staff and submitted to the Minister of the
Environment, and to the Councils of Durham Region and York Region by February 18, 2014.
Also, staff recommend that the Part II Order Request and expert reports be made available to
the public by posting on the Town's website, following submission to the Minister of the
Environment.
Barbara Hodgins, MCIP, RPP Kevin Heritage, MCIP, RPP
Senior Policy Planner Policy Planning Coordinator
Gary Muller, MCIP, RPP Paul Allore, MCIP, RPP
Manager of Planning Director of Planning and Development Services